PVsyst - Simulation report


Grid-Connected System

Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC Rotor Unit
Variant: E/W
No 3D scene defined, no shadings
System power: 282 kWp
Bharādoba, Valuka, Mymensingh - Bangladesh

Client Chint Solar Bangladesh Company


Multazim Spinning Mills Ltd
Vhoradoba,Valuka, Mymensingh
Mymensingh
Bangladesh
Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Project summary
Geographical Site Situation Project settings
Bharādoba, Valuka, Mymensingh Latitude 24.45 °N Albedo 0.20
Bangladesh Longitude 90.39 °E
Altitude 13 m
Time zone UTC+6

Meteo data
Bharādoba, Valuka, Mymensingh
Meteonorm 8.0 (1996-2015), Sat=100% - Synthetic

System summary
Grid-Connected System No 3D scene defined, no shadings
Simulation for year no 1

PV Field Orientation Near Shadings User's needs


Fixed planes 2 orientations No Shadings Unlimited load (grid)
Tilts/azimuths 4 / -90 °
4 / 90 °

System information
PV Array Inverters
Nb. of modules 512 units Nb. of units 2 units
Pnom total 282 kWp Pnom total 200 kWac
Pnom ratio 1.408

Results summary
Produced Energy 364.0 MWh/year Specific production 1292 kWh/kWp/year Perf. Ratio PR 84.87 %

Table of contents
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 5
Loss diagram 6
Special graphs 7
Aging Tool 8

12/11/22 PVsyst Licensed to Page 2/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

General parameters
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation
Orientation Sheds configuration Models used
Fixed planes 2 orientations No 3D scene defined Transposition Perez
Tilts/azimuths 4 / -90 ° Diffuse Perez, Meteonorm
4 / 90 ° Circumsolar separate

Horizon Near Shadings User's needs


Free Horizon No Shadings Unlimited load (grid)

PV Array Characteristics
PV module Inverter
Manufacturer Astronergy Manufacturer ChintPower
Model CHSM72M-HC-550 Model CPS SCA110KTL-DO/EU
(Custom parameters definition) (Custom parameters definition)
Unit Nom. Power 550 Wp Unit Nom. Power 100 kWac
Number of PV modules 512 units Number of inverters 2 unit
Nominal (STC) 282 kWp Total power 200 kWac
Modules 32 Strings x 16 In series Operating voltage 200-1000 V
At operating cond. (50°C) Max. power (=>45°C) 110 kWac
Pmpp 257 kWp Pnom ratio (DC:AC) 1.41
U mpp 605 V
I mpp 425 A

Total PV power Total inverter power


Nominal (STC) 282 kWp Total power 200 kWac
Total 512 modules Nb. of inverters 2 units
Module area 1323 m² Pnom ratio 1.41
Cell area 1217 m²

Array losses
Array Soiling Losses Thermal Loss factor DC wiring losses
Loss Fraction 2.0 % Module temperature according to irradiance Global array res. 31 mΩ
Uc (const) 29.0 W/m²K Loss Fraction 2.0 % at STC
Uv (wind) 0.0 W/m²K/m/s

Serie Diode Loss LID - Light Induced Degradation Module Quality Loss
Voltage drop 0.7 V Loss Fraction 2.0 % Loss Fraction -0.8 %
Loss Fraction 0.1 % at STC

Module mismatch losses Strings Mismatch loss Module average degradation


Loss Fraction 2.0 % at MPP Loss Fraction 0.1 % Year no 1
Loss factor 0.55 %/year
Mismatch due to degradation
Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year

IAM loss factor


Incidence effect (IAM): User defined profile

0° 40° 50° 60° 70° 75° 80° 85° 90°


1.000 1.000 1.000 1.000 1.000 0.984 0.949 0.830 0.000

12/11/22 PVsyst Licensed to Page 3/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

System losses
Auxiliaries loss
Proportionnal to Power 5.0 W/kW
0.0 kW from Power thresh.

