Professional Documents
Culture Documents
Contract.
PT. PUPUK ISKANDAR MUDA No. :
MOM No. :
Project : NPK PROJECT 500.000 MTPY
Location : KREUNG GEUKUH
Minutes By :
ATTENDANCE LIST
Copy to:
4 Status persiapan:
Man Power Indirect (on site) RMS:
1. Project Control (Rizqi) CTI 23-Feb-22
4.a CTI 24-Feb-22
2. Supervisor Installasi (Suharto)
3. Asst. Material Control (TBA) CTI 22-Feb-22
Penambahan Man Power Direct (on site) RMS:
1. Foreman Erection (TBA) CTI 1-Mar-22
2. Fitter Erector (27 org) CTI 21-Feb-22 s.d 1-Mar-22
4.b 3. Welder (4 org) CTI 21-Feb-22 s.d 1-Mar-22
CTI 21-Feb-22 s.d 1-Mar-22
4. Helper (12 org)
CTI 21-Feb-22 s.d 1-Mar-22
5. Rigger (2 org) CTI 21-Feb-22 s.d 1-Mar-22
6. Scaffolder (2 org) CTI 21-Feb-22 s.d 1-Mar-22
7. Painter (2 org)
Mobilisasi Equipment (on site):
1. Crane-1 (70 ton) Lokal PP 1-Mar-22
2. Crane-2 (70 ton) PT. SBP/ Medan CTI 1-Mar-22
3. Crane-3 (25 ton) PT. SBP/ Medan CTI 26-Feb-22
4.c CTI 1-Mar-22
4. Crane-4 (25 ton) PT. SBP/ Medan
CTI 26-Feb-22
5. TMC (5 ton) CTI 1-Mar-22
6. Manlift (1 unit) CTI 21-Feb-22
7. Welding Machine FCAW (8 unit) Medan
Hand Tools (on site):
1. Mesin Gerinda (2 ea) Medan CTI 21-Feb-22
4.d CTI 21-Feb-22
2. Cutting Torch (1 ea) Medan
3. Gerinda Baby/ Reamer (2 ea) Medan CTI 26-Feb-22
Temporary Shop -1 (area kantor CTI):
1. Power dan Tenda done
107 107 107 107 160 160 160 160 158 158 158 158 1700
DETAIL SCHEDULE SITE FABRIKASI RMS (SECTION 1)
VOL FEBRUARY MARET
NO WORK SQUENCH LOCATION QTTY
LOT RAW
26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
WEIGH WEIGH
Modify Column 3-4 4 1.1 4.4 F1
Modify Column 5-6 4 1.1 4.4 F1
1
Modify Column 7-8 4 1.1 4.4 F1
Modify Column 9- 10 4 1.1 4.4 F1
Modification girder 2- 3 2 6.25 12.5 F2
Modification girder 2-2A 2 6.25 12.5 F2
Modification girder 2A-3 2 6.25 12.5 F2
Modification girder 3-3A 2 6.25 12.5 F2
Modification girder 3A- 4 2 6.25 12.5 F2
Modification girder 4- 4 A 2 6.25 12.5 F2
Modification girder 4A- 5 2 6.25 12.5 F2
Modification girder 5 - 5A 2 6.25 12.5 F2
2 Modification girder 5A - 6 2 6.25 12.5 F2 F1
SECTION 2
Modification girder 6 - 6A 2 6.25 12.5 F2 F1
Modification girder 6A - 7 2 6.25 12.5 F2 F1
Modification girder 7 - 7A 2 6.25 12.5 F2 F1
Modification girder 7A - 8 2 6.25 12.5 F2 F1
Modification girder 8- 8A 2 6.25 12.5 F2 F1
Modification girder 8 A- 9 2 6.25 12.5 F2 F1
Modification girder 9- 9A 2 6.25 12.5 F2 F1
Modification girder 9A - 10 2 6.25 12.5 F2 F1
Modify Rafter 2-2A 16 1.2 19.45 F3 F4 F2 F1
Modify Rafter 3-3A 16 1.2 19.45 F3 F4
Modify Rafter 4- 4 A 16 1.2 19.45 F3 F4
3 Modify Rafter 5 - 5A 16 1.2 19.45 F3 F4
Modify Rafter 6 - 6A 16 1.2 19.45 F3 F4 F1
Modify Rafter 7 - 7A 16 1.2 19.45 F3 F4 F1
Modify Rafter 8- 8A 16 1.2 19.45 F3 F4 F1
Modify Rafter 9- 9A 16 1.2 19.45 F3 F4 F1
376.9
TOTAL 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
SECTION 2
Modification girder 6 - 6A 2 6.25 12.5 12.5
Modification girder 6A - 7 2 6.25 12.5 12.5
Modification girder 7 - 7A 2 6.25 12.5 12.5
Modification girder 7A - 8 2 6.25 12.5 12.5
Modification girder 8- 8A 2 6.25 12.5 12.5
Modification girder 8 A- 9 2 6.25 12.5 12.5
Modification girder 9- 9A 2 6.25 12.5 12.5
Modification girder 9A - 10 2 6.25 12.5 12.5
Modify Rafter 2-2A 16 1.2 19.45 4.86 4.86 4.863 4.86
Modify Rafter 3-3A 16 1.2 19.45 4.86 4.86 4.863 4.86
Modify Rafter 4- 4 A 16 1.2 19.45 4.86 4.86 4.86 4.86
3 Modify Rafter 5 - 5A 16 1.2 19.45 4.86 4.863 4.863 4.86
Modify Rafter 6 - 6A 16 1.2 19.45 4.863 4.86 4.86 4.86
Modify Rafter 7 - 7A 16 1.2 19.45 4.86 4.86 4.86 4.863
Modify Rafter 8- 8A 16 1.2 19.45 4.863 4.863 4.863 4.863
Modify Rafter 9- 9A 16 1.2 19.45 4.86 4.86 4.86 4.863
Area painting
Area
fabrication
Area space fame
fabrikasi
column
Area
TERINSTAL
fabrikasi
rafter
Area
painting
ERECTION & ASSEMBLY PLAN
LINE-J 1 1 1 1
INSTALLED
3 2 5 4 CONTINUE
LINE-A 1 1 1 1
DETAIL ASSEMBLY & INSTALLATION RMS
QTTY VOL FEBRUARY MARET
NO WORK SQUENCH LOCATION
LOT UNIT TOTAL 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Assy SF + Column 2-2A 2 5,15 10,3
A1
Assy SF + Column 2A- 3 2 5,15 10,3
Assy SF + Column 3 - 3A 2 7,35 14,7
A1
Assy SF + Column 3 A - 4 2 7,35 14,7
Assy Rafter 2-2A 1 21,63 21,63 A2
Assy Rafter 3 - 3A 1 21,63 19,45 A2
Install SF + Column 2-2A 2 5,15 10,3
1 A1
Install SF + Column 2A- 3 2 5,15 10,3
Install SF + Column 3 - 3A 2 7,35 14,7
A1
install SF + Column 3 A - 4 2 7,35 14,7
Erection Rafter 2-2A 1 21,63 21,63 A1
Assy H Brace + Purlin 1A-2 1 5,8 5,8 A1
Erection Rafter 1A-3 1 21,63 21,63 A1
Assy H Brace + Purlin 2A- 3 1 5,8 5,8 A1
Assy SF + Column 4 - 4A 2 5,15 10,3
A2
Assy SF + Column 4A - 5 2 5,15 10,3
Assy SF + Column 5-5A 2 7,35 14,7
A2
Assy SF + Column 5A-6 2 7,35 14,7
Assy Rafter 4 - 4A 1 19,45 19,45 A3
Assy Rafter 5-5A 1 19,45 19,45 A3 A2
Install SF + Column 5-5A 2 5,15 10,3 A1
2
Install SF + Column 5A-6 2 5,15 10,3
Install SF + Column 4 - 4A 2 7,35 14,7 A1
install SF + Column 4A - 5 2 7,35 14,7
Erection Rafter 4 - 4A 1 19,45 19,45 A1
Assy H Brace + Purlin 3 A - 4 1 5,8 5,8 A1
Erection Rafter 5-5A 1 19,45 19,45 A1
Assy H Brace + Purlin 4A - 5 1 5,8 5,8 A1
Assy SF + Column 6 - 6A 2 5,15 10,3
A2
Assy SF + Column 6 A- 7 2 5,15 10,3
Assy SF + Column 7-7A 2 7,35 14,7
A3
Assy SF + Column 7A -8 2 7,35 14,7
Assy Rafter 6 - 6A 1 19,45 19,45 A3 A2
Assy Rafter 7-7A 1 19,45 19,45 A3 A2
Install SF + Column 7-7A 2 5,15 10,3 A1
3
Install SF + Column 7A -8 2 5,15 10,3
Install SF + Column 6 - 6A 2 7,35 14,7 A1
install SF + Column 6 A- 7 2 7,35 14,7
Erection Rafter 6 - 6A 1 19,45 19,45 A1
Assy H Brace + Purlin 5A-6 1 5,8 5,8 A1
Erection Rafter 7-7A 1 19,45 19,45 A1
Assy H Brace + Purlin 6 A- 7 1 5,8 5,8 A1
Assy SF + Column 8-8A 2 5,15 10,3
A2
Assy SF + Column 8A-9 2 5,15 10,3
Assy SF + Column 9-9A 2 7,35 14,7
A3
Assy SF + Column 9A-10 2 7,35 14,7
Assy Rafter 8-8A 1 19,45 19,45 A3 A2
Assy Rafter 9-9A 1 19,45 19,45 A3 A2
Install SF + Column 9-9A 2 5,15 10,3 A1
4
Install SF + Column 9A-10 2 5,15 10,3
Install SF + Column 8-8A 2 7,35 14,7 A1
install SF + Column 8A-9 2 7,35 14,7
Erection Rafter 8-8A 1 19,45 19,45 A1
Assy H Brace + Purlin 7A-8 1 5,8 5,8 A1
Erection Rafter 9-9A 1 19,45 19,45 A1
Assy H Brace + Purlin 8A-9 1 5,8 5,8 A2
MAN POWER
FORMAN 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
FITTER 1 / ERECTOR 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
FITTER 2 8 8 8 8 8 8 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
HELPER 4 4 4 4 4 4 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
RIGGER 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
SCAFOLDER 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
TOTAL 27 27 27 27 27 27 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34 34
EQUIPMENT JUMLAH
HYDRO CRANE 70 TON 2 UNIT 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
HYDRO CRANE 25 TON 2 UNIT 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TMC 5 TON 1 UNIT 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
RIGGING DEVICE 1 LOT 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
VOLUME & DETAIL, ASSEMBLY & INSTALLATION RMS
QTTY VOL FEBRUARY MARET
NO WORK SQUENCH LOCATION
LOT
UNIT TOTAL 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
GRAND-TOTAL 98 - - - 82 98 98 69 49 20 - 689
EQUIPMENT
EQUIPMENT & TOOL
& TOOLS STATUSSTATUS
A EQUIPMENT ERECTION
1 Hydro. Crane 70 Ton 2 7 1,0 2,0 2,0 2,0 - 2,0 01-Mar SUPLY BY SBP
2 Hydro. Crane 25 Ton 2 8 1,0 2,0 2,0 2,0 1,0 1,0 1,0 01-Mar SUPLY BY SBP
3 Forklift/TMC 5 Ton 1 4 1,0 1,0 1,0 1,0 - 1,0 01-Mar
Purpose:
- Telah terjadi Misdesign fasilitas RMS & BBS Perlu perkuatan Structure untuk memenuhi beban-
beban yang diterima supaya sesuai dengan standard perencanaan, agar tidak terjadi failure.
- Telah dilakukan Fabrikasi dan delivery 100% di site, dan juga dilakukan fabrikasi tambahan (untuk
perkuatan structure) dan juga dikirimkan disite.
- Perlu dilakukan site Fabrikasi (Modifikasi), assembly dan installation.
1. Work Area Sequential
Area-1 Area-3 Area-4
U Area-1 Area-2
Kolom & Space Roof Plan (Hopper)
Kolom & Space Frame Rafter
Frame (Upper&Lower)
300 M
1 2 31
PENGECEKAN OLEH QC
ASSEMBLY
(WELDING, DIMENSI, PAINTING)
ERECTION CHORD RAFTER & SPACE ERECTION RAFTER, BAL OK ANAK &
ERECTION RAFTER
FRAME HORIZONTA L BR ACE
ALIGNMENT / VERTIKALITY
& GROUTING
1. Modification Flow Chart
Install Tripper by ETI (parallel)
Area-1 (Kolom & Space Frame)
Install
Complete Install Roof Plan
Install Kolom Rafter/pasa
2 4 (antar 2 Rafter) Finish
& Space Frame ng
& Remaining SS
(@2Rafter)
1
3 7
Assembly Kolom & Space Frame 5
Assembly -
- 2 set kiri-kanan Sepasang Install
Modif. Area
Rafter Intall:
2. Fabr. Girder 1.Add. Balok Anak 6 Hopper
1. Modif. Kolom (@2rafter)
Space Frame 2.Add. Diagonal
(2 set = 2kolom ) (2 Set kiri-kanan) /Horz. Bracing
3. Fabr. Rafter
(Sepasang=2 rafter) 4.Fabr. Area
a) Modif. Pangkal
a) Ganti Base Plate. Hopper
Rafter (Buat Splicing
b) T-Box Kolom a) Ganti 4 ea ujung Install :
Ujung a) Add. Balok Anak
c) Add. Knee Brace Vertical Bracing
b) Add Bracing
b) Add. Top Chord Rafter
1. Purlin b) Add. Diagonal
c) Fabrikasi Space 2. Post & Girt /Horz. Bracing
c) Add.&Ganti Gasset
e) Add. Jacketing Plate Frame 3. Roofing & Sidding c) Modif. EndPlate
d) Add. Balok Anak
Kolom
e) Add. Diagonal /Horz.
Bracing
1a 3a 5a 7a
Parallel Install :
I. Intall. complete Roof 1st .
I II III
II. Intall. complete Roof 2nd .
III. Dst.
Parallel:
2 4 6 8
A. Intall. complete Roof Area Hopper
B. Dst.
1b 3b 5b 7b
Work Area Overview
AREA-2
(RAFTER)
AREA-1
(KOLOM & SPACE FRAME)
2. SITE FABRICATION MANAGEMENT
Lokasi Site Fabrication :
1. Shop-1: Di Laydown CTI
2. Shop-2: di Bagging Area
Pengelompokan Sub-Area sesuai Katagori Fabrikasi al:
1. Area Modif Kolom
2. Area Modif Space Frame ke Girder
3. Area Modif Rafter
4. Area Modif Roof Hopper
Area Fabr.
Rafter
MOVE
Area Fabr. Area
Hopper Fabr. Rafter
Area Area
Area -Fabr. Fabr. SPACE
Kolom FRAME Painting
DETAIL MODIFICATION ITEM
a. Modif Area-1 (Kolom & Space Frame Girder)
1. Pemasangan Steel Plate pada Pedestal beton (Jacketing Plate)
2. Penggantian Baseplate Kolom
3. Perkuatan Kolom Steel (Add. T-Box)
4. Penambahan Knee Brace (H 250x250x9x14)
5. Modifikasi Girder menjadi Space Frame
Menjadi
Upper Roof Plan Modification
MODIFICATION
QTY= ~1700 ton
(700 ton Add)
ORIGINAL Menjadi
QTY = ~ 1000 ton
Typical Section Modification
Rafter
W= ~20 Ton/pasang
MODIFICATION
ORIGINAL
FRAME LINE – 2A (intermediate Rafter)
MODIFICATION
Menjadi
ORIGINAL
a. Modification Area-1 (Kolom)
Modifikasi pada
Kolom:
1. Penggantian Tambahan T-Box
Menjadi
Baseplate Kolom
2. Perkuatan Kolom
Steel (Add. T-Box)
3. Penambahan Knee
Brace (H SEBELUM PERKUATAN
250x250x9x14)
4. Steel Plate Jacketing
Plate
SETELAH PERKUATAN
a. Modification Area-1 (Space Frame)
Modifikasi Girder menjadi Space Frame:
1. Pemotongan Rafter Ujung / Buat Splicing
2. Penambahan/ Penggantian Bracing
CUTTING & CONNECTION POINT
SPLICING
ꓶΓ 80x80x6
Vertical
member
ꓶΓ 80x80x6
Vertical
member Modif. Area -2 (Rafter)
1. Ganti Vertical Bracing 2x4ea (2
L80.80.6)
2. Penambahan Top Chord Rafter
3. Penggantian/pemindahan gasset
bracing
4. Penambahan Gusset utk HB & Balok
Anak.
W= ~10 ton
c. Modification Area -3 (Roof Plan)
WF 200x100x5x8
Steel beam
d. Modification Area-4 (Hopper)
Modif. Area -4 (Hopper)
1. Modif. End Plate
2. Penambahan balok Anak
Cutting endplate & haunch
3. Penambahan Bracing
Cutting rafter 300 mm
4. ASSEMBLY & ERECTION SEQUANCE
15c
16c
30c
28c
29c
4c
3c
2c
31
29
30
15
16
1
3
2
GROUP – I : GROUP – II :
= Assembly Kolom & Space Frame = Assembly Kolom & Space Frame
= Assembly Rafter = Assembly Rafter
5. RIGGING PLAN & CRANE POSITION
Intall Kolom
& SF
Intall Rafter
C-1
(100t)
C-3
(25t)
C-2
(100t)
Overview Figure
View
Crane
Position
6. Target Schedule
SCHEDULE PRODUCTIVITY STEEL STRUCTURE RMS AREA
RMS FACILITY
SHOP FABRIKASI 02-Jan-22 05-Feb-22 34 5 686 137 137 137 137 137
DELIVERY MATERIAL 02-Jan-22 19-Feb-22 48 7 686 PLAN 98 98 98 98 98 98 98
24 ACTUAL 22 2,4
DELIVERY MATERIAL FORECAST 98 98 98 98 98 98 98
SITE REFABR. & ASS. 19-Feb-22 12-May-22 82 12 1.717 PLAN 143 143 143 143 143 143 143 143 143 143 143 143
ACTUAL
Target
ERECTION 01-Mar-22 21-May-22 81 12 1.717 FORECAST
ACTUAL
Delivery RMS 143 143 143 143 143 143 143 143 143 143 143 143
PLAN 16 16 16 16 16 16 16 16 16 16 16
CREW FORECAST (Crew)
AKTUAL
PLAN 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8 8,8
TARGET PRODUCTIVITY (t/day/crew)
AKTUAL 1,3 3,3 3,3 3,3
PLAN
FORECAST PRODUCTIVITY
AKTUAL
Target Schedule Original VOID
Target Schedule BARU
Facility : RAW MATERIAL STRUCTURE (RMS) MARET APRIL MEI
Unit Total 26-Feb 05-Mar 12-Mar 19-Mar 26-Mar 02-Apr 09-Apr 16-Apr 23-Apr 30-Apr 07-May 14-May 21-May 28-May
Jml Ton/
No Area QTY Weight Weight Type Member Actifity s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
Week week
(ton) (ton) 04-Mar 11-Mar 18-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr 06-May 13-May 20-May 27-May 03-Jun
W-156 W-157 W-158 W-159 W-160 W-161 W-162 W-163 W-164 W-165 W-166 W-167 W-168 W-169
BARAT ( Line 1
I TOTAL (ton) = 915,75 25 82 98 98 98 98 98 98 98 73 40 40
s/d 15)
2x 15 Site Fabrication,
Kolom & Space
1 pasang = 7,35 220,5 9 25 Kolom, Space Frame Assembly & 25 25 25 25 25 25 25 25 25
Frame
30 Sets Installation
15 Sets 2 Rafter Frame, B. Site Fabrication,
