NO NAME OF ACTIVITY TYPE OF ACTIVITY TENTATIVE DURATION


1 setting corner benchmarks. Independent
2 excavation to the approved depth. Dependent

2 Construction of Diversion tunnel Dependent 42 days


3 Drill Blasting Dependent 10 days
4 Accumulation of excavated material Dependent 7 days
5 Abutement Slopes Excavation Independent 12 days
6 Slope Stabilization Independent 7 days
7 Closure dikes Construction Independent 21 days
8 De watering aggregates Independent 10 days
9 Arrangement of silos Independent 12 days
10 Batching plant Independent 15 days
11 Pile foundation Dependent 14 days
12 Raft foundation Dependent 30 days
13 Concrete slab(filling) Dependent 21 days
14 Compaction of Concrete Dependent 21 days
15 Construction of Face of Dam Dependent 42 days
16 Built heel and toe Independent 21 days
17 Construction of Insulating Walls Dependent 28 days
18 Erection of Front plate Dependent 28 days
19 Construction of Buttress Walls Independent 42 days
20 Construction of crest of Dam Dependent 35 days
21 Setting up Parapet wall Dependent 21 days
22 Installation of Sluice gates Independent 21 days
23 Dam testing Dependent 7 days
Total days 488
MATERIALS REQUIRED MODE OF CONSTRUCTION
Machinery
Excavator, Bulldozer Machinery

Tunnel boring machine Machinery


2 Boom Hydraulic Drill Machinery
Dump truck Machinery
Small Excavator & Boom hydraulic drill Machinery
Rock Anchors, Spraying short Grade Machinery
Excavated Material Both
Aggregates, Pre cold bins Machinery
Different Aggregates, Sand Machinery
Tower cranes Manual
Rcc piles Machinery
Steel double mats Manual
Concrete, concrete fillers Machinery
Cement Bricks, cement interlocking bricks Both
concrete, steel Manual
Cement ,Aggregate , steel Manual
concrete , Steel Manual
cement, Aggregate Manual
concrete, steel Manual
concrete, steel Manual
cement, Aggregate Manual
Fiber Reinforced polymer Machinery
Digital Inclinometer Machinery
16 Months