Work Breakdown WBS Dictionary

Structure (WBS)
WBS Activity
1 Develop Overall Project
the Prototyp
e Drones
1.1 initiating
1.1.1 Develop Define the scope of project. Plan the Purpose and goals of Project. Do an initial cost estimation.
Project Scop
and Plan
1.1.2 Develop a Develop a project charter and submit it to the stakeholders and get it approved.
project Charter
1.1.3 Engage Engage the stakeholders and get to know about the project deliverables. Do all the research about project
Stakeholder and stakeholders’ requirement's
1.1.3. Signatures on Project Manager (ME) and Stakeholders sign the official project charter as a contract to start the project legally
1 project
Contract

1.2 Planning Dronetech will design 4 prototypes with Wilmont's logo on it for Delivering Process
1.2.1 Drone Design A project Scope Management Plan will be produced by Project Manager listing the scopes, Deliverables, and
constraints of Project
1.2.2 Project Scope A risk management plan will be made to encounter any possible risks during the project
Plan
1.2.3 Risk A cost estimation of overall project will be given by Project Manager to Dronetech founder. This cost will include
Management the cost for manufacturing and management process
Plan
1.2.4 Cost Estimates A project organizational Chart will be developed listing all the Levels of Authorities and Reporting structure Of
Project
1.2.5 Create a A Work Breakdown Structure for Project will be created for better understanding of communication command And
Project Deliverables of Project.
Organization
Chart
1.2.6 Create a Work A Work Breakdown Structure for Project will be created for better understanding of communication command And
Breakdown Deliverables of Project.
Structure
1.2.7 Project kickoff A project kickoff Meeting will be called which will include all the stakeholders of Project and a consensus will be
meeting Created among them regarding the project deliverables and they will be informed about project

1.3 Execution
1.3.1 Drones Dronetech will manufacture the Drones of approved design and specifications as mentioned in project Scope Plan.
Manufacturing
1.3.2 Piloting and Dronetech will handle piloting the drones and delivery of the products
delivering
1.3.3 Development Dronetech will develop a mobile application as a booking system for Drugs Delivery process.
of Mobile
Application
1.3.4 Interface with Organize the Wilmont’s resources to interface with Dronetech flight operations and other management systems
Dronetech that control and manage the drone delivery system
Flight
Operation
1.3.5 Interface Interface communications about deliveries for Wilmont’s customers electronically through email online, and
communication through mobile alerts as the customer requests
s
1.3.6 Information Ensure the privacy and security of Wilmont pharmacy, Dronetech will collaborate with IT department of Wilmont
security
management
1.3.7 Drones DroneTech’s will need to allocate a total of 4 new drones for this prototype project
Allocation
1.3.8 Drones Budget will be allocated for maintained of Drones and construction of new parts
Maintenance
and repair
Parts
First delivery Delivery through drones will start from November 30
through
Drones

1.4 Management
and Control
1.4.1 Regular There will be regular meetings with the Team, Stakeholders, and Cross‐impacted areas of the company
Meetings
1.4.2 Testing Testing of Drone Delivery system will take place to check that drones are working satisfactory will all the required f
eatures
1.4.3 Quality control Users will be trained to pilot the drone and quality assessment of Drones will take place.
and user
training
1.4.4 Monitoring the Changes in Drone Manufacturing and add on features of drones will be monitored to keep them
Changes within Project cost Plan

1.5 Closeout
1.5.1 Audit Performance of the project personals and delivery systems will be audited by external organizations or
Performance Stakeholders.
1.5.2 Close out A closeout report on project success and Phase will be made at the end of project
report
1.5.3 Documenting All the files will be documented and archived into company storage for future reference.
the files