Professional Documents
Culture Documents
FOR
NUMALIGARH REFINERY EXPANSION
PROJECT
1.1 Background
The crude oil for the design of new refinery train will be high sulphur Arabmix
crude. MS & HSD produced from the new train shall meet the BS-VI specification.
The project has been named as Numaligarh Refinery Expansion Project (NREP).
With this intent NRL appointed EIL to prepare a Feasibility Study Report (FR) with
cost estimate of +/- 30% for the revised configuration for 6 MMTPA expansion for
Project
1.2 Objective & Basis of selected Configuration for feasibility study report
1.2.1 Objectives
The major objectives of the study for Refinery capacity expansion are:
Maximization of HSD & MS production, MS and HSD from new train shall comply to
BS-VI grade requirements
Complying to overall SOx emission limit for the refinery and meeting other pollution
control norms.
1.2.2 Basis
The basis of study in line with the objectives have been detailed out as follows:-
6 MMTPA of crude.
Crude Mix
Following additional stream from existing refinery will also be fed to new expansion
refinery for product upgradation.
Crude assay : The crude assay followed are attached as attachment I and II in the
design basis.
Crude Pipeline : Imported crude will be received through a cross country pipeline from
Paradip port .
Crude Storage: The new crude being high sulphur has dedicated storage within
refinery. Three tanks of 35,500 M3 will be located at Numaligarh refinery site. Balance
storage will be provided at Paradip port.
Product Pipeline: A new multiproduct pipeline to transport products from the refinery
is envisaged.
For white oils (MS/HSD/SKO/ATF): presently, the white oils are dispatched by both
road and rail loading facilities from existing dispatch facilities at Numaligarh and
Siliguri.
In addition to rail and road loading, one 16” cross country pipeline from Numaligarh to
Siliguri owned by Oil India Limited (OIL) is used for handling MS/HSD/SKO with 1.721
MMTPA capacity.
Products Storage: As the expansion refinery will be processing high sulphur crude
independent intermediate product storages have to be considered. However for final
product storage integration with existing facilities is to be considered for optimisation.
Utilities: The utility system requirement for new train shall be independent of existing
refinery. Steam demand in the new refinery shall be met from new Utility Boilers. For
meeting the refinery steam requirements at different levels, new STG shall be
provided. The incidental power generated through new STGs shall be utilised for
power requirement of the complex. Balance power required shall be made available
from the grid for the new refinery operation.
Raw Water: Additional water requirement will be available from river Dhansiri.
Natural Gas: 2.3 MMSCMD of Natural gas will be made available for the new refinery
and the same is envisaged as fuel for utility boiler and process units, as required.
In case higher quantity of natural gas is required, the same shall be made available by
NRL.
1.3 Refinery Configuration
Further to the feasibility study carried out by EIL in Feb, 2015, NRL has identified the below
mentioned additional options for evaluation for which a configuration study has been carried
out by EIL.
From the outcome of configuration study result, NRL selected the configuration of
“Residue Upgrading Facility (approx. 70 % conversion) with integrated VGO HDT-PFCCU
(LPG/Propylene Maximization Case) / FCC Gasoline treatment Unit)” with the objective to
produce petrochemicals in future, with the use of robust technology.
As part of expansion project, MS, HSD & LPG shall be the main products from the new
refinery NRL may go for petrochemical production (Polypropylene). Also the PFCC unit
shall be capable of producing high yield of propylene in future.
Primary processing
Treating Facilities
Secondary Processing
Auxiliary Units
- SRU/SWS/ARU/TGTU
- Straight run LPG treating Unit (Comprising RUF and Straight run LPG treating
Unit)
- Incidental power from new STGs and balance power required from grid.
The unit capacities for the new train for the design crude mix are summarised in table
1.2 below.
Proposed Capacity
Process Units
(MMTPA)
Crude& Vacuum Distillation Unit (CDU/VDU) 6.0
Naphtha Hydro-treater 1.2
Reformer Unit 0.75
Isomerisation Unit 0.49
PFCC Unit 1.95
FCC Gasoline Hydro-Treater 0.58
Diesel Hydro-treater 3.55
Hydrogen Plant 95 (KTPA)
Residue Up-gradation Facility (Ebulated Bed 2.0
Resid Hydrocracker)
Sulphur Recovery Unit (SRU) 2 x 230 (MT/Day)
As integration with existing units has not been considered, none of the existing units
required revamp except coker unit. Existing Coker unit shall need to be revamped from 0.3
to about 0.55 MMTPA with feed integration with RUF bottoms of new refinery. The revamp
of Coker unit is not the part of this expansion project.
1.4.2 Product Slate
The estimated product slate of the expansion project for the design crude mix is
summarised in table 1.3 below. The graphical representation for both the case are also
given below in fig 1.1
Table 1.3 Product Slate
Propylene
LPG Minimization Case Maximization Case
Feed Purchase
(MMTPA) (Future Case) (Note-2)
(MMTPA)
Arab Light 1.8 1.8
Arab Heavy 4.2 4.2
Natural Gas 0.494 0.477
VR of existing refinery VDU 0.306 0.306
Coker Light and Heavy
Naphtha from existing 0.045 0.045
refinery DCU
HCGO from existing
0.109 0.109
refinery DCU
Product Sales (MMTPA)
Note-1: LPG demand from Expansion Refinery to be limited to 500 KTPA. Excess of LPG
Produced, if any, to be used as feed to new HGU.
Note-2: The refinery may operate with high propylene yield in future to produce
polypropylene.
LPG MIN CASE PRODUCT YIELDS (%)
Figure 1.1: Graphical Representation for Product Yields for LPG Minimization Case
Figure 1.2: Graphical representation for product yields for Propylene maximization
Case (Future Case)
Template No. 5-0000-0001-T2 Rev. 1 Copyright ElL- All rights reserved
1.4.3 Utility System Capacities
The estimated capacities and configuration of the utility facilities required to be installed for
the additional train are summarized in table 1.4 below
Sr
Utility System Capacity
No.
Note-1 : Raw water intake requirement finalized based on water balance across total
refinery complex(3 MMTPA + 6 MMTPA). For details of water balance, refer ‘Environment
Impact Assessment’ report for the expansion project.
1. Philosophy for storage of crude: 21 days storage for crude is considered. Three
tanks of 40500 m3 nominal capacity to be installed at refinery. Balance 8 Nos. storage
tanks are considered at Dhamra port.
2. Philosophy for storage of final products: For finished products, total production
from existing 3 MMTPA Refinery as well as from upcoming new 6 MMTPA refinery has
been considered. Excess capacity in existing product tankages as well as Re allocation
of existing tanks service (for e.g. MS to HSD, etc.) in consultation with NRL have also
been considered for the expansion refinery. 10 days storage for all finished products
3. Philosophy for storage of intermediate products: 8 days storage for VGO & VR is
considered. Bottoms of RUF unit is stored in existing tanks No. 45-TT-CR-107A/B,41-
TT-CR-108 A/B and one new storage tank shall be provided catering to total 8.5 days
of storage. All other intermediate products storage is considered for 3 days.
The details of offsite storage facilities required to be installed for the new refinery for
crude, products and intermediate products are summarized in table 1.5 below.
6 (Mounded
9 LPG Storage Bullets) 90 (L) X8 (D)
(Note-1)
Sr Products to be
Facilities Required Location
No. dispatched
Parts of White Oils (MS/SKO/HSD) are transported from Numaligarh to Siliguri by the
multiproduct Numaligarh Siliguri pipeline operated by Oil India Limited. The same is not
covered under this feasibility report. However cost of the pipeline has been provided by
NRL for the purpose of cost estimate.
1.4.7 Effluent Treatment Plant
A new effluent treatment plant with a capacity of 300 M3/Hr will be installed to treat the
effluent generated from the new refinery train. This effluent treatment plant will also
incorporate facilities for reclaiming water from the effluent for reuse in the refinery.