Primavera
Primavera and Project Management
1-Jul-
HP1000 Design Building Addition 1-Sep-21 100%
21
24-Aug- 17-Sep-
HP1030 Review and Approve Designs 100%
21 21
Foundation
20-Sep-
HP1090 Begin Building Construction 100%
21
20-Sep-
HP1100 Site Preparation 9-Nov-21 100%
21
11-Nov- 10-Dec-
HP1230 Excavation 100%
21 21
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 1/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
28-Dec- 27-Jan-
HP1340 Form/Pour Concrete Footings 100%
21 22
1-Feb-
HP1350 Concrete Foundation Walls 70%
22
Mechanical/Electrical
Systems
HVAC
11-Nov- 21-Nov-
HP1240 Review Bids for Heat Pump 100%
21 21
23-Nov- 30-Nov-
HP1270 Award Contract for Heat Pump 100%
21 21
Exterior Finishes
Brick
20-Sep-
HP1040 Assemble Brick Samples 100%
21
20-Sep- 18-Oct-
HP1070 Review and Approve Brick Samples 100%
21 21
5-Nov- 23-Nov-
HP1220 Review Bids for Brick 100%
21 21
21 21
30-Nov- 30-Nov-
HP1280 Deliver Brick 100%
21 21
Interior Finishes
20-Sep- 18-Oct-
HP1080 Review and Approve Flooring 100%
21 21
19-Oct- 16-Nov-
HP1170 Prepare and Solicit Bids for Flooring 100%
21 21
18-Nov-
HP1250 Review Bids for Flooring 4-Dec-21 100%
21
6-Dec-
HP1300 Award Contract for Flooring 9-Dec-21 100%
21
10-Dec-
HP1310 Fabricate and Deliver Flooring 23%
21
For ongoing Activities with Percent Complete Type Physical, as activity HP1350, fill in the Remaining
Duration column with the remaining time required. The example for the HP1350 activity is filled with
six days.
Otherwise, the remaining duration will be calculated automatically for activities that are still in
progress using Percent Complete Type Duration (HP1290 and HP1310).
The steps to update the actual data, according to the data table above, are as follows:
Open the project to be updated. In this example, open the EC005011 Haitang Corporate Park
project.
To fill in the actual date, select the activity for which you want to enter the actual date.
In the Details section, select the Status tab.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 3/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Click on the Checklist column in the Started section for activities that have started and the
Finished column if the activity has been completed (completed).
If your actual date is different from the planned date, you can change it by clicking on the three-
dot box […] on the right side of the date and then selecting the actual date.
For activities that are still in progress enter only the start date, as below. To fill in the percentage
of activity completion (HP1350), fill it in the Physical % column, or you can fill it in the Activity %
Complete column. Fill in according to the progress of the activity.
Note: The % Complete type will match one of the percent Complete types you selected, which are:
Duration, Physical, or Units.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 4/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
If your choice is Duration, then the display in the Details -> Status section, as below:
If your choice is Physical, then the display in the Details -> Status section, as below:
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 5/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
If your choice is Units, then the display in the Details -> Status section, as below:
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 6/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Enter the Auto Compute Actuals column in the activity table. If activities have the same actual
date as the Baseline date (initial plan), click on the Auto Compute Actuals column.
If you do not click on the Auto Compute Actuals column, then the activities that which actual date has
not been filled in and the baseline date is less than the Cutoff Date will shift to the same as the Cutoff
Date (New Data Date) + 1 day, after the Apply Actuals.
For example, if the activity has not started yet, the plan will start one day after the cutoff date (October
31, 2021, will start on November 1, 2021). Or, if the activity is still in progress, the remaining duration
will be calculated from the cutoff date.
The difference between Apply Actuals and Schedule [F9] is that all activity dates on the Apply Actuals
that do not contain the actual date will be shifted to one day after the cutoff date (rather than
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 7/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
While in Schedule [F9], all activities will shift according to their relationship (sequential) starting from
the scheduling date, as shown in the example below:
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 8/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Next go to Tools menu -> Apply Actuals…, fill in the New Data Date column with February 25,
2022. This date is the actual Cuttoff Date date. After that, click the Apply button.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 9/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Primavera Reader
Project Management & Tools
• Then, you can reschedule (Tools -> Schedule…) using the Cutoff Date (Current Data Date) on
February 25, 2022.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 10/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Result:
Edwin
Blogger at Primaverareader
I am a father of 2 children interested in many things related to nature and go green. Currently participating in
construction project related to schedule management.
Some of what I write on this blog is part of my experience that I think can be helpful to read.
Hobbies: Spending time with family, learning valuable knowledge, and sharing valuable experiences.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 11/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
SHARE
RELATED POSTS
9 Advantages of using oracle How to Create S-Curve in Primavera Stages of Scheduling Using
Primavera Cloud in THE PROJECT P6 Primavera P6
TEAMS
How to Filter Activities Data in How to Login to Primavera when You How to Open XER File With or
Primavera Forget Your Password Without Primavera P6
Leave a Reply
Your email address will not be published. Required fields are marked *
Comment
Name*
Email*
Website
Save my name, email, and website in this browser for the next time I comment.
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 12/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Post Comment
3 comments
Adji
October 26, 2021 at 4:02 am
The update actuals images (figures) from 1 to 13 are not visible (do not appear). Please fix this problem.
Reply
Ilham
December 3, 2021 at 10:49 pm
Reply
Adji
October 26, 2021 at 4:03 am
The update actuals images (figures) from 1 to 13 are not visible (do not appear). Please fix this problem.
Reply
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 13/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
Search …
TOPIC
Select Category
RECOMMENDED
https://www.primaverareader.com/how-to-update-actual-project-progress-in-primavera/ 14/15
10/20/22, 4:04 PM How to Update Actual Project Progress in Primavera - Primavera Reader
24 Best Project Management Step by Step Project Scheduling Pelatihan Primavera P6 Jakarta
Tools for 202… Tutorial…
How To Choose The Right Step by Step Project Scheduling Download Primavera P6 Free
Project Software… Tutorial… Full version…