You are on page 1of 2

Doc.

Code: DPWH – JCF-C006


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Revision No. 0
WELDING PERMIT Date 31MAY2017
Page No. 1 of 1
CONTRACT ID
CONTRACT NAME:
LOCATION:
DATE REQUESTED: RFI No.:
STRUCTURE AREA/FLOOR LEVEL: ACTUAL INSPECTION DATE/TIME:
GRIDLINE:
CHECK THAT THE FOLLOWING COMPLY WITH APPROVED SUBMITTALS FOR CONSTRUCTION DRAWINGS AND TECHNICAL SPECIFICATIONS.
COMPLIED
COMPONENTS REMARKS ACTIONS REQUIRED
DFC YES NO N/A
A. Personnel   
Welder(s) qualifications inspected and approved

B. Welding Machine / Equipment


1. Cutting and welding equipment have been inspected and are in   
good operating condition
2. Welding machine cables and electrode holder are safe for   
operation
3. Oxygen, Acetylene and LPG tanks are not inside a confined   
space, and are secure from toppling
4. Torch, hoses, regulators and fittings have been inspected and   
found safe for operation
C. Welder / Fire Watch
5. Assigned for this Permit, during and 30 minutes after the work   
6. Person knowledgeable in identifying probable fire hazards and in   
using fire extinguishers has been assigned.
7. Welder is certified   
8. Fire extinguisher in good operating condition, of correct type   
and size, is available for immediate use in the work area.
D. Personal Protective Equipment Required
9. Welding Mask   
10. Apron   
11. Welding gloves (leather / rubber)   
12. Respirator   
When Grinding
13. Long Sleeves   
14. Safety Glasses   
15. Face Shield   
16. Ear plugs or Ear muffs   
17. Safety Shoes   
REMARKS:

WORK APPROVAL: ☐ Accepted ☐ Rejected


PREPARED BY: CONFIRMED BY: INSPECTED BY: WITNESSED BY: APPROVED BY:

QA
QC
________________________ _______________________ _______________________ ____________________ __________________________
Contractor QC Engineer DPWH Inspector Contractor DPWH Project Engineer

DISTRIBUTION: Contractor QC Engineer Inspector Project Engineer