South Asia Pakistan Terminals

Engineering Department

Daily Activity Report


Section: ARTGC Date: Monday, November 14, 2022
Shift: Day Time: 0800-2000
Staff Available: Daniyal,Imran,Muteeb Absent: Majid (A.L)
Down Time Maintenance Staff Names with
Equipment Activities Equipment Status
From To Time Hours
RC RTGC 32,
Operational
33,34,36,37,38,39,41
RTG 42 Under TDS calibration
RTG-40 LCPS Sick sensor faulty (O/O/O for remote operation)
RTG 35 Accidental
Faults

RTG 36 As per follow up, inspect gantry position fault, found RTG36 work area Operational Umair
changed by ACCS during ganty, Need to further investigate.

Activity

Replaced old sick sensor with new one due to E-10 error, new sensor
RTG40 In-Progress Daniyal, Muteeb
have ethernet communication issue, trouble-shooting in progress.

RTG-42 Adjusted land markers of 20ft and 45ft containers, first landing and In-Progress Imran
stack landing work is in process by ROS operators.
Gate Access Conducted Gate acces training of shift members. Completed Imran
ARTG-33 Performed trolley panels paint work Completed Painter

Prepared By: Umair