You are on page 1of 9

Version 7.2.

PVsyst - Simulation report


Grid-Connected System

Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group at RFL-11, Bike
Variant: South
No 3D scene defined, no shadings
System power: 273 kWp
Sylhet - Bangladesh

Client Chint Solar Bangladesh Co.Ltd


RFL
Habigonj, Sylhet
Bangladesh

Page 1/9
Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Project summary
Geographical Site Situation Project settings
Sylhet Latitude 24.28 °N Albedo 0.20
Bangladesh Longitude 91.38 °E
Altitude 15 m
Time zone UTC+6

Meteo data
Olipur
Meteonorm 8.0 (1996-2015), Sat=100% - Synthetic

System summary
Grid-Connected System No 3D scene defined, no shadings
Simulation for year no 1

PV Field Orientation Near Shadings User's needs


Fixed plane No Shadings Unlimited load (grid)
Tilt/Azimuth 20 / 0 °

System information
PV Array Inverters
Nb. of modules 496 units Nb. of units 2 units
Pnom total 273 kWp Pnom total 220 kWac
Pnom ratio 1.240

Results summary
Produced Energy 375.7 MWh/year Specific production 1377 kWh/kWp/year Perf. Ratio PR 84.74 %

Table of contents
Cover page 1
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 5
Loss diagram 6
Special graphs 7
Aging Tool 8

21/11/22 PVsyst Licensed to Page 2/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

General parameters
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation
Orientation Sheds configuration Models used
Fixed plane No 3D scene defined Transposition Perez
Tilt/Azimuth 20 / 0 ° Diffuse Perez, Meteonorm
Circumsolar separate

Horizon Near Shadings User's needs


Free Horizon No Shadings Unlimited load (grid)

PV Array Characteristics
PV module Inverter
Manufacturer Astronergy Manufacturer Huawei Technologies
Model CHSM72M-HC-550 Model SUN2000-110KTL-M0
(Custom parameters definition) (Custom parameters definition)
Unit Nom. Power 550 Wp Unit Nom. Power 110 kWac
Number of PV modules 496 units Number of inverters 2 unit
Nominal (STC) 273 kWp Total power 220 kWac
Modules 31 Strings x 16 In series Operating voltage 200-1000 V
At operating cond. (50°C) Max. power (=>30°C) 121 kWac
Pmpp 249 kWp Pnom ratio (DC:AC) 1.24
U mpp 605 V
I mpp 412 A

Total PV power Total inverter power


Nominal (STC) 273 kWp Total power 220 kWac
Total 496 modules Nb. of inverters 2 units
Module area 1281 m² Pnom ratio 1.24
Cell area 1179 m²

Array losses
Array Soiling Losses Thermal Loss factor DC wiring losses
Loss Fraction 2.0 % Module temperature according to irradiance Global array res. 32 mΩ
Uc (const) 29.0 W/m²K Loss Fraction 2.0 % at STC
Uv (wind) 0.0 W/m²K/m/s

Serie Diode Loss LID - Light Induced Degradation Module Quality Loss
Voltage drop 0.7 V Loss Fraction 2.0 % Loss Fraction -0.8 %
Loss Fraction 0.1 % at STC

Module mismatch losses Strings Mismatch loss Module average degradation


Loss Fraction 2.0 % at MPP Loss Fraction 0.1 % Year no 1
Loss factor 0.55 %/year
Mismatch due to degradation
Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year

IAM loss factor


Incidence effect (IAM): User defined profile

0° 40° 50° 60° 70° 75° 80° 85° 90°


1.000 1.000 1.000 1.000 1.000 0.984 0.949 0.830 0.000

21/11/22 PVsyst Licensed to Page 3/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

System losses
Auxiliaries loss
Proportionnal to Power 5.0 W/kW
0.0 kW from Power thresh.

AC wiring losses
Inv. output line up to injection point
Inverter voltage 400 Vac tri
Loss Fraction 1.00 % at STC
Inverter: SUN2000-110KTL-M0
Wire section (2 Inv.) Copper 2 x 3 x 95 mm²
Average wires length 61 m

21/11/22 PVsyst Licensed to Page 4/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Main results
System Production
Produced Energy 375.7 MWh/year Specific production 1377 kWh/kWp/year
Performance Ratio PR 84.74 %

Normalized productions (per installed kWp) Performance Ratio PR

Balances and main results

GlobHor DiffHor T_Amb GlobInc GlobEff EArray E_Grid PR


kWh/m² kWh/m² °C kWh/m² kWh/m² MWh MWh ratio
January 100.3 53.6 17.29 122.2 119.6 29.86 29.10 0.873
February 109.5 62.7 21.03 125.0 122.3 30.03 29.24 0.858
March 149.3 79.0 25.71 160.7 157.2 37.74 36.68 0.837
April 149.6 94.7 27.58 150.4 147.0 35.32 34.37 0.838
May 157.4 103.6 28.26 151.3 147.9 35.63 34.69 0.840
June 124.9 89.6 28.09 117.8 115.1 27.90 27.20 0.846
July 120.5 91.6 28.48 114.4 111.8 27.16 26.50 0.849
August 146.6 96.1 28.63 144.3 141.1 34.01 33.13 0.841
September 136.4 72.1 27.94 142.4 139.3 33.35 32.42 0.834
October 118.2 69.3 27.08 131.4 128.5 31.00 30.17 0.842
November 115.7 54.6 23.00 141.4 138.4 33.74 32.83 0.851
December 99.7 52.8 19.03 123.9 121.2 30.13 29.37 0.869
Year 1528.1 919.8 25.19 1625.2 1589.4 385.87 375.69 0.847

Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings

21/11/22 PVsyst Licensed to Page 5/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Loss diagram
1528 kWh/m² Global horizontal irradiation
+6.4% Global incident in coll. plane

-0.21% IAM factor on global


-2.00% Soiling loss factor

1589 kWh/m² * 1281 m² coll. Effective irradiation on collectors

efficiency at STC = 21.32% PV conversion

434.1 MWh Array nominal energy (at STC effic.)


-0.29% Module Degradation Loss ( for year #1)
-0.52% PV loss due to irradiance level

-6.12% PV loss due to temperature

+0.75% Module quality loss

-2.00% LID - Light induced degradation

-2.06% Mismatch loss, modules and strings

-1.29% Ohmic wiring loss


385.9 MWh Array virtual energy at MPP
-1.66% Inverter Loss during operation (efficiency)
0.00% Inverter Loss over nominal inv. power
0.00% Inverter Loss due to max. input current
0.00% Inverter Loss over nominal inv. voltage
0.00% Inverter Loss due to power threshold
0.00% Inverter Loss due to voltage threshold
-0.01% Night consumption
379.4 MWh Available Energy at Inverter Output

-0.50% Auxiliaries (fans, other)


-0.49% AC ohmic loss
375.7 MWh Energy injected into grid

21/11/22 PVsyst Licensed to Page 6/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Special graphs
Daily Input/Output diagram

System Output Power Distribution

21/11/22 PVsyst Licensed to Page 7/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Olipur MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Energy injected into grid

Performance Ratio

21/11/22 PVsyst Licensed to Page 8/9


Project: 272.8 KWp Rooftop Solar Power Plant for RFL Group
at RFL-11, Bike, Habiganj, Sylhet, Bangaldesh
PVsyst V7.2.3
Variant: South
VC0, Simulation date:
21/11/22 15:40
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Olipur MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Olipur MN80 SYN

Year E Grid PR PR loss


MWh %
1 375.7 0.847 0%
2 373.6 0.843 -0.5%
3 371.4 0.838 -1.1%
4 368.9 0.832 -1.8%
5 366.3 0.826 -2.5%
6 363.3 0.819 -3.3%
7 360.0 0.812 -4.2%
8 356.7 0.804 -5.1%
9 353.3 0.797 -6%
10 350.0 0.789 -6.8%
11 347.0 0.783 -7.6%
12 344.4 0.777 -8.3%
13 341.8 0.771 -9%
14 339.4 0.766 -9.7%
15 337.0 0.76 -10.3%
16 334.8 0.755 -10.9%
17 332.7 0.75 -11.4%
18 330.5 0.745 -12%
19 328.1 0.74 -12.7%
20 325.6 0.734 -13.3%
21 322.6 0.728 -14.1%
22 319.0 0.719 -15.1%
23 315.3 0.711 -16.1%
24 311.4 0.702 -17.1%
25 307.5 0.694 -18.2%

21/11/22 PVsyst Licensed to Page 9/9

You might also like