You are on page 1of 1

Form N°: PR – 162

Piping Completion Inspection Record Rev: 00


Date: February 2016
(Pre Test Checklist) Page 1 of 2

Client: Location: Project: Test Pack N:


MAJNOON CPF 2 PROJECT ACD-CP2-F-50701A
PETROFAC LOMMEL CPF-2-50701A/B RADIANT
Description of Activities Punch ACD QC Date Contractor Date Remarks
List Items Checklist, Not Limited Initials QC Initials
To
Welding Complete.

PWHT / HT Complete.

NDE (and Alloy Verification if applicable)


Complete.

Released By QC Welding Department.

Line Installed To Drawing.

Line Size Correct.

Line Correct To Pipe Specification.

Flanges/Fittings Correct.

Branch Connection & Location Correct.

Reinforcing Pads Installed and Tested

Weep Holes Installed and Threaded (if


applicable).

Reducers Installed Correctly.

Piping Straight and Plumb.

Verify all Lines Stress Free Connected.

Line Slope As Per Drawing.

Spades and Blinds Installed Correctly. (see Marking by yellow paint all temporary
note). items (e.g. test blinds) installed.

High Point Vents and Low Point Drains


Installed Correctly.

Flange Joints Aligned Correctly.

Verify Bore Dimensions and Cleanliness of


Drilled Tapings on Orifice Flange.

Verify Orifice Flange Internal Weld Root


Ground Flush With Internal Bore of Pipe

Studs / Bolts Correct.

Gaskets / Type / Rating Correct. Verify that any temporary gaskets are
identified as such.

Valve TAG Numbers Correct.

Valve Stem Orientation Correct.

Valve Locked Open/Closed (as applicable). Verify fluid direction through valves
(globe valves, flexible wedge gate
valve) as per P&ID.

You might also like