AC wiring losses
Inv. output line up to injection point
Inverter voltage 400 Vac tri
Loss Fraction 1.00 % at STC
Inverter: CPS SCA110KTL-DO/EU
Wire section (2 Inv.) Copper 2 x 3 x 95 mm²
Average wires length 59 m

12/11/22 PVsyst Licensed to Page 4/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Main results
System Production
Produced Energy 364.0 MWh/year Specific production 1292 kWh/kWp/year
Performance Ratio PR 84.87 %

Normalized productions (per installed kWp) Performance Ratio PR

Balances and main results

GlobHor DiffHor T_Amb GlobInc GlobEff EArray E_Grid PR


kWh/m² kWh/m² °C kWh/m² kWh/m² MWh MWh ratio
January 102.6 61.2 17.07 102.5 100.0 26.07 25.43 0.882
February 111.1 62.2 20.97 111.1 108.5 27.70 26.97 0.862
March 154.4 79.9 25.76 154.4 150.9 37.59 36.54 0.840
April 153.2 90.3 27.63 153.1 149.7 37.12 36.09 0.837
May 159.1 104.6 28.30 158.8 155.2 38.51 37.46 0.838
June 123.5 88.7 28.14 123.2 120.3 30.05 29.25 0.843
July 119.0 78.5 28.52 118.7 116.0 28.85 28.06 0.839
August 145.6 94.4 28.68 145.4 142.0 35.39 34.45 0.841
September 126.8 73.9 28.00 126.7 123.8 30.83 29.98 0.840
October 118.9 75.9 27.14 118.7 115.9 29.12 28.36 0.848
November 111.9 55.5 23.01 111.9 109.3 27.80 27.07 0.859
December 98.5 56.0 18.89 98.5 96.1 24.90 24.29 0.876
Year 1524.7 921.1 25.19 1522.9 1487.7 373.94 363.95 0.849

Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings

12/11/22 PVsyst Licensed to Page 5/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Loss diagram
1525 kWh/m² Global horizontal irradiation

-0.11% Global incident in coll. plane


-0.32% IAM factor on global
-2.00% Soiling loss factor

1488 kWh/m² * 1323 m² coll. Effective irradiation on collectors

efficiency at STC = 21.32% PV conversion

419.5 MWh Array nominal energy (at STC effic.)


-0.29% Module Degradation Loss ( for year #1)
-0.60% PV loss due to irradiance level

-5.84% PV loss due to temperature

+0.75% Module quality loss

-2.00% LID - Light induced degradation

-2.06% Mismatch loss, modules and strings

-1.21% Ohmic wiring loss


0.00% Mixed orientation mismatch loss
374.0 MWh Array virtual energy at MPP
-1.72% Inverter Loss during operation (efficiency)
0.00% Inverter Loss over nominal inv. power
0.00% Inverter Loss due to max. input current
0.00% Inverter Loss over nominal inv. voltage
0.00% Inverter Loss due to power threshold
0.00% Inverter Loss due to voltage threshold
-0.01% Night consumption
367.4 MWh Available Energy at Inverter Output

-0.50% Auxiliaries (fans, other)


-0.45% AC ohmic loss
364.0 MWh Energy injected into grid

12/11/22 PVsyst Licensed to Page 6/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Special graphs
Daily Input/Output diagram

System Output Power Distribution

12/11/22 PVsyst Licensed to Page 7/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Bhar doba Valuka Mymensingh MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Energy injected into grid

Performance Ratio

12/11/22 PVsyst Licensed to Page 8/9


Project: 281.6 KWp Rooftop Solar Power Plant for ASF CVC
Rotor Unit
PVsyst V7.2.3
Variant: E/W
VC0, Simulation date:
12/11/22 11:12
with v7.2.3

Aging Tool
Aging Parameters
Time span of simulation 25 years
Module average degradation Mismatch due to degradation
Loss factor 0.55 %/year Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year
Meteo used in the simulation
#1 Bhar doba Valuka Mymensingh MN80 SYN
Years 1990 (reference year)
Years simulated 1-25

Bhar doba Valuka Mymensingh MN80 SYN

Year E Grid PR PR loss


MWh %
1 364.0 0.849 0%
2 362.0 0.844 -0.5%
3 359.9 0.839 -1.1%
4 357.5 0.834 -1.8%
5 355.0 0.828 -2.5%
6 352.2 0.821 -3.2%
7 349.0 0.814 -4.1%
8 345.8 0.806 -5%
9 342.6 0.799 -5.9%
10 339.5 0.792 -6.7%
11 336.6 0.785 -7.5%
12 334.1 0.779 -8.2%
13 331.7 0.773 -8.9%
14 329.3 0.768 -9.5%
15 327.1 0.763 -10.1%
16 325.0 0.758 -10.7%
17 322.9 0.753 -11.3%
18 320.9 0.748 -11.8%
19 318.6 0.743 -12.5%
20 316.1 0.737 -13.1%
21 313.0 0.73 -14%
22 309.2 0.721 -15%
23 305.3 0.712 -16.1%
24 301.2 0.702 -17.2%
25 297.2 0.693 -18.3%