2 Rafter (@2Rafter/ 19,45 291,75 9 33 Anak & Horizontal Assembly & 33 33 33 33 33 33 33 33 33
pasang) Bracing Installation
Balok Anak,
3 Roof Plan 15 sets 3,6 54 10 6 Installation 6 6 6 6 6 6 6 6 6 6
Horizontal Bracing
1/2 Beam Girder, B. Site Fabrication &
4 Hopper 432 216 11 20 20 20 20 20 20 20 20 20 20 20 20
Bentang Anak & HB Installation
1/2
5 Girt 54 27 10 3 Cannel u/ Siding Installation 3 3 3 3 3 3 3 3 3 3
Bentang
1/2
6 Purlin 131 65,5 10 7 Cannel u/ Roof Installation 7 7 7 7 7 7 7 7 7 7
Bentang
7 Accessories 41 11 4 Bolt, etc. Installation 4 4 4 4 4 4 4 4 4 4 4
TIMUR ( Line
II TOTAL (ton) = 915,75 25 82 98 98 98 98 98 98 98 73 40 40
31 s/d 16)
II BARAT+TIMUR TOTAL (ton) = 1831,5 50 164 196 196 196 196 196 196 196 146 80 80
7. RESOURCE PLAN VOID
Peak 2021 2021 2022
Total NO DESCRIPTION CAP. Q'TY
TOTAL
NO Description PIC Unit Remarks E/M Jul Agus Sep Okt Nov Des
Men/Month
Q'ty Okt Nov Sept
Jul Agus Des Jan
Okt Feb
Nov Mar
Des
A INDIRECT LABOR A EQUIPMENT
1 Project Manager Muhammad Guntur Prs 1 1 1 1 1 1 1 6 1 Mobile. Crane 100 Ton 1 1 1 - - - - -
2 Site Manager Adi Wijaya Prs 1 1 1 1 1 1 1 6
2 Hydro. Crane 45/50 Ton 2 7 1 - - 2 2 2
3 Superintendent Samsul Rohman Prs 1 1 1 1 1 1 1 6
4 Project Control Heru Prs 1 1 1 1 1 1 1 6 3 Hydro. Crane 35 Ton 0 0 - - - - - -
5 Q/C Inspector Fajar Prs 1 1 1 1 1 1 1 6 3 Hydro. Crane 25 Ton 2 10 1 1 2 2 2 2
6 Q/C Site Fabrication Tobi Prs 1 - - 1 1 1 1 4 4 Trailler/Tronton 20 Ton 1 5 0 1 1 1 1 1
7 Safety Coordinator Soniar Sonata Prs 1 1 1 1 1 1 1 6
5 Generator 10 kva 1 6 1 1 1 1 1 1
8 Safety Officer Azwir Prs 1 1 1 1 1 1 1 6
6 Pick-Up 1 Ton 1 6 1 1 1 1 1 1
9 Mat'l. Control Supv. TBA Prs 1 - - 1 1 1 1 4
10 Warehouseman Bayu Prs 1 1 1 1 1 1 1 6 7 Total Station 1 6 1 1 1 1 1 1
11 Surveyor Kusuma Prs 1 1 1 1 1 1 1 6 8 Auto Level 1 6 1 1 1 1 1 1
12 Assistant Surveyor Rendy Prs 1 1 1 1 1 1 1 6 9 Elect. Wld M/C 8 32 4 4 8 8 4 4
13 Adm. Project By HO Prs - - - - - - - -
10 Cutting Torch 4 20 0 4 4 4 4 4
14 Security Andre, Roji, TBA Prs 3 2 3 3 3 3 3 17
15 Driver Muhadar, Turmudi Prs 2 1 2 2 2 2 2 11 11 Elect. Plasma Cutting 2 10 0 2 2 2 2 2
TBN Tahyan
S/I-2 S/S S/I1 S/S
Heru
Project Manager
CTI SHOP FABRICATION
Shop Fabrication (JKT)
Adi Wijaya
Site Manager
FABRICATION G-2 ERECTOR GROUP-2 FABRICATION G-1 ERECTOR GROUP-1 TBA TBA
1. Welder 8 org 1. Erector 12 org 1. Welder 8 org 1. Erector 12 org Consumable Ctl. QC Feld Inspector
2. Fitter 8 org 2. Helper 6 org 2. Fitter 8 org 2. Helper 6 org
3. Helper 16 org 3. Helper 16 org GENERAL SUPP.
PAINTING FIELD PAINTING FIELD SURVEYOR TEAM
1. Painter 2 org 1. Painter 2org 1. Mechanic 1 org
2. Electrician 1org 1.Surveyor 2 org
PAINTING SHOP G-2 2. Helper 2 org PAINTING SHOP G-1 2. Helper 2 org 2.Ass. Surv. 2org
1. Sandblaster 2 org 1. Sandblaster 2 org 3. Driver 2org
2. Painter 4 org 2. Painter 4 org 4. Helper 4org
SCAFFOLDING G-2 SCAFFOLDING G-1
3. Helper 4 org 1. Scaffolder 8 org 3. Helper 4 org 1. Scaffolder 8 org
Dirrect MP
2. Helper 8 org 2. Helper 8 org Group-1 = 94 orang
SUPPORTING SHOP SUPPORTING SHOP
1. Op. crane-25 2org SUPPORTING 1. Op. crane-25 2org SUPPORTING
Group-2 = 94 orang
2. Op. TMC 2org 1. Op. crane-100 4org 2. Op. TMC 2org 1. Op. crane-100 4org Masing2 Terdiri dari:
3. Rigger 2 org 2. Op. crane-25 2 org 3. Rigger 2org 2. Op. crane-25 2 org Shop 1+22+10+8 = 41org
4. Helper 2 org 3. Rigger 6 org 4. Helper 2 org 3. Rigger 6org
Field 1+18+4+16+14 = 53 org
Group-1 4. Helper 2 org Group-2 4. Helper 2 org
MP CTI
INDIRECT
PEAK
No Description PIC UNIT
QTY MARET APRIL MEI
I Indirect Manpower Subtotal Prs 26 26 26 26
1 Project Manager Heru Prs 1 1 1 1
2 Site Manager Adi Wijaya Prs 1 1 1 1
3 Superintendent TBA Prs 2 2 2 2
4 Supervisor Shop ? Prs 3 3 3 3
5 Siupervisor Field ? Prs 3 3 3 3
6 Project Control ? Prs 1 1 1 1
7 Lead QC Inspector Fajar Prs 1 1 1 1
8 Shop Inspector Tobi Prs 1 1 1 1
9 Safety Coordinator Soniar Sonata Prs 1 1 1 1
10 Safety Officer Azwir Prs 3 3 3 3
11 Warehouse Prs 1 1 1 1
12 Material Control Akmal Prs 1 1 1 1
13 Consumable Control ? Prs 1 1 1 1
14 Surveyor Kusuma Prs 1 1 1 1
15 Ass Surveyor Rendy Prs 2 2 2 2
16 Project Admin ? Prs 1 1 1 1
17 Security Andre,Roji,TBA Prs 1 1 1 1
18 Driver Prs 1 1 1 1
MP CTI
DIRECT MP TIM-A 93 Orang DIRECT MP TIM-B 93 Orang
PEAK PEAK
No Description PIC UNIT No Description PIC UNIT
QTY MARET APRIL MEI QTY MARET APRIL MEI
II Dirrect LABOR Subtotal Prs 93 93 93 93 II Dirrect LABOR Subtotal Prs 93 93 93 93
A SITE FABR (SHOP) Subtotal Prs 47 47 47 47 A SITE FABR (SHOP) Subtotal Prs 47 47 47 47
1 Welder Prs 8 8 8 8 1 Welder Prs 8 8 8 8
2 Fitter Prs 8 8 8 8 2 Fitter Prs 8 8 8 8
3 Helper Welding Prs 16 16 16 16 3 Helper Welding Prs 16 16 16 16
4 SandBlaster Prs 2 2 2 2 4 SandBlaster Prs 2 2 2 2
5 Painter Prs 3 3 3 3 5 Painter Prs 3 3 3 3
6 Helper Painting Prs 3 3 3 3 6 Helper Painting Prs 3 3 3 3
7 Operator Crane25 Prs 1 1 1 1 7 Operator Crane25 Prs 1 1 1 1
8 Operator TMC1 Prs 1 1 1 1 8 Operator TMC1 Prs 1 1 1 1
9 Operator Tronton Prs 1 1 1 1 9 Operator Tronton Prs 1 1 1 1
10 Rigger Prs 3 3 3 3 10 Rigger Prs 3 3 3 3
11 Helper Prs 1 1 1 1 11 Helper Prs 1 1 1 1
Terimoung Geunaseh