CRG(1SBR01) Substructure

PlanGrid Tasks Report - Zone 01_Main 1 Sub C_(TB) - Mar 29


2023
Prepared by QC CIVIL SCL PG
Mar 29, 2023

Description

Issued by qccivil.scl.pg@sobhaconst.com

Contents

#291 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance.................................... 4

#292 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance .................................................................................................................................. 25

#293 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance.............................................................................................................. 28

#294 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................... 75

#295 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance.................................. 96

#296 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 115

#297 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 117

#298 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 131

#299 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 139

#300 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 144

#301 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 149

#302 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 151

#303 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 159

#304 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 169

Prepared by QC CIVIL SCL PG 1 Created with PlanGrid


CRG(1SBR01) Substructure

#305 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 181

#306 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 183

#307 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 193

#308 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 199

#309 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 209

#310 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 211

#583 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 225

#584 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 231

#585 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 233

#586 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 237

#587 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 244

#588 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 248

#589 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 250

#590 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 255

#591 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 263

#592 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 267

#593 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 269

#594 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 273

#595 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance................................. 281

#596 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water
Stopper Clearance ................................................................................................................................ 287

Prepared by QC CIVIL SCL PG 2 Created with PlanGrid


CRG(1SBR01) Substructure

#597 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/Water Stopper
Approval ‐ Formwork Clearance............................................................................................................ 289

#598 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance................................ 294

Prepared by QC CIVIL SCL PG 3 Created with PlanGrid


CRG(1SBR01) Substructure

#291 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 28, 2022 3:38 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 25, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- Deadshutter Formwork (block work) is in progress


CIVIL1 SCL PG Nov 14, 2022

Gandhi Rajan: Pile cap 78 rebar inspected and found comments for rectification 1. Welding of u clamp
for Pig tail anchors to be completed. . 2. damaged protection board to be rectified 3. Missing Links to be
provided. 4. coupler to be tightened properly 5. Pile rebar to be cleaned using wire brush. 6. Missing
starter bars to be provided. 7. Complete cleaning to be done. 8. attach supporting documents.
QC CIVIL SCL PG Nov 25, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and comments attached in C2
CIVIL1 SCL PG Nov 25, 2022

Palanivel Govindaraju:- DM approval verbally received from the DM Engineer Snapshot attached). The
portal approval shall be received on Monday.
CIVIL1 SCL PG Nov 25, 2022

Based on the attached Documents stamp can be closed.


HF QT PG Nov 25, 2022

Photos

Prepared by QC CIVIL SCL PG 4 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3910
CIVIL1 SCL PG
Nov 28, 2022 3:38 PM
IMG_3911
CIVIL1 SCL PG
Nov 28, 2022 3:38 PM

Prepared by QC CIVIL SCL PG 5 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3909
CIVIL1 SCL PG
Nov 28, 2022 3:24 PM

IMG_3897
CIVIL1 SCL PG
Nov 28, 2022 2:50 PM

Prepared by QC CIVIL SCL PG 6 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3885
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

IMG_3896
CIVIL1 SCL PG
Nov 28, 2022 2:48 PM

Prepared by QC CIVIL SCL PG 7 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3886
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

IMG_3879
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

Prepared by QC CIVIL SCL PG 8 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3881
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

IMG_3887
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

Prepared by QC CIVIL SCL PG 9 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3883
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

IMG_3880
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

Prepared by QC CIVIL SCL PG 10 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3884
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

IMG_3887
CIVIL1 SCL PG
Nov 28, 2022 1:27 PM

Prepared by QC CIVIL SCL PG 11 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3889 IMG_3878
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 28, 2022 1:27 PM Nov 28, 2022 1:27 PM

Prepared by QC CIVIL SCL PG 12 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3867
CIVIL1 SCL PG
Nov 25, 2022 6:30 PM

WhatsApp Image 2022-11-25 at 18.10.39


CIVIL1 SCL PG
Nov 25, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 13 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3833 IMG_3832
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 12:27 PM Nov 25, 2022 12:27 PM

Prepared by QC CIVIL SCL PG 14 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3825
CIVIL1 SCL PG
Nov 25, 2022 12:11 PM

IMG_3824
CIVIL1 SCL PG
Nov 25, 2022 9:44 AM

Prepared by QC CIVIL SCL PG 15 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3822 IMG_3823
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 9:44 AM Nov 25, 2022 9:44 AM

Prepared by QC CIVIL SCL PG 16 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3818 IMG_3815
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

Prepared by QC CIVIL SCL PG 17 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3816 IMG_3819
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

Prepared by QC CIVIL SCL PG 18 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3814 IMG_3821
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

Prepared by QC CIVIL SCL PG 19 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3820 IMG_3817
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

Prepared by QC CIVIL SCL PG 20 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3812 IMG_3813
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

IMG_3809 IMG_3811
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:49 AM Nov 25, 2022 8:49 AM

Prepared by QC CIVIL SCL PG 21 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3810
CIVIL1 SCL PG
Nov 25, 2022 8:49 AM

B5 block work (1)


CIVIL1 SCL PG
Nov 23, 2022 8:01 AM

20221121_090318_photo 20221121_090218_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:03 AM Nov 21, 2022 9:02 AM

Prepared by QC CIVIL SCL PG 22 Created with PlanGrid


CRG(1SBR01) Substructure

20221121_085429_photo
CIVIL1 SCL PG
Nov 21, 2022 8:54 AM

IMG_3476
CIVIL1 SCL PG
Nov 14, 2022 7:04 AM

Prepared by QC CIVIL SCL PG 23 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3475
CIVIL1 SCL PG
Nov 14, 2022 7:04 AM

Prepared by QC CIVIL SCL PG 24 Created with PlanGrid


CRG(1SBR01) Substructure

#292 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 25, 2022 6:20 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 25, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Nov 12, 2022

Shijo - No electrical services in pile cap.


MEP SCL PG Nov 25, 2022

Shameer- No Plumbing services in pile cap.


MEP SCL PG Nov 25, 2022

Abdul Nafih- Noted. Stamp closed.


QC MEP SCL PG Nov 25, 2022

Photos

Prepared by QC CIVIL SCL PG 25 Created with PlanGrid


CRG(1SBR01) Substructure

WhatsApp Image 2022-11-25 at 6.07.58 PM (1)


MEP SCL PG
Nov 25, 2022 6:17 PM

11_21_2022_Work Clearance Request (V1.0)_Draft (1)_page-0001


MEP SCL PG
Nov 25, 2022 6:16 PM

Prepared by QC CIVIL SCL PG 26 Created with PlanGrid


CRG(1SBR01) Substructure

WhatsApp Image 2022-11-25 at 5.58.12 PM


MEP SCL PG
11_21_2022_Work Clearance Request (V1.0)_Draft_page-0001 Nov 25, 2022 6:06 PM
MEP SCL PG
Nov 25, 2022 6:11 PM

IMG_1587 IMG_1588
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 8:50 AM Nov 25, 2022 8:50 AM

Prepared by QC CIVIL SCL PG 27 Created with PlanGrid


CRG(1SBR01) Substructure

#293 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 8:40 AM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 25, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works in TBPC78 is in progress


CIVIL1 SCL PG Nov 12, 2022

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Nov 23, 2022

Gandhi Rajan: Pile cap 78 bottom rebar inspected and found comments for rectification 1. cleaning 2.
Binding to be done. 4. damaged protection board to be rectified 5. Side Face bar to be Provided. 6.
Links to be provided 7. coupler to be tightened properly 8. Pile rebar to be cleaned using wire brush.
QC CIVIL SCL PG Nov 24, 2022

PRADEEP ILANGO:- all QAQC comments rectified and documents attached


CIVIL1 SCL PG Nov 25, 2022

Gandhi Rajan: Pile cap 78 rebar inspected and found comments for rectification 1. Welding of u clamp
for Pig tail anchors to be completed. . 2. damaged protection board to be rectified 3. Missing Links to be
provided. 4. coupler to be tightened properly 5. Pile rebar to be cleaned using wire brush. 6. Missing
starter bars to be provided. 7. Complete cleaning to be done. 8. attach supporting documents.

Prepared by QC CIVIL SCL PG 28 Created with PlanGrid


CRG(1SBR01) Substructure

QC CIVIL SCL PG Nov 25, 2022

PRADEEP ILANGO:- all mentioned comments were rectified


CIVIL1 SCL PG Nov 25, 2022

Ok, Q & T regarding site Inspection rectification complete, stamp is closed.


HF QT PG Nov 25, 2022

Photos

20221128_095355_photo 20221128_095333_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 28, 2022 9:54 AM Nov 28, 2022 9:53 AM

Prepared by QC CIVIL SCL PG 29 Created with PlanGrid


CRG(1SBR01) Substructure

20221128_094405_photo 20221128_094334_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 28, 2022 9:44 AM Nov 28, 2022 9:43 AM

Prepared by QC CIVIL SCL PG 30 Created with PlanGrid


CRG(1SBR01) Substructure

20221128_093748_photo
QC CIVIL SCL PG
Nov 28, 2022 9:37 AM

IMG_3863
CIVIL1 SCL PG
Nov 25, 2022 1:58 PM

Prepared by QC CIVIL SCL PG 31 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3862 IMG_3861
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 1:57 PM Nov 25, 2022 1:57 PM

Prepared by QC CIVIL SCL PG 32 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3858
CIVIL1 SCL PG
Nov 25, 2022 1:52 PM

IMG_3823
CIVIL1 SCL PG
Nov 25, 2022 1:53 PM

Prepared by QC CIVIL SCL PG 33 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3857
CIVIL1 SCL PG
Nov 25, 2022 1:52 PM

IMG_3860
CIVIL1 SCL PG
Nov 25, 2022 1:52 PM

Prepared by QC CIVIL SCL PG 34 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3851
CIVIL1 SCL PG
Nov 25, 2022 1:52 PM

IMG_3855
CIVIL1 SCL PG
Nov 25, 2022 1:52 PM

Prepared by QC CIVIL SCL PG 35 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3846 IMG_3848
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 1:00 PM Nov 25, 2022 1:00 PM

Prepared by QC CIVIL SCL PG 36 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3849 IMG_3847
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 1:00 PM Nov 25, 2022 1:00 PM

Prepared by QC CIVIL SCL PG 37 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3844
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

IMG_3840
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

Prepared by QC CIVIL SCL PG 38 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3843
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

IMG_3841
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

Prepared by QC CIVIL SCL PG 39 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3834
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

IMG_3842
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

IMG_3837 IMG_3836
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 12:43 PM Nov 25, 2022 12:43 PM

Prepared by QC CIVIL SCL PG 40 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3838 IMG_3835
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 25, 2022 12:43 PM Nov 25, 2022 12:43 PM

IMG_3830
CIVIL1 SCL PG
Nov 25, 2022 12:27 PM

IMG_3839
CIVIL1 SCL PG
Nov 25, 2022 12:43 PM

Prepared by QC CIVIL SCL PG 41 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3829
CIVIL1 SCL PG
Nov 25, 2022 12:10 PM

IMG_3831
CIVIL1 SCL PG
Nov 25, 2022 12:27 PM

Prepared by QC CIVIL SCL PG 42 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3828
CIVIL1 SCL PG
Nov 25, 2022 12:10 PM

IMG_3827
CIVIL1 SCL PG
Nov 25, 2022 12:10 PM

Prepared by QC CIVIL SCL PG 43 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3826
CIVIL1 SCL PG
Nov 25, 2022 12:10 PM

20221125_113808_photo
QC CIVIL SCL PG
Nov 25, 2022 11:38 AM

Prepared by QC CIVIL SCL PG 44 Created with PlanGrid


CRG(1SBR01) Substructure

20221125_111326_photo 20221125_104451_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 25, 2022 11:13 AM Nov 25, 2022 10:45 AM

Prepared by QC CIVIL SCL PG 45 Created with PlanGrid


CRG(1SBR01) Substructure

20221125_104432_photo 20221124_155121_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 25, 2022 10:44 AM Nov 24, 2022 3:51 PM

Prepared by QC CIVIL SCL PG 46 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3709
CIVIL1 SCL PG
Nov 23, 2022 8:04 AM

20221124_154807_photo
QC CIVIL SCL PG
Nov 24, 2022 3:48 PM

Prepared by QC CIVIL SCL PG 47 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3707
CIVIL1 SCL PG
Nov 23, 2022 8:04 AM

IMG_3708
CIVIL1 SCL PG
Nov 23, 2022 8:04 AM

Prepared by QC CIVIL SCL PG 48 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3710
CIVIL1 SCL PG
Nov 23, 2022 8:04 AM

IMG_3711
CIVIL1 SCL PG
Nov 23, 2022 8:04 AM

Prepared by QC CIVIL SCL PG 49 Created with PlanGrid


CRG(1SBR01) Substructure

12eedd2e-6a57-4b6b-a313-47cb7cde8901_t ad13ef96-2e5f-4d52-a046-627503b10841_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:57 PM Nov 21, 2022 4:55 PM

Prepared by QC CIVIL SCL PG 50 Created with PlanGrid


CRG(1SBR01) Substructure

799a6c8b-31c8-4b8f-b372-4160e7e15a2b_t b225d452-2922-44b8-93a7-b8eb1b3de5da_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:53 PM Nov 21, 2022 4:51 PM

Prepared by QC CIVIL SCL PG 51 Created with PlanGrid


CRG(1SBR01) Substructure

c461b53a-a0be-4675-8469-a2fa27a868bd_t 14fd64f2-de4c-4891-9577-12fbefc5ed3a_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:49 PM Nov 21, 2022 4:48 PM

Prepared by QC CIVIL SCL PG 52 Created with PlanGrid


CRG(1SBR01) Substructure

5c4c3abb-ce1f-42d7-ad7a-a5fea690385f_t f19a10b6-4775-4339-bb5f-5476543ff35b_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:46 PM Nov 21, 2022 4:45 PM

Prepared by QC CIVIL SCL PG 53 Created with PlanGrid


CRG(1SBR01) Substructure

5679e816-98e9-4ea6-b13a-b7b9d57192fe_t 9d486c3d-378b-4657-80ed-2d44219d61a7_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:41 PM Nov 21, 2022 4:40 PM

Prepared by QC CIVIL SCL PG 54 Created with PlanGrid


CRG(1SBR01) Substructure

b3ad10c9-3b2d-45be-9112-426f71962e5d_t 42e227a4-3eab-4c78-8a82-a678779978c3_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:39 PM Nov 21, 2022 4:12 PM

Prepared by QC CIVIL SCL PG 55 Created with PlanGrid


CRG(1SBR01) Substructure

dedb1823-26db-4bfc-89f6-8b9c72523237_t dedb1823-26db-4bfc-89f6-8b9c72523237_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:10 PM Nov 21, 2022 4:10 PM

Prepared by QC CIVIL SCL PG 56 Created with PlanGrid


CRG(1SBR01) Substructure

d7f1c73c-4f34-4181-a4fb-72a8d036c891_t fe024f0e-56bd-484a-8d5d-58675e3cae2e_t
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 21, 2022 4:09 PM Nov 21, 2022 4:09 PM

IMG_1541 IMG_1594
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 57 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1542 IMG_1542
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

IMG_1598
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1548
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 58 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1585 IMG_1544
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 59 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1587
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1549
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 60 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1591
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1545
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 61 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1590
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_3623
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 62 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1541
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1543
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1592 IMG_1597
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 63 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1593 IMG_1588
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

IMG_3617 IMG_3619
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 64 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1596
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_3624
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_1595 IMG_1586
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 65 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3622
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_3618
CIVIL1 SCL PG
Nov 21, 2022 9:48 AM

IMG_3621 IMG_3620
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:48 AM Nov 21, 2022 9:48 AM

Prepared by QC CIVIL SCL PG 66 Created with PlanGrid


CRG(1SBR01) Substructure

20221121_090414_photo 20221121_090339_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 9:04 AM Nov 21, 2022 9:03 AM

IMG_3497 IMG_3498
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 16, 2022 7:43 AM Nov 16, 2022 7:43 AM

Prepared by QC CIVIL SCL PG 67 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3508
CIVIL1 SCL PG
Nov 16, 2022 7:43 AM

IMG_3499
CIVIL1 SCL PG
Nov 16, 2022 7:43 AM

IMG_3509 IMG_3512
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 16, 2022 7:43 AM Nov 16, 2022 7:43 AM

Prepared by QC CIVIL SCL PG 68 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3525 IMG_3524
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 16, 2022 7:43 AM Nov 16, 2022 7:43 AM

IMG_3511 IMG_3510
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 16, 2022 7:43 AM Nov 16, 2022 7:43 AM

Prepared by QC CIVIL SCL PG 69 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3513
CIVIL1 SCL PG
Nov 16, 2022 7:43 AM

IMG_3495
CIVIL1 SCL PG
Nov 15, 2022 8:35 PM

IMG_3480 IMG_3479
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 15, 2022 6:55 AM Nov 15, 2022 6:55 AM

Prepared by QC CIVIL SCL PG 70 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3480 IMG_3450
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 15, 2022 6:55 AM Nov 14, 2022 7:02 AM

IMG_3471
CIVIL1 SCL PG
Nov 14, 2022 7:02 AM

IMG_3440
CIVIL1 SCL PG
Nov 14, 2022 7:02 AM

Prepared by QC CIVIL SCL PG 71 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3449
CIVIL1 SCL PG
Nov 14, 2022 7:02 AM

IMG_3448
CIVIL1 SCL PG
Nov 14, 2022 7:02 AM

Prepared by QC CIVIL SCL PG 72 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3447 20221113_201158_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 14, 2022 7:02 AM Nov 13, 2022 8:12 PM

Prepared by QC CIVIL SCL PG 73 Created with PlanGrid


CRG(1SBR01) Substructure

20221113_201139_photo 20221113_201127_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 13, 2022 8:11 PM Nov 13, 2022 8:11 PM

IMG_3416 IMG_3414
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 12, 2022 6:37 AM Nov 12, 2022 6:37 AM

Prepared by QC CIVIL SCL PG 74 Created with PlanGrid


CRG(1SBR01) Substructure

#294 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 2:40 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

Prabhu - concrete pouring started 9.30 PM(25-11-2022)


CIVIL1 SCL PG Nov 26, 2022

PRADEEP ILANGO:- pilecap concreting completed at 6:30 AM


CIVIL1 SCL PG Nov 26, 2022

Gandhi Rajan: 617m3 received as of now


QC CIVIL SCL PG Nov 26, 2022

Gandhi Rajan: 745m3 received as of now


QC CIVIL SCL PG Nov 26, 2022

Prabhu -pc78 upper part pile casting on progress . 28-11-2022 at 9.30 pm started
CIVIL1 SCL PG Nov 28, 2022

Prabhu - pile cap concreting on progress


CIVIL1 SCL PG Nov 29, 2022

PRADEEP ILANGO:- pilecap concreting completed by9:45Am


CIVIL1 SCL PG Nov 29, 2022

Prepared by QC CIVIL SCL PG 75 Created with PlanGrid


CRG(1SBR01) Substructure

Prabhu - curing on progress


CIVIL1 SCL PG Nov 30, 2022

PRADEEP ILANGO:- curing ensured for 7days


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found Satisfactory. stamp closed


QC CIVIL SCL PG Dec 14, 2022

Photos

9ba38c50-35b0-4857-bae5-880799adf546 4264e176-c407-42b1-86d2-2d31668bf036
QC CIVIL SCL PG QC CIVIL SCL PG
Dec 14, 2022 2:39 PM Dec 14, 2022 2:39 PM

Prepared by QC CIVIL SCL PG 76 Created with PlanGrid


CRG(1SBR01) Substructure

fa386228-860c-4785-b5ec-d67fda7df608 IMG_2140
QC CIVIL SCL PG CIVIL1 SCL PG
Dec 14, 2022 2:39 PM Nov 30, 2022 4:54 PM

IMG_2127 IMG_2132
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 4:54 PM Nov 30, 2022 4:54 PM

Prepared by QC CIVIL SCL PG 77 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2125 IMG_2128
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 4:54 PM Nov 30, 2022 4:54 PM

IMG_2126 IMG_2130
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 4:54 PM Nov 30, 2022 4:54 PM

Prepared by QC CIVIL SCL PG 78 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2139 IMG_2124
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 4:54 PM Nov 30, 2022 4:54 PM

