PHASES PROJECT
1 PHASE 1
2 PHASE 2
3 PHASE 3
4 QUESTIONS?
Fitting in the premise’ corner the main electrical distribution cabinet. Low voltage is carried by overhead cables from left side on
the following drawing: OK.
A 20ft container will be provided on site as temporary office. Proper location will be discussed.
Temporary oil heater will be connected at the opposite side compared to current situation. Reversing the flow.
Need to buy a new double jacketed tank (20’ container) to avoid retention wall
A temporary loading bay need to be built as shown below. Il will be connected to the currents pipes and pumps:
Construction of the new retention wall and pipe supports (along TAYLOR SMITH & along CHC Ltd)
Construction of the new retetntion wall for new tank. Retention volumes need to be calculated