Professional Documents
Culture Documents
TABLE OF CONTENTS
DIVISION 3 - CONCRETE
DIVISION 4 - MASONRY
04100 Mortar
04200 Unit Masonry
DIVISION 5 - METALS
DIVISION 6 - CARPENTRY
07100 Waterproofing
07320 Tiled Roofing
07400 Metal roofing
DIVISION 8 - DOORS & WINDOWS
DIVISION 9 - FINISHES
DIVISION 10 - SPECIALTIES
DIVISION 11 - MECHANICAL
PART 1 GENERAL
1.01 SCOPE
1.02 PERMITS
Secure and pay for all necessary permits required for the work.
1.04 PROTECTION
PART 2 EXECUTION
2.01 DEMOLITION
c. Cap all existing utility lines, consult owner before commencing work.
2.03 REPAIRS
54
SECTION 02200 EARTHWORK
PART 1 GENERAL
1.01 SCOPE
Stripping
Site grading
Excavation
Trenching
Backfilling
Compaction
Dewatering
a. Verify and examine the site of work to familiarize with the character
of materials to be encountered and all other existing conditions
affecting the work.
1.03 PROTECTION
PART 2 PRODUCTS
2.01 MATERIALS
a. Select fill material shall be laboratory approved from off site source,
passing a 75 mm (3 in.) sieve. The fraction passing a C.425 mm
(No. 40) sieve shall have a liquid limit not exceeding 35% and a
plasticity index not exceeding 12%
55
uniformly graded and of a size which will pass a 1-inch mesh screen
and be retained on a No. 4 mesh screen.
PART 3 EXECUTION
3.01 STRIPPING
a. Strip top soil only in areas required as shown in the plans. Remove
top soil to depths indicated or as required by the Architect but in no
case less than 100 mm in depth, prior to start of regular excavation or
backfilling work.
b. Stock pile the removed top soil separate from other excavated
materials in locations designated by the Architect and or spread and
compact with a light roller in areas indicated in the plans or where
directed by the Architect.
a. Cut & fill and machine grade the site area. Deposit materials in
horizontal layer not exceeding 200 mm in depth and compact in
accordance with method A of ASTM D 1557-667. Rough grade
elevations and levels shall be approximately 150 mm below the
bottom of t he slabs on grade, 250 mm below finish grades in areas to
be lawn seeded or landscaped.
3.04 EXCAVATION
56
c. Bottoms of excavation shall be level, free from loose material, and
brought to indicated or required levels in undisturbed earth or in
compacted fill.
d. Excavate with proper allowance made for floor slabs, form erection,
shoring, drain tile, waterproofing, masonry and adequate space for
inspection of foundations.
3.05 DEWATERING
3.07 BACKFILLING
a. All existing earth within building lines that has been disturbed shall
be placed in 150 mm layers and compact ed to 95% of maximum
density at optimum moisture content required for fill in accordance
to AASHO method.
57
PART 4 SOIL BEARING CAPACITY
4.01 If during excavation, conditions discovered at the site does not conform to
the findings of the "SOILS INVESTIGATIONS REPORT" submitted by the soil
engineer, the owner shall immediately notify the architect or his
representative, in writing, of such conditions.
4.02 The soil engineer and the structural engineer shall visit the site and make the
changes in foundation design as necessary.
4.03 No footing shall rest on fill unless directed ot herwise by the structural
engineer.
58
SECTION 02280 TERMITE PROOFING : Bukbok Proofing
PART 1 GENERAL
SCOPE OF WORK
The owner shall hire the services of the specified pesticide company to
furnish all labor, materials, equipment, tools, plants, and services to
complete the termite proofing and bukbok proofing work hereinafter
described.
PART 2 PRODUCTS
For termites, use only "CHLORDANE" diluted with water at the proportion of
ONE (1) PART CHLORDANE to FIFTY (50) parts water. Dilution shall be done at
the job site in the present of the owner's Project Engineer or the Architect.
Use MOTORIZED POWER SPRAYERS ONLY. For bukbok, use
pentachlorophenon (with organs chlorine) colorless, and at ratio 1:100.
PART 3 EXECUTION
a. Foundation Treatment
b. Backfill Treatment
Apply another ONE (1) gallon per linear meter of all backfill materials
as it is being replaced into the trenches after the footing slab are
poured.
Prior to pouring concrete slabs apply ONE (1) gallon per square meter
as an overall treatment.
d. Other Areas
Treat all voids found in masonry walls such as in concrete blocks and
to all surfaces as in concrete blocks and to all surfaces before veneer
finishes are place with ONE (1) gallon per linear meter. PVC pipes
should be treated with powder form Aldrin.
59
e. Wood Drenching
f. Termite Mounds
Demolish and treat all termite mounds within the property if any.
g. Bukbok Proofing
3.02 WARRANTY
The termite proofing work herein called for shall be guaranteed for a
minimum of FIVE (5) years with free semi-annual check-ups and retreatment
in case of infestation.
60
SECTION 02400 SITE DRAINAGE
PART 1 GENERAL
1.01 SCOPE
1.02 PROTECTION
PART 2 PRODUCTS
2.02 MATERIALS
a) Drainage pipes:
d) Area drain catch basin - load - bearing 4.8 Mpa (700 PSI) concrete
hollow blocks (CHB) or reinforced concrete as indicated in the
drawings with steel grating.
PART 3 EXECUTION
3.01 EXCAVATION
b) Rest/ pipes on well tamed solid bedding along its entire length.
61
3.02 BACKFILLING
62
DIVISION 3 CONCRETE
PART 1 GENERAL
1.01 SCOPE
1.02 PROTECTION
c. Exercise care in the choice of the surface forms and form fittings that
will be in contact with concrete.
PART 2 PRODUCTS
MATERIALS
Forms
1. Use the plywood, metal, or surfaced lumber forms where it will best
give the most advantage in the specific concrete work involved.
2. For the beams and columns, use not less than (12mm thick) plywood
forms for exposed concrete and 20mm T & G for covered concrete.
PART 3 EXECUTION
3.01 PREPARATION
a. Check all forms to the shape, lines and dimensions of the members as
called for in the plans.
63
b. Check all formwork for plumbness and correct alignment.
e. Coat all forms with form oil before reinforcement is placed. Remove
all surplus oil on forms.
a. Removal
The results of suitable control tests shall be used as evidence that the
concrete has attained sufficient strength to permit removal of
shorings and supporting forms. Cylinders required for control tests
shall be made in addition to those required by this specifications.
In 3 meters 6mm
In any storey or 6m max 10mm
64
2. Variation from the level or from the grades indicated on the drawings:
In 3m 6mm
In any way or 6m max 10mm
In 12m or more 10mm
Minus 6mm
Plus 12mm
6. Footings
Minus 12mm
Plus 50mm
7. Variation in steps:
I. In a flight of steps:
Rise .. 3mm
Thread 6mm
65
II. In Consecutive steps:
Rise 2mm
Thread 3mm
DIVISION 3 - CONCRETE
PART 1 GENERAL
1.01 SCOPE
1.02 PROTECTION
a. Stack panels clear of the guard of the ground with a fall or drainage.
PART 2 PRODUCTS
MATERIALS
67
appropriate design modification.
PART 3 EXECUTION
3.01 INSTALLATION
Structural decking can be cut using a power saw with suitable disk. When
cutting, the panels should be turned over with the ribs downward. If holes or
openings are required, these are classified as follows:
Fixings
Deckings shall be accurately aligned, side laps fully lapped and the gap
between the abutting ends kept to a minimum. Panels should be aligned
over t he support ensuring a minimum end bearing of 50mm by sliding them
into place with adjacent panels hard up against the precious one and the rib
overlapping the adjacent panel's rib. After panels have been placed over the
supports, they should be secured immediately against wind lift. Where
panels are acting as a work platform, care should be taken not to overload
panel after t hey have been erected. Heavy points should be distributed by
means of t imber planking. Fix panels by use of nail directly to beam
formwork.
Propping
68
Provide caneite or similar materials between the props and panels to reduce
the effect of propping line since the exposed soffit will be used as ceiling.
Propping may be erected before or after the installation of the decking and
should be left until the concrete has reached sufficient strength of at least
70% of its design strength.
Side lap shall be fastened by 16mmXgalO Hex head self drilling and tapping
screws which can be placed either through the side or through the top of the
ribs at quarter points of the span.
3.03 Inspection
Decking panels must be clear of grease, oil and dirt. The concrete should be
placed continuously and if the placing is interrupted, the construction joints
should be provided by stop boards located over supporting beams. The
concrete should be placed in accordance with Section 03300 of this
specifications. In addition, pouring shall be done parallel to the panels, this
is very important!
69
SECTION 03200 CONCRETE REINFORCEMENT
PART 1 GENERAL
1.01 SCOPE
Protect steel reinforcement adequately from rusting and store under cover.
1.03 TESTING
PART 2 PRODUCTS
2.01 MATERIALS
a. Steel Bars
1. Shall be new and free from rust, oil, grease, defects or kinks.
PART 3 EXECUTION
3.01 PREPARATION
b. All bars shall be bent cold. Bends for stirrups and ties shall shall be
made around pins with & diameter of at least twice the thickness of
70
the bars; for bars 25mm and smaller, six t imes the thickness; for
a. Metal Reinforcement
1. Placing shall be in accordance with the plans furnished. Refer
to the Engineer in case of doubt in placing of steel.
b. Bar Spacing
Clear distance between parallel bars shall be one and one half
(1 Vi) times the diameter of t he bars.
2. Clear distance shall not be less than 11/ 3 times the maximum
size of aggregate, nor less than 25mm.
a. Splices
b. Offsets
71
Where offset, the slope of the included portion shall not be more
than one on six (1:6) and in case of tied columns, the ties shall be
spaced 75mm on center for a distance of 300mm below and above
the point of offset.
72
SECTION 03300 CAST-IN PLACE CONCRETE
PART 1 GENERAL
1.01 SCOPE
proportioning
mixing
placement
curing and
finishing of concrete
All strength of concrete shall be at least 24 Mpa for slabs, stairs, beams,
columns, tie beams, and footings, and 21 Mpa for slab on fill, and 10 Mpa for
temporary encasement of dowel bars for all roof/ floor/ tie beams towards
phase 2 area, or as indicated on the Construction Notes.
PART 2 PRODUCTS
2.01 MATERIALS
a. Cement
73
b. Concrete Aggregates
c. Water
Use water that is clean and free from injurious amounts of oils, acids,
alkali, organic materials or other deleterious substances.
d. Concrete Additives
74
b. Measurement
b. Let the mixer be of an approved size and t ype which will insure a
uniform distribution of material t hroughout the mass. Equip it with a
DEVICE FOR ACCURATELY MEASURING AND CONTROLLING THE
AMOUNT OF MIXING WATER IN EACH BATCH.
PART 3 EXECUTION
3.01 PREPARATION
a. Inspect and clean all forms and check all installations before placing
75
concrete.
c. Keep conveyors full of concrete and keep ends buried in the newly
placed concrete as pouring progresses.
e. Construction Joints
a. Finished Surface
76
3.04 REPAIR OF CONCRETE
a. Imperfections
b. Large Bulges
c. Drypack Filling
1. Use for holes having at least one surface dimension less than
the depth of the hole.
e. Concrete filling shall be used for: holes extending entirely through the
concrete for holes which are greater in the are than 1,000 square
centimeter and deeper than 10 centimeter and for holes in reinforced
concrete which are greater in area than 500 square centimeters and
which extend beyond reinforcement.
g. Fillings shall be bonded tightly to the surfaces of the holes and shall
be sound and free from shrinkage, cracks and dummy areas, after the
fillings have been cured and dried.
77
3.05 FLOOR FINISHES
78
DIVISION 4 - MASONRY
PART 1 GENERAL
1.01 SCOPE
PART 2 PRODUCTS
2.01 MATERIALS
2.02 MIXES
Cement
2 parts sand,
PART 3 EXECUTION
Installation
1. Scratch Coat: Apply with sufficient force and materials to form full
keys or bond. Cross scratch as soon as scratch has attained initial set
and apply brown coat as soon as practicable.
2. Brown Coat: Scratch or broom for bond of finish coat and allow to
set hard. Keep brown coat moist until finish coat is applied.
79
3. Finish Coat: Bring to true, even surface with rods, dries and trowel
smooth, leaving finished surface free from tool marks and blemishes.
Keep cement plaster moist for at least 3 days and protect against
rapid drying until cured.
Lay all solid and structural red bricks with 10mm thick horizontal and
vertical mortar joints.
1. Provide the same mixture of gray and white cements for patching
mortar used to fill holes and imperfections, but should be a stiffer
mixture and the cement and sand proportions should be the same as
those used in the concrete.
2. Never steel trowel patches, but finish with wood or cork floats.
80
SECTION 04200 UNIT MASONRY
PART 1 GENERAL
1.01 SCOPE
1.03 SUBMITTALS :
a. Samples:
Within 35 days after award of contract, and before any concrete unit
masonry materials are delivered to the jobsite, submit one sample of
the proposed concrete masonry units with the name and address of
the manufacturer to the Architect for his approval.
b. Certification :
PART 2 PRODUCTS
2.01 MATERIALS
81
2. MORTAR
3. REINFORCEMENT STEEL:
4. WATER :
Water used in mixing mortar shall be clean and free from injurious
amounts of oils, acids, alkalies, salts, organic materials, or other
substances that may be deleterious to concrete or steel.
5. GROUT:
6. ADMIXTURES:
PART 3 EXECUTION
a. General:
2. Mix mortar at least three minutes after all materials have been
added. The actual mixing shall not be less than two minutes.
3. Mix only as much mortar as can be used in one hour after water has
been first mixed into the batch.
82
b. Ret empering:
3.02 INSTALLATION :
a. General:
1. Lay up all walls in running bond, plumb, level, and true to the lines
and dimensions indicated on the Drawings.
2. Do not used chipped or broken units; if any such units are discovered
in the finished wall, the Architect may require their immediate
removal and replacement with new units at no additional cost to the
Owner.
b. Dampening:
c. Laying Up :
1. Place all units in mortar with full shoved bed and head joints.
d. Reinforcement :
e. Tooling:
83
3.03 GROUTING :
a. General:
Perform wall grouting in strict accordance with the provisions for high
lift grouting as described in Chapter 24 of the Uniform Building Code,
1970 edition.
b. Timing:
3.04 CLEANING UP :
b. Cleaning:
1. Clean all surfaces of the concrete unit masonry as required for proper
application of the specified finishes.
84
DIVISION 5 - METALS
PART 1 GENERAL
1.01 SCOPE
Furnish material and equipment and perform labor and services required to
complete fabrication and erection of all structural steel.
PART 2 PRODUCTS
2.01 MATERIALS
e. Use only approved brand of red lead paint and linseed oil for all shop
painting for structural steel.
85
PART 3 EXECUTION
b. Make surface to be welded free from scale, slag, rust, grease, paint
and any other foregoing material except that mill scale which
withstands vigorous wire brushing may remain.
g. Never exceed the separation between laying surfaces of lap joints and
butt joints on a backing structure by 1.5mm.
h. Bring the fit of joints at contact surfaces which are not completely
sealed by welds, close enough to exclude water after painting.
86
m. Let all complete penetration butt welds by manual welding except
when produced with the aid of backing material or welded in the flat
position from both sides in square-edge material not more than 8mm
thick with opening not less than one-half t he thickness of the thinner
parts joined, have the root of the initial layer gouged out on the back
side before welding is started on that side. Weld so as top secure
sound metal and complete fusion t hroughout the entire cross-
section. With butt welds made with use of a backing of the same
material as the base metal, have the weld metal thoroughly fused
with the backing material.
3.02 BOLTS
a. Tighten all bolts to a bolt tension not less than the proof load given in
the applicable ASTM Specifications for the t ype of bolt used.
3.03 TOLERANCES
c. Let completed members be free from twists, bends and opens joints.
Sharp kinks or bends shall be the cause of rejection of materials.
87
after inspection, approval, and before leaving the shop.
3.05 INSPECTION
3.06 IDENTIFICATION
88
SECTION 05170 MISCELLANEOUS METALS
PART 1 GENERAL
1.01 SCOPE
Furnish material and equipment and perform labor required to complete all
metal work which include:
a. Steel gussets, sag rods, turnbuckles, shear plates, erection plates and
angles, etc. for roof framing system
b. Steel windows and grilles
c. Steel Frames and facing for doors
d. Handrails and railings
PART 2 PRODUCTS
PART 3 EXECUTION
3.01 WORKMANSHIP
a. Make all work well formed to shape and size shown and assemble as
detailed.
b. Cut, shear and punch to produce clean, true line and surfaces with
burrs removed.
89
DIVISION 6 - CARPENTRY
PART 1 GENERAL
1.01 SCOPE
d. Temporary protection
PART 2 PRODUCTS
2.01 LUMBER
90
c. Refer to drawings showing Materials and Finishes.
d. Substitution of Lumber
Plates, straps, nails, spikes, bolts , joists, hangers, rods, dowels, fasteners and
miscellaneous iron and steel items shall be of sizes and types to rigidly
secure member in place.
PART 3 EXECUTION
a. Fit carefully mortise and tenon joints of all framings including tongues
and grooves of sheathing. Anchor all frames coming in contact with
concrete, unless otherwise specified, by means of 20 D nails,, spaced
the contact surfaces. Plane and dress side of frames that will receive
the wallboards of sidings.
91
SECTION 06220 MILLWORKS
PART 1 GENERAL
1.01 SCOPE
Wood jambs
Wood shelvings
Cabinets
Wood slats
Wood trims
PART 2 PRODUCTS
2.01 LUMBER
In dried quarter sawn containing not more than 14% moisture, free from
imperfections impairing its strength and finish.
2.02 PLYWOOD
For interior plywood, use Class A plywood whose specie and thickness shall
conform to schedule and drawings.
92
PART 3 EXECUTION
3.01 WORKMANSHIP
a. Make all wood finish, and millwork true to details, clean and sharply
defined.
3.02 FINISH
b. Separate with % inch stone-cut joints all interior trims set against
concrete, masonry or wood.
93
b. Use sound kiln-dried lumber or plywood.
c. Erect cabinets straight level and plumb and securely anchor in place.
3.07 HARDWARE
94
DIVISION 7-THERM AL & MOISTURE PROTECTION
PART 1 GENERAL
1.01 SCOPE
1. Integral waterproofing for all concrete flashing of metal and clay tile
roofing.
See drawings and details for location and extent of the waterproofing
requirements.
PART 2 PRODUCT
2.01 MATERIALS
-Waterproofing Membrane
PART 3 EXECUTION
3.02 Store and protect waterproofing materials from damage, weather moisture
and extreme temperature with extraordinary care.
3.03 Clean, free from holes and projections, smooth and dry all surfaces to
receive waterproofing materials. The Contractor shall perform the necessary
surface preparation. Immediately before application of waterproofing, clean
surface and secure approval. No application of waterproofing is permitted in
wet weather.
95
SECTION 07320 TILED ROOFING
PART 1 GENERAL
SCOPE
Fitting and installation of Fish-scale sheet tiles for eaves and stair
roofing, wire strap/ anchor units as well as the installation of
supplementary materials to make the roof watertight and leakproof.
See drawings and details for sizes and location of work required.
PART 2 PRODUCTS
MATERIALS
PART 3 EXECUTION
a. Install the first row of fish-scale roof tiles starting from the eaves.
c. Anchor each tile using wire ties or screws in accordance with PART 2.
96
SECTION 07400 METAL ROOFING
PART 1 GENERAL
SCOPE
See drawings and details for sizes and location of work required.
PART 2 PRODUCTS
MATERIALS
Substrate Metal: Galvanized steel sheet, using annealed and tempered cold
rolled steel coils hot-dipped to PNS 67:1986 Standard (i.e at least 215 g/ m2).
All costs oven-baked to meet properties of JIS G 3312 Standard including salt
spray test duration of at least 500 hours.
PART 3 EXECUTION
a. Lay down the ribbed roofing tiles starting from the end opposite the
prevailing wind.
b. Lay and install the first sheet with the turned down edge towards the
outside of the area to be covered.
c. Overlay the next sheet in such a manner that the exposed edge is
turned down and the covered edge is turned up.
97
f. Side lap fasteners shall be done by rivets and washers paced from 12"
to 18" on centers.
98
DIVISION 8 - DOORS & WINDOWS
PART 1 GENERAL
1.01 SCOPE
B. Wood doors
See drawings and details for sizes, location extent and other requirements.
PART 2 PRODUCTS
All Steel casement windows shall be the sizes shown on the drawings, low
carbon hot-rolled steel frame. Vent sections shall be mitered and electrically
welded with exposed surfaces ground smooth. Each vent shall have a solid
brass, polished, camlocking handle and strike. All steel casement windows
shall be shop-finished with a dip coat of dark red primer.
Stiles and rails shall be constructed of 14 gauged pressed steel tube with lock
seam. Steel panels shall be constructed from 16 gauge annealed and patent
leveled sheets. Corners shall be welded construction with all joints face
welded and ground smooth. Glass panel mountings, designed for inside
glazing with steel clips and bed putty, shall be securely and neatly welded to
rails and stiles. All doors and frames shall be thoroughly cleaned of rust and
scales and shall be giver two coat of dark red primer.
99
PART 3 EXECUTION
3.01 INSTALLATION
a. Erect all frames plumbs, square, and true to line and level, with
secure fastening to structures and anchors. Install formed steel
stiffeners and reinforcement within frames at all points where top
screw fastenings are used in connections with embedded strap
anchorage.
c. Shop paint with two coats of air dried zinc chromate rust inhibitive
primer.
d. Clean all surfaces and test all framing and hardwares. Make all repairs
and adjustment to the work, leaving it in a satisfactory condition.
3.02 HARDWARE
Have all metal doors and frames mortised, reinforced, drilled and tapped for
mortise hardware in accordance with templates or hardware finish.
100
SECTION 08200 WOOD DOORS
PART 1 GENERAL
1.01 SCOPE
louver doors
See drawings and details for sizes, location, extent and other requirements.
1.02 SAMPLES
Submit sample corner sections of wood doors and jambs, for approval of the
Architect.
1.03 PROTECTION
Protect doors adequately from scratches, and other stains with heavy
building paper.
PART 2 PRODUCTS
2.01 MATERIALS
2.02 FABRICATION
b. Sand smooth finished door. Provide doors with joints and clean out
cut mouldings.
c. Keep faces from defects or machine marks that will show through the
finish.
Provide doors with cross bonding and edgings. Make face veneer first
quality selected plywood or lawanit as directed in the drawings or as
specified herein. Provide lock blocks of size required for hardware
used.
101
PART 3 EXECUTION
3.01 INSTALLATION
a. Cut, trim, and fit each door to its frame and hardware accurately.
c. Provide not more than 1/ 8 inch clearance at lock and hanging stiles
and not more than % inch at bottom.
d. Round all corners to 1/ 16 inch radius. Bevel slight lock and rail edges.
e. All doors shall operate freely and all hardwares shall be properly
adjusted and functioning.
102
SECTION 08520 ALUMINUM WINDOWS
PART 1 GENERAL
1.01 SCOPE
See drawings and schedules for size, details and location of required work.
b. Submit sample corner sections, hinges, tracks, handles and all other
accessories.
PART 2 PRODUCTS
2.01 MATERIALS
PART 3 EXECUTION
3.01 FABRICATION
b. Cut join and fit rails and stiles to hairlines joints securely reinforced
and jointed by means of concealed fastening wherever possible.
c. Protective Coating
3.03 INSTALLATION
103
b. Set frames plumb and square and brace where necessary to prevent
distortion.
3.04 ADJUSTMENTS
104
SECTION 08710 FINISH HARDWARE
PART 1 GENERAL
1.01 SCOPE
1.02 SAMPLES
Submit samples of locksets, hinges, door pulls, door stops, door closers and
PART 2 PRODUCTS
2.01 MATERIALS
A. Locks
1. All steel doors and other doors specified in the schedule of doors and
windows shall be equipped with "ASSA" double cylinder locksets or
any approved equivalent. Cylinder lock to be equipped with latch
bolts operated by lever handles and dead bolt operated by key lever
handles and dead bolt operated by key or thumb-turn on inside and
key from outside.
B. Latches
Bar doors for shower and toilet compartments shall be provided and fitted
with rim bolt and an indicator, chromium plated and polished.
C. Hinges
1. All steel door with steel facing shall be provided with three heavy
steel hinges.
105
2. All steel door with glass panel shall be provided with heavy duty pivot
hinges to be fixed on top and bottom rails.
3. Butt hinges
Each panel of hinged door shall hung on three (3) butts for doors 1.80
or less in height and four (4) butts for doors 2.10 m in height. The size
of the butt hinges shall conform to the Schedule of Doors and
Hardwares.
4. Concealed Hinges
a. For doors that will strike on object rubber bumper provide or door
stop. Type and location of installation to be approved by the
Architect.
b. For heavy frequency door with closer and mortise locks provide
stainless steel push plates.
d. For silencing the door when it strikes the stop strip and to prevent
rattles, install three (3) silencers in t he stop of frame.
PART 3 EXECUTION
INSTALLATION
106
SECTION 08730 WEATHER STRIPPING
PART 1 GENERAL
1.01 SCOPE
all types of weatherstripping in the form of rubber and vinyl strip and
caulking
1.02 Submit samples of weather strip elements for approval by the Architect.
PART 2 PRODUCTS
MATERIALS
PART 3 EXECUTION
107
SECTION 08800 GLASS AND GLAZING
PART 1 GENERAL
1.01 SCOPE
Furnish glass free from imperfection and water marks and other materials
and equipment and perform labor required to complete all glass and glazing
work.
1.02 SAMPLES
1.03 PROTECTION
PART 2 PRODUCT
GLAZING
PART 3 EXECUTION
3.01 GLAZING
a. Prevent glass from all contact with metal or any hard or sharp
materials by use of resilient shims placed at quarter point.
108
b. Use resilient sealants.
d. Install glass only in openings that are rigid, plumb and square.
109
DIVISION 9-FINISHES
PART 1 GENERAL
SCOPE
all:
PART 2 PRODUCT
MATERIALS
PART 3 EXECUTION
b. Apply the scratch coat with sufficient material and pressure to ensure
a good bond and then scratch to a rough surface. Provide a thickness
of 3/ 8" for scratch boat. Dampen with water before applying brown
coat.
c. Apply brown coat, one day after applying scratch coat, with a
thickness of 3/ 8" and level to a flat even surface. When stiff enough,
trowel with a wooden float and cross hatch or broom lightly and
evenly to secure a good mechanical bond for the finish coat. Wet the
surface and keep from drying out for at least three (3) days.
d. Apply finish coast seven (7) days after the application of brown coat.
Provide thickness of 1/ 8', keep the finish coat damp but not saturated
for a period of seven (7) days.
110
SECTION 09310/ 09390 CERAMIC/ CEMENT TILEWORK
PART 1 GENERAL
1.01 SCOPE
Furnish materials and equipment and perform labor required to complete all
types of tile works.
See drawings and details for location and extent of work required.
PART 2 PRODUCTS
MATERIALS
PART 3 EXECUTION
3.01 APPLICATION OF SCRATCH COAT
b. On masonry, first apply a thin coat with great pressure, then bring it
out sufficiently to compensate for the major irregularities on the
masonry surfaces to a thickness of not less than % inch at any point.
c. Evenly rake scratch coats, but not wash coats, to provide good
mechanical key for subsequent coats before the mortar has fully
hardened.
Il l
b. Clean concrete sub-floor t hem moisten but not soak. Afterwards
sprinkle and spread the mortar on the setting bed.
e. After setting bed has set sufficiently to be worked over, sprinkle dry
cement over surface and lay tile.
f. Keep tile joints parallel and straight over the entire area by using
straight edges.
g. Tamp the tile solidly onto the bed, using wood blocks of size to
ensure solid bedding free from depressions.
h. Lay tiles from center lines outward and make adjustments at walls.
c. Apply the mortar bed over an area no greater than can be covered
with tile while the coat is still plastic.
g. Press tile firmly into the bed and beat into place within 1 hour.
112
I. Within 1 hour after installation of tile, remove strings from string-set
tile and wet the faces of face-mounted tile and remove the paper and
glue. Avoid using excess water. Adjust any tile that is out of
alignment.
3.04 GROUTING
a. After tile has sufficiently set, force a maximum of grout into joints by
trowel, brush or finger application.
b. Before grout sets, strike or tool the joints of cushion-edged tile to the
depth of the cushion.
c. Fill all joints of square-edged tile flush with the surface of the tile. Fill
all gaps or sips.
d. During grouting clean all excess grout off with clean burlap, other
cloths or sponges.
3.05 CLEANING
Sponge and wash tile thoroughly with clear water after the grout has
stiffened. Then clean by rubbing with damp cloths or sponges and polish
clean with dry cloth.
113
SECTION 09650 VINYL FLOOR FINISH
PART 1 GENERAL
SCOPE
PART 2 PRODUCT
MATERIALS
Where shown or scheduled in the drawings, all floors finished with vinyl tiles
shall be constructed 3mm or 4mm below the finished floor levels and shall
be troweled to a smooth and even surface free from pits, visible joints,
marks or other imperfections. Tiles to be used shall be Vinyl Quartz
Tiles or equivalent, 3mm. In thickness and shall be of dimension, color and
laying pattern to conform to the schedule as indicated in the drawings.
PART 3 EXECUTION
A. Preparation of Surfaces
Clean the floor thoroughly of dirt, grease, paintdrops, etc., leaving the
surface suitable for the installation of the tiles. The resulting surface shall be
smooth, even thoroughly dry and clean.
B. Laying
Before tiles are laid, apply over the surface a coat of asphalt emulsion in
accordance with the manufacturer's specifications. In laying the tiles over
this emulsion coat, the edges of the tiles shall be carefully matched and the
seems cut. All seams and edges shall be cemented with asphalt cement. The
surface of the finished floor shall be left smooth, clean and in first class
condition.
At completion of the work, clean all vinyl tiles and remove all cement, dirt or
other foreign substance. Apply two coats of emulsion wax and polish each
coat to a gloss and shiny finish.
114
SECTION 09900 PAINTING
PART 1 GENERAL
1.01 SCOPE
See drawings for location, quantity and extent or surfaces to receive paint
and varnish.
PART 2 PRODUCT
MATERIALS
PART 3 EXECUTION
a. Mix paint with proper consistency. Apply paints evenly and brush
efficiently to minimize brush marks.
e. Touch up knots, pitch streaks, sappy spots, etc. where finish calls for
interior paint or enamel. For exteriors, use and approve sealer.
115
f. Sand smooth woodwork to be finished with enamel or varnish. Use
fine sandpaper between coats of enamel of varnished applied to
wood or metal to produce an even smoot h surface.
h. Do necessary putting of nail holes, cracks, etc. after the prime coat
has been applied. Bring putty flush with adjoining surface in a neat,
workmanlike manner.
116
D IV IS ION 1 0 - S P E C IA L T IE S
PART 1 GENERAL
SCOPE
PART 2 PRODUCTS
PART 3 EXECUTION
117
D IV IS ION 1 0 - S P E C IA L T IE S
PART 1 GENERAL
SCOPE
toilet accessories
See drawings and details for sizes and locations of work required.
PART 2 PRODUCTS
2.01 MATERIALS
PART 3 EXECUTION
Furnish and install all toilet accessories true to line, plane and level, in
accordance to manufacturer's specifications.
118
DIVISION 11- MECHANICAL
I. GENERAL
2. Drawings Specification
2.2 All dimensions location of fixtures, equipment floor and roof drains,
risers and pipe chase shall be verified on the architectural drawings and
manufacturer's catalogue.
3. Intent - It is not intended that the drawings shall show every pipe, fitting,
valve and appliance. All such items show whether specifically mentioned or not, or
indicated on the drawings, shall be furnished and installed if necessary to complete
the system in accordance with the best practice of the plumbing trade and to the
satisfaction of the Architect, the Engineer and the Owner.
5. Shop Dr awi ng-The Contractor shall submit to the ARCHITECT and the
Engineer, for approval, four (4) copies of all s hop drawings of details and connection
not shown on the drawings or deviation thereof but required for the work. The
Contractor shall certify that the drawings have been checked for dimensions,
materials, erection details and conform to the intent of the drawings and
specifications.
119
6. Record Drawings
6.1 The Contractor shall during the progress of work, keep a record of the
actual installation from that shown on the contract drawings.
6.2 Upon completion of the work, the Contractor shall submit four (4)
copies of as-built drawings indicating the work as actually and finally
installed.
7. Guarantee - The Contractor shall guarantee that the plumbing system is free
form all defective workmanship and materials and will remain so for a period of one
(1) year from the date of acceptance of the work. Any defects, appearing within the
aforesaid period shall be remedied by the Contractor at his own expense.
8. Permits - The Contractor shall be responsible for securing all the required
construction and operation permits and pay all necessary fees thereof. Copies of
inspections shall be submitted to the Owner.
9. Codes and Standards - The work under this contract is to be installed with
reference to the latest requirements of the following:
II. MATERIALS
1. Quality Assurance - All materials shall be used shall be new and shall
conform with the reference codes and standards. Use or materials shall
further be governed by other requirements, imposed on other sections of
t hese specifications. Materials shall be subject to test necessary their fitness
if so requires.
120
2. Alternate Materials - Use of any material, not specified in these
specifications may be allowed provided such alternate has been approved by
the Architect and Engineer and provided further that a test, if required , shall
be done by an approved agency in accordance with the generally accepted
standards.
4.2 Moldex blue or approved equal for all water line piping.
4.3 Sanimold orange uPVC with exclusive O-ring or approved equal for all
water lines and vents.
4.6 75 mmO Sanimold Orange uPVC pipes or approved equal for all
downspouts.
5. Concrete Piping
5.2 Minimum wall thickness - Plain concrete for 250 mmO and smaller
pipes; Reinforced concrete for 300 mmO and bigger pipes, class IV
6.3 Joints - Threaded joints for pipe sized 50mm and smaller; Welded or
flanged joints for pipe sizes 65 mm and bigger.
121
6.4 Fittings - Malleable iron ASTM A - 197 for threaded fittings and steel
ASTM A - 126 for flanged fittings.
6.5 Valves - Bronze, ASTM B - 62, 1035 Kpa for 50 mm and smaller; All
iron, bronze fitted, 1035 Kpa for 65 mm and bigger.
6.6 Pipe Sealant - Teflon tape for threaded joints and rubber gasket for
flanged joints.
8.1 Pipe support shall be fabricated with flat bar, round bar and angular
bar of appropriate size.
9. Pipe Sleeves
EQUIPMENT
1. Quality Assurance - All equipment to be used shall be new and shall conform
with the reference codes and standards. The manufacturer shall provided
representatives for start-up supervision.
2. Operation & Maintenance Manual - The manufacturer shall provide four (4)
copies of operation & maintenance manual, including spare parts list to the
Owner.
3.1 Cabinet - Fire hose cabinet shall be flushed to the wall. Frame shall
be gage 16 steel with white interior and red exterior enamel paint
finish over primer. Door frame shall be aluminum.
122
3.2 Unit shall consist of the following:
One (1) - 40 mm combination fog and solid stream nozzle brass finish
One (1) - Semi automatic rack, brass finish and hose nipple
One (1) - 4.5 Kg. Dry chemical ABC extinguisher. UL/ FM listed
INSTALLATION
1. Workmanship
1.1 The work throughout shall be executed in the best and most
t horough manner to the satisfaction of the Architect and the Engineers, who
will jointly interpret the meaning of the drawings and specifications and
shall have power to reject any work and materials which in their judgment,
are not in full accordance therewith.
1.2 This Contractor shall assume unit responsibility and shall provide the
services for a qualified Engineer to supervise the complete installation of
equipment and systems and who shall be available for
conducting the finial acceptance tests.
123
1.3 All equipment shall be installed in accordance with the
manufacturer's standard. Certificate of compliance by the manufacturer's
representative shall be submitted to the Owner.
2.1 Excavating
Trenches for all underground pipe lines shall be excavated to the required
depth and grades.
Bell holes shall be provided so that the pipe shall rest on well tamped solid
ground for its entire length.
Pipes in trenches shall be laid true line and grade on a stable or suitably
prepared foundation, each section of t he pipe being bedded and bottom of
the trench shaped to fit the lowest quadrant of the pipe circumference.
Pipe shall not pass through columns, footings, beams of ribs, except where
noted on the drawings.
2.3 Backfilling
After pipe lines have been tested, inspected and approved by the Architect
and prior to backfilling, all forms and bracings shall be removed and the
excavation shall be cleaned from trash and debris.
Materials for backfilling shall consists of approved materials and shall be free
of debris or big rocks.
3. Water Piping
3.1 All piping shall be installed parallel to building line unless otherwise
noted.
124
3.2 The piping shall be extended to all fixtures, outlets and equipment
from the valve installed in each branch.
3.3 The piping system shall be installed with a fall toward a main shut-off
valve and drains. Ends of pipes to fixtures shall be capped with pipe
extension of 30 cm long.
3.4 All pipes embedded underground shall have at least two (2) coat of
tar or carboline.
3.5 All hot water piping shall be insulated except those embedded in
concrete or otherwise noted.
3.6 All water pipe connections to equipment shall be provided with gate
valves and unions or flanges to provide access and maintenance.
4.1 Clean-outs - Clean-out shall be of the same size as the pipe. For pipes
100 mm and larger, use 100 mm clean-out.
4.2 Trap - Each fixture trap except those cast integral or in combination
with fixtures in which the trap seal is readily accessible or if the trap is
removable shall have an accessible brass trap screw of ample size.
Floor, Wall and Ceiling Plates - Provide chromium plated metal plates of the
same materials as the pipe for all exposed piping passes through floors, walls
and ceilings.
6.1 Fixture Support. All fixtures and equipment shall be supported and
fastened in a safe and satisfactory manner.
6.2 Pipe sleeves shall be installed and properly secured in place at all
points where pipes pass through masonry or concrete, except
unframed floors on earth.
125
Trapeze hangers may be used in lieu of separate hangers on pipes
running parallel to and close to each other.
7.2 Painting
Pipe hangers supports and all other iron work in concealed spaces
shall be thoroughly cleaned and painted with one coat of asphalt
varnished.
126
8. Testing and Disinfection
8.1 Testing
8.2 Disinfection
The chlorine dosage shall be such as to provide no less than fifty (50)
parts per million of available chlorine, following a contact period of
not less than sixteen (16) hours, the heavily chlorinated water shall
be flushed from the system with clean water until the residual
chlorine content is no greater two tenth ppm.
127
DIVISION 12 - ELECTRICAL WORKS
PARTI
1.1 The General Conditions and Provisions of the Civil Works Contract, not in conflict
with these Specifications and the Drawings, form part of and are included in this
Section of these Specifications.
The CONTRACTOR is advised to visit the site and satisfy himself as to local conditions
and facilities, the nature of the soil, and ascertain such other conditions affecting his
work. He will be deemed to have done this before preparing his proposal and no
subsequent claims on the grounds of inadequate or inaccurate information will be
entertained.
1.3 SUB-CONTRACTOR
The CONTRACTOR shall not sub-contract the whole or any part of the work without
the written consent of the OWNER. The CONTRACTOR as if he himself were
undertaking the work.
The CONTRACTOR shall execute all works in a neat and workmanlike manner and
shall do all necessary work whether it is clearly specified on these Specifications or
shown on t he Drawings or not. All works shall be done in accordance with the best
practices employed in modern electrical installations.
The CONTRACTOR shall employ only competent and efficient workmen and shall,
upon written request of the ARCHITECT, discharge or otherwise remove from work
any employee who is, in the opinion of the ARCHITECT careless or incompetent or
who obstruct the progress of the work or act contrary to instructions or conducts
himself improperly.
All materials shall be new and shall conform to the Technical Specifications. All
materials shall be the standard products of reputable manufacturers and shall bear
the name of the manufacturers.
All materials shall be subject to the approval of the ARCHITECT. This approval does
not relieve the CONTRACTOR of the responsibility of inspecting such materials for
defects or non-conformity of the Specifications.
Where the Technical Specifications or Drawings give the name of the manufacturers
and/ or catalogue, number of materials, it is given as guide to the size, strength,
128
quality or class of material desired and shall be interpreted to mean that item or
another fully equal for the service intended. Substitution shall be subject to the
prior written approval of the ARCHITECT.
The apparent silence of the Specifications and Drawings as to any detail of apparent
omission from t hem or any detailed description concerning any material shall be
regarded to mean t he only materials of first class quality shall be used.
The CONTRACTOR shall, within ten (10) days after the award of the Contract, submit
for the approval of the ARCHITECT, a listing of the materials he proposed to use in
t he work including such sample catalogues, drawings or descriptive data as maybe
required by the ARCHITECT or risk the subsequent rejection of the same.
Any defective work, whet her the result of poor workmanship, defective materials,
damage t hrough carelessness or any other cause found to exist prior to acceptance
of, or final payment from the work shall be removed immediately and replace by
work and materials which conform to those Specifications or shall be otherwise
remedied in an acceptable manner. This clause shall have full effect regardless of the
fact that the work may have been done with the full knowledge of the ARCHITECT.
Defective materials which has been subsequently corrected shall be re-used upon
approval of the ARCHITECT.
These Specifications and Drawings indicate t he general layout of the system and the
CONTRACTOR shall be responsible for the proper installation of the system without
substantial alternatives or modifications.
Whet her field conditions or exigencies of construction make departure from these
Specifications and Drawings necessary, details of such departure and reason thereof
shall be submitted to t he ARCHITECT for approval.
The CONTRACTOR shall examine and shall be familiar with the Specifications and
Drawings of the Civil Works, the Refrigeration Works and the Sanitary Works. He
shall arrange his work and dispose his materials of other Contractors. Should the
CONTRACTOR cause damage to any other Contractor on the work, the CONTRACTOR
shall upon due notice settle with such Contractor by agreement or by arbitration.
The CONTRACTOR shall be liable for any claims by other Contractors against the
OWNER on account of such damage.
129
1.9 INSPECTIONS AND TESTS
The ARCHITECT or his representative shall be allowed access to all parts of the
works at all time and the CONTRACTOR shall furnish such information and assistance
as maybe required to make a detailed inspection. Materials and installations shall be
subjected to tests as are deemed necessary by t he ARCHITECT to properly ascertain
their fitness both during and after installation is completed. The cost of such tests
shall be borne by the CONTRACTOR.
The CONTRACTOR shall do all cutting and patching required by the work, engaging
men who are skilled in the particular trade to do all the work. Surfaces obtained by
cutting and patching shall exactly match surrounding work so that there will be no
evidence of laceration or patching.
The CONTRACTOR shall be responsible for all injuries to persons and damage to
property caused by the works or by workmen and shall be liable for any claims
against the OWNER on account of such injury and/ or damage. The CONTRACTOR
shall likewise take necessary precautions to protect the property of the OWNER
against rain or other inclemencies of the weather or theft due to the performance of
his work. The CONTRACTOR shall be liable for any such damage or loss.
The CONTRACTOR shall make all arrangements and pay for the provisions of the
necessary electricity supply required for the work and shall clear away all temporary
installations before and upon completion of the work.
The CONTRACTOR shall not withdraw from the site until the OWNER has agreed that
no further work is necessary at the time.
The CONTRACTOR shall not suspend or fail to make proper progress with the work
wit hout justifiable cause. The OWNER, in the event of delays or suspension of the
work, shall inventory all the materials on the site and make arrangements as are
necessary t o have the work completed by others.
1.15 CLEANING UP
During the process of the work and on the completion of the project, the
CONTRACTOR shall remove from the premises all dirt, debris, rubbish and waste
materials caused by him in the performance of his work. He shall remove all tools,
130
scaffoldings and surplus materials after completion and acceptance of the work. All
salvageable materials removed from the existing building should be turned over to
t he OWNER for proper inventory and disposal.
The CONTRACTOR shall submit to the ARCHITECT with such promptness as not to
cause delay in his work or that of any CONTRACTOR, t wo (2) copies of all shop
drawings and schedules required by the work. The CONTRACTOR shall make all
corrections required by the ARCHITECT and submit t wo (2) corrected copies and
other copies as needed. The ARCHITECT'S approval of such drawings shall not relieve
the CONTRACTOR of responsibility for the deviations at the time of submission, nor
shall it relieve the CONTRACTOR of responsibilities for errors of any sort.
The work under this contract shall be made in accordance with the requirements of
the latest edition of the Philippine Electrical Code, the rules and regulations of the
local enforcing authority and the requirements of the local power utility firm.
Nothing contained in these Specifications or shown on the Drawings shall be
constructed as to conflict with the national and local ordinances and laws governing
t he installations of electrical works, and all such laws and ordinances are hereby
made part of t hese Specifications. The CONTRACTOR is required to meet the
requirements thereof.
All permits, certificates and fees required for the work shall be obtained by and at
the expense of the CONTRACTOR. The CONTRACTOR shall furnish t he ARCHITECT
and t he OWNER a copy of the Final Certificate of Electrical Inspection and Approval
from the proper government authorities after t he completion of the work. The
CONTRACTOR shall prepare all plans and other related document s required by the
approving authorities.
The work of the CONTRACTOR consists of furnishing of all plants, labor, equipment
and materials and performing of all operations in connection with the electrical
system shown on the Drawings, their tests and inspections, complete and in
accordance with these Specifications and Drawings and subject to the terms and
conditions of the Contract, and all other labor and materials not specifically
mentioned under sections, to bring the electrical system to operating conditions and
be ready for use by the OWNER.
131
The scope of work of the CONTRACTOR includes the ff:
2. Separate concrete manholes/ handholes for power and communication lines from R1
to R3 and R1 to A2 as shown in the plans.
3. Underground concrete envelope for both power and communication conduits from
the concrete pedestal to R3 and A2.
4. Underground power and communication conduits with its corresponding wiring and
wiring devices from the concrete pedestal to R3 and A2 as indicated in the plans.
8. Any and all other works involved in providing the complete operations of the
Electrical and Auxiliary systems and all other items not mentioned but necessary to
complete the said work in accordance with t he plans, specifications and other
related documents.
1. Incoming underground service entrance for power and communication lines with
concrete envelope from R3 of the Site Development Plan to the Main Distribution
Panel (MDP) of the building.
2. Power and lighting distribution system including panel boards, circuit breakers and
stub-out for future loads.
3. A system of lighting and power wiring including feeders, branch circuits and
connections to lighting and power outlets.
4. Supply and installation of power and lighting fixtures and wiring devices.
5. Conduit layout, cables, boxes and receptacles and stub-outs for the complete
installation of the fire alarm system including the fire alarm equipment and the
t elephone system excluding the telephone equipment.
132
8. Securing the necessary permits and payment to fees incidental to the work.
9. Any and all other works involved in providing the complete operations of the
Electrical and Auxiliary systems and all other items not mentioned but necessary to
complete the said work in accordance with t he plans, specifications and other
related documents.
1. Incoming underground service entrance for power and communication lines with
concrete envelope from R3 of the Site Development Plan to the Main Distribution
Panel (MDP) of the building.
2. Power and lighting distribution system including panel boards, circuit breakers and
stub-out for future loads.
3. A system of lighting and power wiring including feeders, branch circuits and
connections to lighting and power outlets.
4. Supply and installation of power and lighting fixtures and wiring devices.
5. Conduit layout, cables, boxes and receptacles and stub-outs for the complete
installation of the fire alarm system including the fire alarm equipment and the
telephone system excluding the telephone equipment.
8. Securing the necessary permits and payment to fees incidental to the work.
9. Any and all other works involved in providing the complete operations of the
Electrical and Auxiliary systems and all other items not mentioned but necessary to
complete the said work in accordance with t he plans, specifications and other
related documents.
The following items shall be furnished and installed by others and are, therefore, not
included in the contract.
1. Air-conditioning units
2. Telephone units
133
PART 3 TECHNICAL SPECIFICATIONS
Wiring shall be Rigid Steel Conduit (RSC) and corrugated, flexible PVC conduit.
3.2 GROUNDING
The following shall be grounded in accordance with the Drawings and the
requirements of the Philippine Electrical Code and with standard grouping practices.
Ground resistance shall not exceed 0.5 ohms. Additional ground rods shall be
installed when necessary to obtain this amount. Exposed or accessible ground
clamps, pressure connectors and/ or ground connections shall be brazed. The
CONTRACTOR'S attention is especially called to the double lockout requirements of
Rule 2808 of the Philippine Electrical Code for conduits containing conductors
operating at more than 250 volts to ground.
Service entrance shall be laid underground and should be enveloped with concrete
from MDP to the concrete pedestal as shown in the Site Development Plan and Riser
Diagram. Sizes and locations are also indicated in the Plans.
Panelboards shall be mounted with their centers at 1.4 meters above the floor
unless
otherwise dictated by field conditions.
3.5 FEEDERS
Distribution voltage shall be 220 VAC, single phase, 2-wire unless other wise noted
in the Drawings. Feeder conductors and conduits shall be installed as shown in the
Drawings and no change in sizes shall be made wit hout the consent of the
ARCHITECT.
134
Feeder conductors shall be continuous and without splices between terminals and
boxes.
The DRAWINGS indicate the general methods of installations of all circuit wiring and
t he outlets which are to be supplied from these circuits. Branch circuit conduits shall
be run from outlets to panelboards as direct as building conditions will allow. Circuit
allocations shall be indicated on the Drawings. Where it becomes necessary to
correct any outlet to a circuit other than shown on the Drawings, this shall be done
without extra charge and only upon written consent of the ARCHITECT. No wire
smaller than 3.5 mm2 (# 12 AWG) shall be used for any lighting and power circuits.
The approximate location of each fixture receptacle, special purpose outlet and
switch is indicated on the Drawings. The exact location is to be determined later at
the site as t he work progresses. The right is reserved by the ARCHITECT to change
the exact location of any switch, light and power outlet installed by the
CONTRACTOR in such as manner as to be out of the building construction. Its
position or location shall be corrected at the expense of the CONTRACTOR and
under the direction of the ARCHITECT. Mounting the heights of outlets and switches
shall be as called for on the Drawings.
ALL MOUNTING HEIGHTS SHALL BE VERIFIED FROM THE ARCHITEC BEFORE ACTUAL
INSTALLATION OF THE OUTLET BOXES.
No wires shall be drawn into the raceway until works which may cause injury to the
wires is completed and until permission is granted by the ARCHITECT in writing. Only
powdered lubricant not injurious to cable insulations and raceways shall be used
only when lubrication is necessary.
Solderless pressure connectors of proper sizes shall be used for terminals, tape for
splices of all wires and cables except for branch circuits in which case connectors
shall be surely fastened and shall be such as not to loosen under vibrations and
normal strain.
Branch circuit splices shall be soldered or joined by the use of insulated splicing
devices (wire nuts). All soldered joints must be made mechanically strong before
soldering and shall be carefully soldered without the use of acid, then taped with
rubber tape to a thickness equal to the insulation and with a covering of friction
tape of t wo layers. 3M Scotch tape may be used in lieu of insulated wire nuts.
Where conductors are to be connected directly to devices without the use of lugs,
such as occurs at lighting switches and convenience outlets, the wires shall be
135
formed into a clockwise loop fitted around the screws.
The CONTRACTOR shall install standard pressed steel boxes or cast metal boxes at all
outlets for lights, power and switches and other points as required by the
Construction.
Boxes shall be of approved design and construction, and of such form and
dimension as required to serve the kind of fixtures to be used and the number, sizes
and arrangement of conduits connecting thereof. The allowable conductor fill as
given in Rule 2486 of the Philippine Electrical Code should not be exceeded.
Deep boxes, box rings and raised pressed covers shall be used when necessary to
obtain the required conductor capacity.
All boxes of what ever kind, for all systems shall be provided with a suitable fitting
which shall be either a box or other device or locknut and bushing to receive and
hold and device or fitting to be mounted.
All boxes shall be painted with anti-rust lead paint after installation.
Not more than four 90 degrees bend shall occur in any run. When it becomes
necessary to have more than four 90 degree bends in any run, an intermediate pull
box shall be installed to facilitate the pulling-in of wires.
All conduit runs shall be as called for in the Drawings. Conduits shall be installed in
such a manner as not to weaken or interfere with structure of the building. Conduits
and t ubings shall be concealed within finished wall, ceilings, steel framings or floor
slabs. Exposed conduits shall be run parallel to at right angles with lines of the
building and shall be securely fastened to walls by means of screws or bolts with
expansion sleeves. The use of wooden or lead plug is not permitted. Conduits shall
be cut by hacksaw, the ends shall be reamed after firmly attached to cabinets or
boxes by means of locknuts and bushings.
Fieldmade bends and offsets shall be avoided when possible, but when necessary
shall be made in accordance with manufacturer's recommendations. Trapped
raceways shall be avoided where possible. Care shall be made to avoid lodgment of
dirt or trash in t he conduits, tubing, boxes, fittings and equipment during the course
of t he construction .
136
Conduits below grade line or installed in the ground or fill beneath the floor slab
shall be encased in a rectangular concrete envelop with a minimum thickness of
75mm (3").
The CONTRACTOR shall furnish and install all lighting fixtures as indicated in the
Drawings, including mounting channels and supports. Where the Drawings call for
incandescent lighting ceiling outlets of the screw-shell type, the ceiling receptacles
and lamps shall be furnished and installed by the CONTRACTOR. Lighting fixtures
shall conform to appropriate sections of these Specifications.
4.1 Rigid Steel Conduits shall be hot-dipped galvanized mild steel pipe with an interior
coating and shall be 3 meter lengths including and coupling. All conduits shall be
Japanese manufactured or approved equal.
4.2 Wires and cables shall be insulated for 600 volts. Feeder, branch circuit and service
entrance cables should be copper, soft-drawn and annealed 98 % conductivity. They
should be Type TW or THW as required by the Drawings. All wires and cables shall
be Phelps Dodge or approved equal subject to t he approval of the ARCHITECT.
4.3 Conduit fitting shall be U.S. Underwriters Laboratories (UL) listed or approved local
accessories.
4.4 Panelboards for light and power shall conform to the indications in the Drawings
with respect to supply characteristics and rating of main lugs or main breakers,
number and size of branch circuit breakers.
Panelboards and cabinets shall be dead-front t ype factory assembled of back plan,
main busses, overcurrent and switching units. Cabinets shall be fabricated with code
gauge galvanized sheet steel with cover capped and approved methods of casting.
Cabinets shall permit suitable wiring gutter space all around at least 100 mm (4") or
wider.
Panelboards and trims shall be suitable for the t ype of mounting shown in the
Drawings. The inside and outside of the panelboard cabinets and trims shall be
factory painted and having one rust-proof prime coat and one finish shop of grey
enamel paint. All cabinets and enclosures shall be general purpose, NEMA Type I
137
except where specifically noted in the Drawings.
Circuit breakers for panelboards shall be molded case circuit breaker with quick-
made, quick-break trip free mechanisms. They maybe either plug-in or bolted Q-
type. Circuit breakers shall be as manufactured by GE, ITE, Westinghouse, Mitsubishi
or its equivalent.
Wall switches shall be rated at least 10 amperes, 220 volts. Switches shall be of the
outlet type, spring operated and thumbler type.
Wall receptacles shall be flush mounted, duplex, rated 15 amperes, 250 volts,
parallel slots wit hout grounding slots unless specified in the Plans.
Fluorescent fixtures shall be surface mounted, box type, equipped with a high
power factor ballast, spring loaded lamp holder and standard daylight lamp. Fixture
housing shall be baked enamel, white interior, gauge 22 minimum galvanized steel.
The CONTRACTOR shall submit samples of the lighting fixtures for the approval of
t he ARCHITECT.
GROUNDING
All metallic conduits, panelboards and equipment requiring ground shall be properly
grounded and bonded by means of copper straps. The conduits of each system shall
be grounded by connecting to the nearest water service pipe.
All ground connections shall have clean contact surfaces and shall be tinned and
sweated while bolting. Unless otherwise specified, exposed ground cables shall be
installed in conduits and connections made readily accessible for inspections.
Connections shall not be made underground or concealed in floors or walls.
Connections to ground rods shall be provided with ground walls.
TESTING
Ground Test - The entire installation shall be free from improper grounds and short
circuits. All branch circuits shall be tested for ground and short defects in the
presence of the ARCHITECT or the OWNER. Each panel shall be tested with mains
connected to feeders and all homeruns connected to each assigned branch circuits.
Each individual power feeder shall be tested with the power equipment connected
for proper and intended operation. In no case shall the insulation resistance be less
than that allowed by the regulations for electrical equipment in buildings. Failures
and defects shall be corrected in a manner satisfactory to the OWNER.
4.9 GUARANTEE
The CONTRACTOR shall guarantee that the electrical system is free from defects and
defective workmanship and materials, and will remain so for a period of on (1) year
from date of acceptance of work. Any defects appearing within the aforesaid period
shall be remedied by the CONTRACTOR at his own expense.
139