Professional Documents
Culture Documents
Soriano - Jean Kathleen Bar Chart Final
Soriano - Jean Kathleen Bar Chart Final
LOCATION:
OWMER:
ITEM NO
I.
II.
III.
IV.
V.
VI.
VII.
VIII.
IX.
X.
XI.
XII.
TWO STOREY RESIDENTIAL BUILDING
EARTHWORKS
1.EXCAVATION
2.BACKFILL
CONCRETE WORKS
2.1. CONCRETING OF COLUMN FOOTING
2.2. CONCRETING OF COLUMN
2.3.CONCRETING OF TIE BEAM
2.4. CONCRETING OF SECOND FLOOR BEAM
2.5. CONCRETING OF ROOF BEAM-1 AND 2
2.6.CONCRETING OF GROUND FLOOR AND SECOND FLOOR SLA
FORMWORKS AND SCAFFOLDINGS
3.1 PREPARATION OF FORMS
3.2. INSTALLATION OF FORMS
3.3 REMOVING OF FORMS
3.4 INSTALLATION OF SCAFFOLDING
3.5 REMOVING OF SCAFFOLDING
MASONRY WORKS
4.1. LAYING OF CHB
4.2 PLASTERING
STEEL WORKS
1.PREPARATION OF RSB
2. INSTALLATION OF RSB IN COLUMN FOOTING
3.INSTALLATION OF RSB IN COLUMN
4. INSTALLATION OF RSB IN ROOF BEAM
5. INSTALLATION OF RSB IN WALL FOOTING
6.INSTALLATION OF RSB IN GROUND SLAB AND SECOND FLOOR SLAB
ROOFING WORKS
6.1 FABRICATION OF TRUSS
6.2 INSTALLATION OF TRUSS
CEILING WORKS
7.1 INSTALLATION OF CEILING JOIST
7.2 INSTALLATION OF CEILING
TILE WORKS AND PLASTER FINISH
DOORS AND WINDOWS
9.1 INSTALLATION OF JAMBS
9.2 INSTALLATION OF DOORS
9.3INSTALLATION OF WINDOWS
ELECTRICAL WORKS
10.1 INSTALLATION OF ELECTRICAL PIPES
10.2 INSTALLATION OF ELECTRICAL WIRES/ APPURTANCES
PLUMBING WORKS
11.1 INSTALLATION OF PIPES
11.2 INSTALLATION OF ACCESSORIES
11.3 SEPTIC TANCK
PAINTING WORKS
QUANTITY UNIT AMOUNT % NUMBER OF DAYS
3.28%
### 4.10%
3.28% 3.28%%
0.82% 0.82%
1.64% ###
14.76%
14.76%
WEEK 2 WEE
2 3 4 5 6 1 2
1.64%
1.64%
4.10% 4.10%
3.28%% 3.28%
###
0.82%
1.64%
11.48% 9.8
26.24% 36.0
WEEK 3 WEEK 4
3 4 5 6 1 2 3 4
0%
6.56% 6.56%
0.82%
3.28%
1.69%
1.69% 1.69% 1.69%
1.64%
9.84% 8.20%
36.08% 44.28%
WEEK 4 WEEK 5
4 5 6 1 2 3 4 5
4.92% 4.92%
4.92% 4.92%
0.82% 0.82%
1.64% 1.69%
4.92%%
1.64%
1.64%
1.64% 1.64%
1.64%
7.38%
59.04%
WEEK 7
6 1 2 3 4 5 6 1
1.64%
3.28%
3.28%
3.28%
4.92
6.56%
65.60%
WEEK 8
1 2 3 4 5 6 1 2
1.64% 1.64%
4.92% 4.92%
8.20%
1.64% 1.64%
1.64% 1.64%
2.28%
1.64%
3.28%
9.84%
75.44%
WEEK 9 WEEK 10
2 3 4 5 6 1 2 3
1.64%
4.92%
8.20% 8.20% 8.20%
1.64%
1.64%
3.28% 3.28% 3.28%
8.20% 8.20%
83.64% 91.84%
WEEK 10 WEEK
3 4 5 6 1 2 3
1.64%
4.92%
8.20%
8.20% 8.20%
8.20% 8.20
91.84% 100.0
WEEK 11
3 4 5 6
1.64%
8.20%
8.20%
100.04%
PROJECT : 2 STOREY RESIDENTIAL BUILDING
OWNER:
LOCATION OF PROJECT:
ITEM NO ITEM DESCRIPTION/ ACTIVITIES QUANTITY UNIT
₱ 17,244.00 6.56 4
₱ 307,281.93 31.15 19
₱ 40,355.00 4.92 3
₱ 75,156.65 4.92 3
₱ 47,188.25 6.56 4
₱ 62,649.76 4.92 3
₱ 30,000.00 8.19 5
₱ 72,750.00 8.19 5
₱ 40,000.00 6.56 4
₱ 39,613.02 4.92 3
₱ 36,875.00 4.92 3
₱ 25,000.00 8.19 5
₱ 794,113.61 100% 61 DAYS
PROJECT
LOCATION:
OWMER:
ITEM NO
I.
II.
III.
IV.
V.
VI.
VII.
VIII.
IX.
X.
XI.
XII.
TWO STOREY RESIDENTIAL BUILDING
LOCATION:
OWMER:
ITEM DESCRIPTION/ ACTIVITIES
EARTHWORKS
1.EXCAVATION
2.BACKFILL
CONCRETE WORKS
2.1. CONCRETING OF COLUMN FOOTING
2.2. CONCRETING OF COLUMN
2.3.CONCRETING OF TIE BEAM
2.4. CONCRETING OF SECOND FLOOR BEAM
2.5. CONCRETING OF ROOF BEAM-1 AND 2
2.6.CONCRETING OF GROUND FLOOR AND SECOND FLOOR SLAB
2.7 CONCRETING OF WALL FOOTING
2.8 POURING OF CONCRETE-STAIR
FORMWORKS AND SCAFFOLDINGS
3.1 PREPARATION OF FORMS
3.2. INSTALLATION OF FORMS
3.3 REMOVING OF FORMS
3.4 INSTALLATION OF SCAFFOLDING
3.5 REMOVING OF SCAFFOLDING
MASONRY WORKS
4.1. LAYING OF CHB
4.2 PLASTERING
STEEL WORKS
1.PREPARATION OF RSB
2. INSTALLATION OF RSB IN COLUMN FOOTING
3.INSTALLATION OF RSB IN COLUMN
4. INSTALLATION OF RSB IN ROOF BEAM
5. INSTALLATION OF RSB IN WALL FOOTING
6.INSTALLATION OF RSB IN GROUND SLAB AND SECOND FLOOR SLAB
7. PREPARATION AND INSTALLATION OF RSB-STAIR
ROOFING WORKS
6.1 FABRICATION OF TRUSS
6.2 INSTALLATION OF TRUSS
CEILING WORKS
7.1 INSTALLATION OF CEILING JOIST
7.2 INSTALLATION OF CEILING
TILE WORKS AND PLASTER FINISH
DOORS AND WINDOWS
9.1 INSTALLATION OF JAMBS
9.2 INSTALLATION OF DOORS
9.3INSTALLATION OF WINDOWS
ELECTRICAL WORKS
10.1 INSTALLATION OF ELECTRICAL PIPES
10.2 INSTALLATION OF ELECTRICAL WIRES/ APPURTANCES
PLUMBING WORKS
11.1 INSTALLATION OF PIPES
11.2 INSTALLATION OF ACCESSORIES
11.3 SEPTIC TANK
PAINTING WORKS
QUANTITY UNIT AMOUNT % NO. OF DAYS
1
4.92%
10 cu.m ₱ 6,000.00 3.75 3
2 cu.m ₱ 11,244.00 1.25 1 4.92%
3.75%
3.28%
1.64% 1.64%
1.64%
2.50% 2.50% 2.50%
4.10% 4.10%
3.28% 3.28%%
1.25%
1.25%
0.82%
1.25%
1.25% 1.25%
1.25%
1.25%
7.50%
15.00%
WEEK 3
5 6 1 2 3 4
4.10% 3.13%
3.28% 2.50% 2.50%
6.56%
1.25%
1.25%
0.82%
3.28%
1.25%
1.69%
1.25%
6.88%
21.88%
EEK 3 WEEK 4
4 5 6 1 2 3
1.25% 1.25%
3..12%
6.56%
3.75%
1.25% 1.25%
1.25%
1.69%
1.69%
2.50%
1.64%
88% 7.50%
88% 29..38
WEEK 4
3 4 5 6 1 2
5.00%% 5.00%
4.92% 4.92%
4.92%
1.25% 1.25%
1.25% 1.25%
2.50% 2.50%
7.50%
29..38%
WEEK 5
2 3 4 5 6 1
3.13%
5.00%% 5.00%
4.92% 3.75%
1.25%
0.82% 0.82%
2.50%
3.75% 3.75%
1.25%
1.64%
2.50%
1.25%
1.64% 1.64%
1.64%
1.25%
8.75%
45.63%
WEEK 7
6 1 2 3 4 5
3.12%
3.75%
1.25%
1.64%
3.28%
3.28%
3.28%
9.38%
55.01%
WEEK 8
5 6 1 2 3 4
3.75%
1.25%
1.64%
2.50%
4.92%
8.20%
1.64%
7.50%
62.51%
EEK 8 WEEK
4 5 6 1 2 3
1.25%
1.64%
2.50%
2.50%
4.92%
8.20%
1.64% 1.64%
1.64% 1.64% 1.64%
2.28% 3.28%
3.28%
50% 7.50%
51% 70.01%
WEEK 9
3 4 5 6 1 2
1.64%
50%
2.50%
3.75%
8.20% 8.20%
3.28% 3.28%
7.50%
70.01%
WEEK 10
2 3 4 5 6 1
1.64%
4.92%
2.50% 2.50%
2.50% 2.50%
8.20% 8.20%
7.50%
77.51%
WEEK 11
1 2 3 4 5 6
3.75%
1.25% 1.25%
2.50%
7.50%
85.01%
WEEK 12
6 1 2 3 4 5
1.64%
4.92%
6.25%
50% 2.50%
2.50%
8.20%
7.50%
92.51%
WEEK 13
5 6 1 2 3 4
1.64%
4.92%
6.25%
8.20% 6.25%
7.50%
100%
EK 13
4 5 6
6.25%
50%
00%