You are on page 1of 3

Contractor: DOCG Project: EACOP MoC No: AZHAR-MOC-001

Asset or worksite(s): Tank Area - MST Client: EACOP Date: 04-12-2022


Single Point of Contact (SPOC): Chotikorn H

Part I Change identification - Proposal


Title: Big Trees Falling (By Excavator)

Description of Change:

Reference Method statement for site preparation and earth work. (TZ-TAN-90-DBO1-
30039_01_AFC_20221030) Item, 9.2 Vegetation clearance and Trees cutting. For item 9.2 Tree cutting work.

 Tree higher than 5m with many trunks found unstable due to excavation performed around
need to be throw down with excavator. Trunks to be cut with chainsaw are at heights and
without safe access.

Tree falling by Excavator


 In case that some big trees with higher than 5 m, but there is a sticky wood or have many
trunks in one tree (Figure 1), safe felling process will be:
 Before conducting cutting work, barricade the area with safety tape and signage (area shall
be > the estimate height of the tree).
 Assess Tree Center of Gravity (CoG) to anticipate falling direction.
 Excavate the soil one side of the trunk area (on falling side) until the roots appear and cut off
all roots. (Figure 2)
 Use the excavator bucket to push the tree down in the specified direction.
 After falling, cut the trunk and branches with chainsaws.

1
Figure 1 Figure 2

Justification of Change:

For item 9.2 Tree cutting work, which MS specify allow to cutting if the diameter of the trees shall be between
100mm and 600mm with a maximum height of 5 meters. But in the MST area, some trees higher than 5 m.
and some trees have many trunks in one tree which makes it difficult to cut.

Areas Affected by Change:

☒ H3SE Review required by H3SE Dpt.


☐ Costs: _________($) Review required by CTR Site PM
☐ Schedule: ______ (days) Review required by CTR Site PM

Note: COMPANY Representative(s) only sign for Technical/H3SE, not for Cost/Schedule impact.

Processes Involved:

☒ Operating Standards ☒ H3SE Procedure ☐ Installation


☐ Organization/Personnel ☐ Engineering Standard ☐ Equipment Certification
☐ Equipment Maintenance ☐ Client Contract ☐ Lifting Procedure

Change Classification:
☐ Permanent Change
☒ Temporary Change Expiration of Temporary Change:

Documents affected by the Change:

 Method statement for site preparation and earth work. (TZ-TAN-90-DBO1-


30039_01_AFC_20221030)
 RA-0020A Risk assessment for Tree Cutting (using Excavator & Chain saw) and wood shifting

Remarks:

Requested by: Initial Review:


Chotikorn H / AZHAR ☒ Approved
☐ Rejected

Signed: Date:

2
Reasons for Rejecting (if applicable):

Part II To be completed before Authorization of Change


Change Risk Ranking Matrix

Severity of Potential Consequence: ☐ S1 ☐ S2 ☒ S3 ☐ S4


Probability: ☐ P1 ☐ P2 ☐ P3 ☒ P4 ☐ P5

Risk Ranking: ☐ A (Intolerable) ☐ C (Moderate)


☐ B (High) ☒ D (Minimal)

(Deviation from “operational standards” will always result in Risk Rank B or higher)

Part III Change Authorization


Approved: ☒ Rejected: ☐

SUB-CTR (AZHAR) CTR (DOCG) CTR (DOCG) Client


Project Manager Dep. HSE Manager Dep. Construction Manager EACOP Site Rep.

Name: Chotikorn H Name: Tariq Saleem Name: Zhang Yanshuai Name:

Signature: Signature: Signature: Signature:


Date: Date: Date Date:
Date: