Professional Documents
Culture Documents
Impacts on Schedule
Overview
• Definitions
• Methods of Delay Evaluation
• Best Practices
2
Classification of Project Delays
(Risk Point of View)
•Non-excusable
•Excusable
–Compensable
–Non-compensable
3
Non-excusable Delays
• Contractor culpable delays impacting
the schedule
5
Excusable Compensable
Delays
• Owner or owner’s agent problems result
in schedule impacts
• Contractor eligible for time extension
• Contractor eligible for extended
“General Conditions” cost
• Contractor has to meet burden of proof
6
Concurrent Delays
Definition:
• “Concurrent Delay” is experienced on a
construction project when two or more
separate delay events occur during the same
time period.
• Multiple causes to a critical path delay with
both contract parties involved. In the
absence of one party’s cause, the other
party’s cause will govern.
• The schedule has more than one critical path
with a separate delay affecting each at the
same time (very rare)
7
Concurrent Delays
• Significance
Determines compensability
• Apportionment:
Where both parties contribute to the
delay neither can recover damages
unless there is clear evidence by which
we can apportion the delay and the
expense attributable to each party
8
Concurrent Delays
Elements:
• Two or more delays occur during the same time period
• Both delays impact the critical path
• Delays may be caused by either or both parties, or
unforeseen events
• In the absence of one delay event, the other delay
event will govern.
Governing Rules:
• The float belongs to the project
• Both parties have the right to use any additional float
• The Critical Path with respect to a specific milestone is
the path with the least total float
9
Concurrent Delays:
Result:
5 excusable (non-compensable) days to contractor
10
Concurrent Delays:
• Concurrent delay by contractor and an uncontrollable
event is excusable but not compensable
Critical Path Activity
✓ Delay events occur
during the same time
Contractor period
5 Days of CP Slippage
Delay: 5
days lost ✓ They impacted the critical
due to path
productivity Critical Path Activity
issues ✓ In the absence of one
delay event, the other
3 days of Rain delay event will govern.
Result:
3 excusable (non-compensable) days
2 non-excusable days
11
Concurrent Delays:
•Concurrent delay by owner and an uncontrollable event
is excusable but not compensable
Critical Path Activity
✓ Delay events occur
during the same time
period
Owner Delay: 15 Days of CP Slippage
15 days lost ✓ They impacted the critical
Critical Path Activity path
resolving a
design issue
✓ In the absence of one
10 days of Rain delay event, the other
delay event will govern.
Result:
10 excusable non-compensable days
5 excusable compensable days
12
Example: Delays Concurrent
Owner Delay Impacting
Framing Activity (12 days)
12
WF L1 WF L2
5
TF=5 days
Submittal/Fabrication L2 ✓ Delay events occur
during the same time
7 period
Contractor Delay Impacting
Fabrication (7 days)
✓ They impacted the critical
path
Result:
7 days of Concurrent Delay
(Excusable, Non-compensable)
5 7
Non-critical Delay
7 CP Delay
WF L1 WF L2
5 7
Submittal/Fabrication L2
7
13
Example: Delays not Concurrent
Owner Delay Impacting
Foundation Activity
15 ✓ Delay events occur
TF=5 during the same time
Foundation Steel Erection
period
Steel Fabrication
Contractor has the right to
5
Added Float use the added float
7
15
Recovery Schedules &
Proposals
• Requesting a Recovery Proposal to
recover from an Owner-caused delay
limits the Contractor’s right to the added
Float in non critical paths created by the
owner-caused delay.
• Unrealistic Recovery Schedules can be
used to hide Contractor delays and
delay concurrency.
16
Methodology for Delay
Quantification
• Total-Time Schedule Approach
17
Total-Time Approach
Owner-
As-planned Duration caused
Project
Delay
As-built Duration
18
Adjusted As-Planned Approach
Owner-
As-planned caused
Project
Delay
Owner-
caused
Delay
Adjusted
As-planned
Owner-
caused
Delay
19
Collapsed As-Built “But For”
Approach
As-planned
Owner Delay
As-Built
Contractor Delay
Owner-caused
Collapsed Project Delay
As-built Contractor Delay
20
Contemporaneous Approach
2 Delays
As-planned
Contractor-caused
Contractor-
Update Project Delay
caused
Date
Delay
1st Delay
Owner-caused
Owner-
Contractor- Project Delay
caused
caused Delay
Delay
2nd Delay
Update
Date
21
Contemporaneous Approach
Same but Owner Delay Happened First
As-planned
Owner-caused
Owner-
Update Project Delay
caused
Date Delay
1st Delay
Owner-
caused
Delay No Project
Delay
2nd Delay
Contractor-
Update caused
Date Delay
22
Contemporaneous Approach
“TIA Event Update Analysis”
“ Fragnet Analysis”
• The importance of timing: When the delay-causing
events occurred
• What was the Critical Path when the delay-causing
events occurred
• Using current schedule updates as the basis for
analysis
• Takes into account the dynamic nature of the
schedule
• Concurrency and therefore compensability of delays
can be evaluated.
• The most preferred method
23
LAUSD Scheduling Specification
• Calls for contemporaneous Fragnet
approach
• Requests supporting elements:
Baseline schedule, weekly and monthly
schedule updates
• Baseline and monthly schedule
submittals reviewed/accepted for quality
24
LAUSD Scheduling Specification;
Steps
• Contractor recognizes an impact
• Contractor notifies District of actual or
potential impact in a timely manner
• Pre-delay schedule prepared by Contractor
• Pre-delay schedule approved by District
• Delay Fragnet prepared by Contractor
• Delay Fragnet approved by District
• Net impact calculated/negotiated
25
Projected Delays
• Projected delays are delays or portions
of a delay that extend into the future
• They are time estimates
• They affect the Critical Path
• LAUSD Specifications calls for the
approval of projected delays (Fragnets)
before they can be incorporated into the
schedule
26
Projected Delays
27
Risk!!!!
28
Risk!!!!
29
Risk!!!!
30
Elements of Constructive
Acceleration
• Based on the owner’s unjustified
refusal to grant a time extension or
failure to act
• Requires that:
– A cause exists that would justify a time extension
– A proper request for a time extension
– Denial of that request
– Demand (express or implied) that performance be
completed on time
– An actual acceleration
31
Best Practice
• Enforce the contract requirement for a
good baseline schedule and schedule
updates with a narrative for each as
required
• Enforce the contract requirement for a
formal notice announcing a potential delay
• Enforce the contract requirement for a
Fragnet showing Critical Path impact
• Enforce the contract requirement for
timely submittal of all the above
32
Best Practice
35
Best Practice
39
Best Practice
• Demonstrate good faith even if the
Contractor is not cooperating
– If you’re able to reach only partial resolution
with the Contractor, isolate the disputed
portion and issue a separate unilateral CO
for this portion
– If you’re unable to reach any resolution with
the Contractor, issue a unilateral CO for
time extension
– Avoid constructive acceleration by
discussing recovery options
40
Key Points to Remember
• Communicate
• Document
• Shift the risk to the Contractor, for work that you have no control over,
as soon as possible
41
42