METALITE BUILDERS DEVELOPMENT CO. INC.

WEEK NO. 13
SEPTEMBER 8-14, 2017
!  PROJECT STATUS UPDATE
!  PERMIT STATUS
!  ON-GOING ACTIVITIES
!  PROGRESS PHOTOS
!  SAFETY AND HEALTH
!  OTHER CONCERN
PERMIT REQUIRED BY MOLINO / BACOOR CITY ENGINEERING STATUS RESPONSIBLE

1. BARANGAY CLEARANCE COMPLIED MBDCI

2. LOCATIONAL CLEARANCE MBDCI

T.C.T COMPLIED MWSI

TAX DECLARATION COMPLIED MWSI

SECRETARY CERTIFICATE COMPLIED MWSI

LOT GEO-SURVEY (LOT PLAN) COMPLIED MWSI

ARCHITECTURAL DRAWINGS – BLUE PRINT COMPLIED MWSI/MBDCI

LC ACCOMPLISHED FORM WITH SIGN OF MS. LUCAS COMPLIED MWSI/MBDCI

CONTRACT / N.O.A / N.T.P COMPLIED MBDCI

OFFICIAL RECEIPT (TAX DECLARATION) COMPLIED MWSI

3. BUILDING PERMIT
T.C.T COMPLIED MWSI

TAX DECLARATION COMPLIED MWSI

CONTRACT / N.O.A / N.T.P / TECH. SPECS / COST ESTIMATE COMPLIED MBDCI

AUTHORIZATION LETTER FROM MWSI COMPLIED MBDCI

BRGY. PERMIT COMPLIED MBDCI

LOCATIONAL CLEARANCE COMPLIED MBDCI

PRC / PTR OF PROFESIONAL COMPLIED MBDCI

ZONING CLEARANCE COMPLIED MBDCI

FIRE SAFETY CLEARANCE ON-PROCESS MBDCI

CONTRACTOR’S TEMPORARY BUSINESS PERMIT COMPLIED MBDCI


PERMIT REQUIRED BY MOLINO / BACOOR CITY ENGINEERING STATUS RESPONSIBLE

BUILDING PERMIT FORM (S & S) (ELEC / CIVIL) (NOTARIZED) ON PROCESS MBDCI

PLAN & DRAWINGS ON-PROCESS MWSI/MBDCI

OCCUPANCY PERMIT ON-PROCESS MBDCI


PERMIT TO OPERATE ON-PROCESS MBDCI
ELECTRICAL PERMIT ON-PROCESS MBDCI
MECHANICAL PERMIT ON-PROCESS MBDCI
SANITARY PERMIT ON-PROCESS MBDCI
PLUMING PERMIT ON-PROCESS MBDCI
CERTIFICATE ELECTRICAL INSPECTION ON-PROCESS MBDCI
NOTICE'TO'PROCEED:' JUNE'16,'2017'
REMAINING'
CALENDAR'DAYS:' 300' DAYS'ELAPSED' DAYS'

SCHEDULED'COMPLETION:' APRIL'11,'2018' !!
91' 209'

30.33%' '
! !

CONTRACT'COST' PHYSICAL''ACCOMPLISHMENT'

PREVIOUS'WEEK' THIS'PERIOD'
TO'DATE'
₱ 322,800,000.00
WEEK'12' WEEK'13'

AMOUNT' % WT AMOUNT' % WT AMOUNT' % WT

SCCURVE' 30,769,296 9.53 3,518,520 1.09 34,281,360 10.62

ACTUAL' 31,279,320 9.69 2,517,840 0.78 33,797,160 10.47

VARIANCE' 510,024 0.16' -1,000,680 C0.31' -484,200 C0.15'

TOTAL'AMOUNT'RECEIVED'/'%'BILLED:' '

TE'1'DURATION'/'TE'1'COMPLETION'DATE:' !

TE'2'DURATION'/'TE'2'COMPLETION'DATE:' !

TE'3'DURATION'/'TE'3'COMPLETION'DATE:' !
QTY.'
ITEM'NO.' DESCRIPTION' UNIT' AMOUNT' AMOUNT'TO' BILLABLE'
THIS'WEEK' DATE' TO'DATE'

BID' PREV' WK'13' TO'DATE'

I.A.1 Mobiliza*on! LS! 1.0! 0.52! 0.08! 0.6! 192,000.00! 1,440,000!.00! !!

I.B! Health!&!Safety! MO! 10.0! 2.4! 0.2! 2.6! 56,000.00! 728,000.00!

II.B.1.2.1.1! Suspended!Slab! CU.M! 52! H! 16! 16! 129,600.00 129,600.00 !!

II.B.1.2.1.2!
! Column!/!Corbel! CU.M! 63! 25! 13! 38! 105,300.00 307,800.00 !!

II.B.1.3.1.2!Slab!on!Grade! CU.M! 82! H! 25! 25! 194,400.00 194,400.00 !!


ITEM'NO.' QTY.'
DESCRIPTION' UNIT' AMOUNT' AMOUNT'TO' BILLABLE'
' THIS'WEEK' DATE' TO'DATE'
BID' PREV' WK'13' TO'DATE'

Metal!Works!(Pump! LS! 0.07!


II.D.1.1 LS! 0.18! 0.25! 299,980.80 1,071,360.00 !!
Sta*on)!

Perimeter!Fence!With!CHB,!
Cyclone!Wire!and!Barbed!
III.!H.1.3.1! Wire!! LM! 405! 150! 60! 210! 1,069,200.00! 3,742,200.00! !!
(Perimeter!Fence!Type!1!/!
Sht.!No.!C506)!

Perimeter!Fence!With!CHB!
III.!H.1.3.2! and!Barbed!Wire!! LM! 139! 50! 10! 60! 194,400.00! 1,166,400.00 !!
(Perimeter!Fence!Type!2!/!
Sht.!No.!C507)!
ITEM DESCRIPTION STATUS

1 RETAINING WALL
UNDER NEGOTIATION W/
THE OWNER OF
ADJACENT PROPERTY
2 PERIMETER FENCE (FACING ROADWAY)
Week 13 (SEP 8-SEP 14, 2017)
DESCRIPTION NO. OF PERSONS REMARKS
Total Number of Staff (MBDCI) 5

Total Number of Workers 61


Total Number of Manpower 66

Accumulated Total Man hours w/o LTI 39410


Week 13
Safety Induction – Number of Persons Inducted
Number of Person(s) Inducted

Incident / Accident Details


Injury Incidents First Aide Cases 0
Medical Treated Cases 0
Disabling Injury Cases 0
Lost Time Injury Cases 0
Total Worker Days Lost 0

Other Accident / Incident Related Near Misses 0


Property Damage 0
Security Work Related 0
Environment Related 0
No. Topics Date No. of Conducted by
Conducted Attendees
1 HOT WORK SAFETY SEPT. 8,2017 66 ARJAY SEVILLA

2 HAND PROTECTION SEPT. 9,2017 66 ARJAY SEVILLA

3 EYE PROTECTION SEPT. 10,2017 66 ARJAY SEVILLA

4 WORKING AT HEIGHTS SEPT. 11,2017 66 ARJAY SEVILLA

5 HEAVY EQUIPMENT SEPT. 12,2017 66 ARJAY SEVILLA

6 HOUSE KEEPING SEPT. 13,2017 66 ARJAY SEVILLA

7 SCAFFOLDING SEPT. 14,2017 66 ARJAY SEVILLA