You are on page 1of 3

Title Document no. Rev.

Page Of
5 1 3
930 G 0032
Confidential class 2
Project Document state
Inspection Form
Project number
- Issued
PRE-COMMISSIONING TEST SHEET
Customer Supplier

Doc. type Issued by Language Product / Structure Derived from

930 G Engineering English -/- 930G0032 rev.3


Rev. Revisions

3 REN 01/06/95
4 Upload in Document Management System
5 Bookmark error removed on page 3

Scan QR code to verify revision validity


or
check on http://212.78.221.90/

AKL IA-JZA RLI

27-3-2018 28-3-2018 28-3-2018

Created/Revised Checked Approved Authorized

Ansaldo Thomassen reserves all rights on this document that can not be reproduced in any part without its written consent.
Title Document no. Rev. Page Of

5 2 3
PRE-COMMISSIONING TEST SHEET 930 G 0032
Confidential class 2

FEEDER in AC MCC and ELECTRICAL HEATER

System: Project:

EQUIPMENT DETAILS
Manufacturer Phases
Voltage Rating
Serial n Connection Star/delta

1 CHECK OF FEEDER FOR ELECTRICAL HEATER RESULTS INITIALS


1.1 Visual inspection of contactor
1.2 Operation of all moving parts and mechanisms
1.3 Withdrawable feeder easily with-drawn and re-inserted
1.4 Mechanical interlock between isolator switch and panel door
1.5 All dust seals undamaged
1.6 Electrical connections correct and tightened
1.7 Fuse ratings correct and fuses inserted
1.8 Shrouds intact on "live" terminals
1.9 Push button operation
1.10 Indicator lamps
1.11 Anti condensation heater (in cable compartment of MCC)
1.12 Cable core connections correct and identified correctly
1.13 Cable terminations satisfactory
1.14 Cables identified correctly
1.15 Label correct

2 CHECK OF ELECTRICAL HEATER RESULTS INITIALS


2.1 Equipment undamaged
2.2 Nameplate details correct
2.3 Terminal box correct
2.4 Electrical connections correct and tightened
2.5 Cable terminations satisfactory
2.6 Cable core identified correctly
2.7 Earthing of heater shell satisfactory
2.8 Terminal box covers re-installed and fastened
2.9 Field switch operation

Ansaldo Thomassen reserves all rights on this document that can not be reproduced in any part without its written consent.
Title Document no. Rev. Page Of

5 3 3
PRE-COMMISSIONING TEST SHEET 930 G 0032
Confidential class 2

3 INSULATION TEST OF ELECTRICAL HEATER AND CABLES


DEVICE RESULT MEGOHMS TEST DATE INITIALS
3.1 Electrical heater
3.2 Power cable See E/I Contractor
3.3 Control cable See E/I Contractor

4 "LIVE" TEST OF ELECTRICAL HEATER RESULTS INITIALS


4.1 Switch on heating element and verify Amps to KW-rating.
Check delta/star connection, if reading is wrong
4.2 Measure current ............. Amps

Test performed by Ansaldo Thomassen: Customer: