PROGRAM OF WORKS
BILL OF MATERIALS
DISCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
A. MASONRY WORKS
Cement 60 Bags 250.00 15,000.00
Sands 10 Cu. M 900.00 9,000.00
Gravel 15 Cu. M 1,500.00 22,500.00
12 mm D/B 45 Pcs. 320.00 14,400.00
Total 60,900.00
B. COLUMN
DISCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Premium Cement 30 Bags 250.00 7,500.00
Sands 8 Cu. M 900.00 7,200.00
Gravel 10 Cu. M 1500.00 15,000.00
16 mm D/B 24 Pcs. 630.00 15,120.00
10 MM D/B 40 Pcs. 290.00 11,600.00
Tie Wire #16 4 Klg. 85.00 340.00
Total 56,760.00
C. WALL FOOTING
DISCRIPTION QUANTITY UNIT UNIT COST TOTAL COST
Premium Cement 20 Bags 250.00 5,000.00
Sands 6 Cu. M 900.00 5,400.00
Gravel 8 Cu. M 1500.00 12,000.00
10 MM D/B #16 30 Klg. 290.00 8,700.00
Tie Wire #16 2 Klg. 85.00 170.00
Total 31,100.00
D. CHB WALL
CHB #4" (Standard) 12000 Pcs. 12.00 144,000.00
Premium Cement 70 Bags 250.00 17,500.00
Sands 8 Cu. M 900.00 7,200.00
Gravel 15 Cu. M 1500.00 22,500.00
10 mm D/B 58 Pcs. 290.00 16,820.00
Tie Wire #16 5 Klg. 85.00 425.00
Total 208,445.00
E. FORMS AND SCAFFOLDINGS
2 X 2 X 10 Coco Lumber 264 B. Ft. 20.00 5,280.00
1/4 THR Plywood 18 Pcs. 450.00 8,100.00
Assorted CW Nails 40 Klg. 80.00 3,200.00
Total 16,580.00
B. Labor Cost (40% of total Material Cost) ₱ 149,582.00
Total Material Cost ₱ 373,955.00
Labor Cost (40%) ₱ 149,582.00
Contingency (20%of Labor Cost) ₱ 29,916.40
Eng'g Supervision (25% of Labor Cost) ₱ 37,395.50
Total Project Cost ₱ 590,848.90
Prepared: Confirmed:
2022_Accounting_Template
DEPARTMENT OF EDUCATION
REGION-IX, ZAMBOANGA PENINSULA
DIVISION OF PAGADIAN CITY
CO TEK CHUN NATIONAL TRADE SCHOOL
TIGUMA, PAGADIAN CITY
PROGRAM OF WORKS
NICK L. MOJELLO RONALD O. UY, EdD
Head Teacher I/ SPF Coordinator School Principal II
2022_Accounting_Template