Professional Documents
Culture Documents
Approved Construction Inspection Report For Tightening of Bolts (Form Applied for Group I, II, III, V
1.6 Fasten the anchor bolts tightly check Snug Tightening H W RW 100%
Drawing #5) Applied for group IV
V-Belt Installation check (use for motor with Inspection Report For V-Belt Installation (Form
1.7 Manufacture Instruction Manufacturer Instruction H W RW 100% Applied for Group III, VIII
belt) #5.1)
Construction Drawing
API 686 Para.4.6
Flange parallelism:
- Less than 0.025 mm per 25 mm (of flange
OD) up to 0.75 up to 0.75 mm maximum
Flange aligment check between rotating Construction Drawing Inspection Report For Flange Aligment (Form
1.8 - 0.25 mm maximum of flange OD smaller than H W W 100% Applied for Group I, II, III, IV, V, VI
equipment and piping before tightening API 686 #3.1)
250 mm
Bolt Hole offset:
- Bolt can be introduced through bolt holes
smoothly within 1.5 mm maximum offset from
center bolt hole
Final Alignment Check (After Pump Is
Connected To Pipe, equipment connected to Coupling Alignment Tolaerrance follow Inspection Report For Final Alignment Check
1.9 Construction Drawing H W W 100% Applied for Group I, II, III, IV
duct) After Soft Foot & Distance Between manufacture instruction (Form#6)
Coupling Check
2.1 Final Inspection & Walkdown Construction Drawing Construction Drawing Punch List Report (Form #11) H W W 100%
Noted: The stringent criteria between the Codes and manufacturer recommendation (guideline) shall be applied
ITP No :
TUWAIQ CASTING & FORGING FACILTY PROJECT
TITLE: INSPECTION AND TEST PLAN FOR PIPING INSTALLATION
Sketch
0°
P.1
Padding Padding
x
P...
EL: 0,000
270° 90°
P...
P...
Result
No Location Design Actual Deviation Remark
Accept Reject
1 P1 X1
2 P2 X2
3 P3 X3
4 P4 X4
5 P5 X5
6 P6 X6
7 P7 X7
. . .
n Pn Xn
<Remarks & Comments>
Signature
Full Name
Date
ITP No.
TUWAIQ CASTING & FORGING FACILTY PROJECT
Construction Drawing/
Inspection Item Accept Reject Remarks
Code & Standard
1 Documents
5 4 A
6 3
Liner
C B A
7 2 B
8 1
8 7 6
EL : (+) 3579
Pumb base
Flat Liner
1. Elevation
1 2 3 4 5 6 7 8 Remarks
Drawing
Actual
Difference
2. Location
1 2 3 4 5 6 7 8 Remarks
Drawing
Actual
Difference
<Remarks & Comments>
Signature
Full Name
Date
ITP No.
TUWAIQ CASTING & FORGING FACILTY PROJECT
Building/Structure Unit £ #1 □ #2
Inspection Item Date
Before Grouting
After Grouting
Note: The acceptance criteria are referring to manufacturer instruction while inspection
<Remarks & Comments>
Signature
Full Name
Date
ITP No.
TWAIQ CASTING & FORGING FACILTY PROJECT
Location:
Equipment:
Drawing Number:
Actual (mm)
Result
- Bolt can be introduced through bolt holes smoothly within 1.5 mm maximum offset from center bolt
Bolt Hole offset
hole
Signature
Full Name
Date
Sketch
P M
A
B
C
D
Distance Between Shaft ends and Coupling Hub in "mm" (Tolerance: ± 0.5 mm)
Note: The acceptance criteria are referring to manufacturer instruction or API 686 while inspection
+ In case of BFP(Boiler Feedwater Pump), The allowance tolerance for shim plate as follow: - Installation Stage: Max. 16mm, O&M Stage: Max. 18mm
Signature
Full Name
Date
ITP No. NS2-DH01-P0ZEN-740012 (4)
TUWAIQ CASTING & FORGING FACILTY PROJECT
Actual Torque
Bolt size Material Tension Value Accept Reject Remark
No.
(Snug check)
10
11
12
13
14
Note: The acceptance criteria are referring to manufacturer instruction while inspection
Remarks & Comment
Signature
Full Name
Date
ITP No. NS2-DH01-P0ZEN-740012 (5)
TUWAIQ CASTING & FORGING FACILTY PROJECT
Sketch
P M
A
B
C
D
Distance Between Shaft ends and Coupling Hub in "mm" (Tolerance: ± 0.5 mm)
Note: The acceptance criteria are referring to manufacturer instruction or API 686 while inspection
Signature
Full Name
Date
ITP No. NS2-DH01-P0ZEN-740012 (6)
Inspection Report For Perpendicular Check For Vertical Equipment
Report Number Sub-contractor LILAMA
VERTICAL EQUIPMENT
Design:
No H/1000 (mm) Actual: e (mm) Deviation Accept Reject Remarks
H(mm)
Signature
Full Name
Date
HORIZONTAL EQUIPMENT
Design:
No L/1000 (mm) Actual: f (mm) Deviation Accept Reject Remarks
L(mm)
Signature
Full Name
Date
ITP No. NS2-DH01-P0ZEN-740012 (7.2)
Fit-up Inspection Report
Report Number Sub-contractor LILAMA
Building / Structure Unit
Inspection Item Date
Drawing Number Sheet
Construction Drawing /
Inspection Item Accept Reject Remarks
Code & Standard
Fit-up records
No. Drawing No. Joint No. Gap (R) Root face (f) Beveling (α) Result Remarks
Signature
Full Name
Date
Construction Drawing /
Inspection Item Accept Reject Remarks
Code & Standard
Result
No. Drawing No. Joint No. Type Material Welder ID WPS Remarks
(Acc/Rej)
Signature
Full Name
Date
Construction Drawing /
Inspected properties Description Accept Reject Code & Standard
Signature
Full Name
Date
ITP No. NS2-DH01-P0ZEN-740012 (10)
Punch List Report
Report No. Sub-contractor LILAMA
Drawing Number
Ref.Report No.
10
11
12
13
14
Notes :
Category A comment that commissioning can proceed only after closure of this comment
Category B comment that commissioning can proceed even if comment still not closed
Signature
Full Name
Date