The document outlines a 21 step plan for dam construction over 16 months. It involves setting benchmarks, excavating to depth, constructing diversion tunnels using tunnel boring machines, drill blasting, accumulating excavated materials, excavating abutment slopes and stabilizing slopes using machinery. It also includes constructing closure dikes, dewatering and arranging aggregates, installing batching plants, pile and raft foundations, pouring concrete slabs, compacting concrete, and constructing various dam components like the face, heel, toe and walls. The plan also includes erecting front plates, constructing buttress walls, the crest, parapet walls and installing sluice gates before testing the dam.
The document outlines a 21 step plan for dam construction over 16 months. It involves setting benchmarks, excavating to depth, constructing diversion tunnels using tunnel boring machines, drill blasting, accumulating excavated materials, excavating abutment slopes and stabilizing slopes using machinery. It also includes constructing closure dikes, dewatering and arranging aggregates, installing batching plants, pile and raft foundations, pouring concrete slabs, compacting concrete, and constructing various dam components like the face, heel, toe and walls. The plan also includes erecting front plates, constructing buttress walls, the crest, parapet walls and installing sluice gates before testing the dam.
The document outlines a 21 step plan for dam construction over 16 months. It involves setting benchmarks, excavating to depth, constructing diversion tunnels using tunnel boring machines, drill blasting, accumulating excavated materials, excavating abutment slopes and stabilizing slopes using machinery. It also includes constructing closure dikes, dewatering and arranging aggregates, installing batching plants, pile and raft foundations, pouring concrete slabs, compacting concrete, and constructing various dam components like the face, heel, toe and walls. The plan also includes erecting front plates, constructing buttress walls, the crest, parapet walls and installing sluice gates before testing the dam.
NO NAME OF ACTIVITY TYPE OF ACTIVITY TENTATIVE DURATION
1 setting corner benchmarks. Independent 2 excavation to the approved depth. Dependent
2 Construction of Diversion tunnel Dependent 42 days
3 Drill Blasting Dependent 10 days 4 Accumulation of excavated material Dependent 7 days 5 Abutement Slopes Excavation Independent 12 days 6 Slope Stabilization Independent 7 days 7 Closure dikes Construction Independent 21 days 8 De watering aggregates Independent 10 days 9 Arrangement of silos Independent 12 days 10 Batching plant Independent 15 days 11 Pile foundation Dependent 14 days 12 Raft foundation Dependent 30 days 13 Concrete slab(filling) Dependent 21 days 14 Compaction of Concrete Dependent 21 days 15 Construction of Face of Dam Dependent 42 days 16 Built heel and toe Independent 21 days 17 Construction of Insulating Walls Dependent 28 days 18 Erection of Front plate Dependent 28 days 19 Construction of Buttress Walls Independent 42 days 20 Construction of crest of Dam Dependent 35 days 21 Setting up Parapet wall Dependent 21 days 22 Installation of Sluice gates Independent 21 days 23 Dam testing Dependent 7 days Total days 488 MATERIALS REQUIRED MODE OF CONSTRUCTION Machinery Excavator, Bulldozer Machinery
Tunnel boring machine Machinery
2 Boom Hydraulic Drill Machinery Dump truck Machinery Small Excavator & Boom hydraulic drill Machinery Rock Anchors, Spraying short Grade Machinery Excavated Material Both Aggregates, Pre cold bins Machinery Different Aggregates, Sand Machinery Tower cranes Manual Rcc piles Machinery Steel double mats Manual Concrete, concrete fillers Machinery Cement Bricks, cement interlocking bricks Both concrete, steel Manual Cement ,Aggregate , steel Manual concrete , Steel Manual cement, Aggregate Manual concrete, steel Manual concrete, steel Manual cement, Aggregate Manual Fiber Reinforced polymer Machinery Digital Inclinometer Machinery 16 Months