Execution Plan: FHS-031 Issue 1
Execution Plan: FHS-031 Issue 1
NECESSARY EQUIPMENT AND TOOLS (To Clarify Capacity, Specification and No. Etc.)
CRAN E ACC ES
S
PROCEDURE
1.0 Materials Preparation: workers and equipment. 4.2.4 Establish correct and final Elevation before fixing
1.1 All Materials shall be stored not to obsruct on-going Operations 4.0 Work Sequence 4.2.5 Fixing of Roof Truss using bolt connection
1.2 All small fabricated items shall be arranged in terms of installation sequence 4.1 Anchor Bolt Setting 4.2.6 Continue until braced bay is complete
1.3 All Anchor Bolts & accessoires shall be provided with proper platform for laydown 4.1.1 Insatallation of Scaffolding with complete accessories (by CTT) 4.2.7 Bolt Tightening
2.0 Tools Preparation: 4.1.2 Surveying Works, layout of reference elevation ¢erlines (by CCT) 4.3 Installation of Purlins and sagrods
2.1 All Welding Machine must be place in proper platform 4.1.3 Installation of Setting plate and installation of Anchor Bolts 4.3.1 Manual Hauling of Purlins and Sagrod
2.2 All tools and equipment are properly checked "good" for use 4.1.4 Final Inspection for Anchor Bolt setting and House keeping 4.3.2 Installation of Purlins and sarods using bolted connection
3.0 Safety Preparation: 4.2 Erection of Roof Trusses 4.3.3 Bolt Tightening
3.1 Conduct toolbox meeting prior to any works or any related construction activity. 4.2.1 Position 25T Mobile Crane on Stable Ground & barricade installation 4.4 Touch-up Paint for damaged part During Erection Works
3.2 All Warning signs are in place, Barricades and other safety paraphernalias. 4.2.2 Install 2 pcs - 3 tons capacity lifting belt to the truss with proper levelness 4.5 Housekeeping and pull out of tools
3.3 Safety Officer to ensure the enclosed area is controlled & secured for other 4.2.3 Erection of Roof Truss
PPE'S REQUIRED: OTHER SAFETY PRE-CAUTION: SITE SUPERVISOR SAFETY OFFICER AREA MANAGER
Safety Shoes Rubberized Hand Glooves Visibility Vest JAYSON PALKING ARDEE DE CASTRO REX DELGADO
FHS-031
EXECUTION PLAN Issue 1
RISK ASSESSMENT:
RISK ASSESSMENT NEW RISK RATING RISK ASSESSMENT NEW RISK RATING
ACTIVITY ACTIVITY
C L R C L R C L R C L R
RISK ASSESSMENT:
RISK ASSESSMENT NEW RISK RATING RISK ASSESSMENT NEW RISK RATING
ACTIVITY ACTIVITY
C L R C L R C L R C L R
RISK ASSESSMENT:
RISK ASSESSMENT:
1.2 UNATTENDED MATERIALS, 1.2.1 100% TIE-OFF TOOLS AND ADDITIONAL TOE
2 2 4
TOOLS AND OTHER ACCESSORIES BOARD FOR THE MATERIALS TO BE INSTALLED.
1.7 EXPLOSION FROM COMPRESS 1.7.1 CHECK CUTTING HOSE REGULARLY AND DO
3 1 3 SUPERVISOR
GAS CYLINDER. NOT PUT OXY-ACY IN HAP-HAZARD POSITION.
LIKELIHOOD
CONSEQUENCE
CONSEQUENCE
FHS-031
EXECUTION PLAN Issue 1
RISK ASSESSMENT:
2.3 MATERIALS FALL AND COLLAPSE 2.3.1 ENSURING MATERIALS ARE PROPERLY
2 2 4 SUPERVISOR
OF STRUCTURE RIGGED BY A COMPETENT RIGGER/SLINGMAN.
LIKELIHOOD
NSEQUENCE
CONSEQUENCE
FHS-031
EXECUTION PLAN Issue 1
RISK ASSESSMENT:
INSTALLATION OF PURLINS 3.1 NO PROPER INGRESS AND 3.1.1 INGRESS AND EGRESS MUST BE PROVIDED
3.0 PURLINS,WRECH 2 2 4 SUPERVISOR
AND SAGRODS EGRESS PRIOR TO PERFORM WORKS AT ELEVATED AREA.
3.2 FALL FROM HEIGHTS LEAD TO 3.2.1 100% FALL PROTECTION TIE-OFF WHEN
2 2 4
BONE FRACTURE AND FATALITY. WORKING IN ELEVATED AREA.
LIKELIHOOD
CONSEQUENCE
CONSEQUENCE
FHS-031
EXECUTION PLAN Issue 1
RISK ASSESSMENT:
4.1 FALL FROM HEIGHTS LEAD TO PAINT CANISTER, PAINT, PAINT 4.1.1 100% FALL PROTECTION TIE-OFF WHEN
4.0 PAINTING/TOUCH UP 1 2 2 SUPERVISOR
BONE FRACTURE AND FATALITY. BRUSH, PAINT ROLLER WORKING IN ELEVATED AREA.
LIKELIHOOD
NSEQUENCE
CONSEQUENCE