points capacity (both LA & LG) Manufactured GCO probe test rigging point (stated in for plant sitting location KNOW supplier Certified with OR manual) Supervisor THE Form 6,7 (6-month check for load sitting S.W.L validity) location Fatal zone Minimum Rigging 3-3-3 team members for heavy lifting Rigger stands 3 meters away from 1 Lifting load Supervisor Ensure counterweight Lift up300 mm above ground and of plant is INSIDE BARRICADED fatal zone 1 Rigger Hold for 3 seconds Document Environment Planning
Follow the Lifting Plan
NO PICK & Be aware of NEARBY CARRY without approval facilities/ plant to prevent collision