IMG_2138 IMG_2131
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 4:54 PM Nov 30, 2022 4:54 PM

Prepared by QC CIVIL SCL PG 79 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2137
CIVIL1 SCL PG
Nov 30, 2022 4:54 PM

IMG_4341
CIVIL1 SCL PG
Nov 30, 2022 7:39 AM

Prepared by QC CIVIL SCL PG 80 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4342 IMG_4344
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:39 AM Nov 30, 2022 7:39 AM

Prepared by QC CIVIL SCL PG 81 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4335
CIVIL1 SCL PG
Nov 30, 2022 7:38 AM

IMG_4343
CIVIL1 SCL PG
Nov 30, 2022 7:39 AM

IMG_4338 IMG_4339
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:38 AM Nov 30, 2022 7:38 AM

Prepared by QC CIVIL SCL PG 82 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4334
CIVIL1 SCL PG
Nov 30, 2022 7:38 AM

IMG_4340
CIVIL1 SCL PG
Nov 30, 2022 7:38 AM

IMG_4337 IMG_4336
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:38 AM Nov 30, 2022 7:38 AM

Prepared by QC CIVIL SCL PG 83 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4331 IMG_4333
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:36 AM Nov 30, 2022 7:36 AM

Prepared by QC CIVIL SCL PG 84 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4332 20221129_083230_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:36 AM Nov 29, 2022 8:32 AM

Prepared by QC CIVIL SCL PG 85 Created with PlanGrid


CRG(1SBR01) Substructure

20221129_083123_photo 20221129_083116_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 8:31 AM Nov 29, 2022 8:31 AM

Prepared by QC CIVIL SCL PG 86 Created with PlanGrid


CRG(1SBR01) Substructure

20221128_221130_photo 20221128_221104_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 28, 2022 10:11 PM Nov 28, 2022 10:11 PM

Prepared by QC CIVIL SCL PG 87 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3874 IMG_3877
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 26, 2022 8:51 AM Nov 26, 2022 8:51 AM
Download video Download video

Prepared by QC CIVIL SCL PG 88 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3870
CIVIL1 SCL PG
Nov 26, 2022 8:51 AM

IMG_3869
CIVIL1 SCL PG
Nov 26, 2022 8:51 AM

Prepared by QC CIVIL SCL PG 89 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3868
CIVIL1 SCL PG
Nov 26, 2022 8:51 AM

IMG_3875
CIVIL1 SCL PG
Nov 26, 2022 8:51 AM

Prepared by QC CIVIL SCL PG 90 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3876 IMG_3871
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 26, 2022 8:51 AM Nov 26, 2022 8:51 AM

Prepared by QC CIVIL SCL PG 91 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3873 IMG_3872
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 26, 2022 8:51 AM Nov 26, 2022 8:51 AM

Prepared by QC CIVIL SCL PG 92 Created with PlanGrid


CRG(1SBR01) Substructure

20221125_232837_photo 20221125_230208_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 25, 2022 11:28 PM Nov 25, 2022 11:02 PM

Prepared by QC CIVIL SCL PG 93 Created with PlanGrid


CRG(1SBR01) Substructure

20221125_214932_photo 20221125_214925_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 25, 2022 9:49 PM Nov 25, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 94 Created with PlanGrid


CRG(1SBR01) Substructure

20221125_214911_photo
QC CIVIL SCL PG
Nov 25, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 95 Created with PlanGrid


CRG(1SBR01) Substructure

#295 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 9:07 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- dead shutters-block works completed; backfilling is in progress


CIVIL1 SCL PG Nov 23, 2022

PRADEEP ILANGO:- Formwork and backfilling completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC1,2,3,4 & 5 Pile cap reinforcement checked and found comments 1. Top mesh
spacing to be aligned and rectified. 2. cleaning of pile rebars, 3. protection of verticals before casting.4.
complete backfilling around the pile cap. 5. All supporting documents : turkish checklist , WIR approval ,
DM approval and concrete clearance to be attached. 6.curing photos to be updated in C4 stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and documents attached
CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 96 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2235 IMG_4059
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 9:06 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 97 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4060
CIVIL1 SCL PG
Nov 30, 2022 8:58 PM

IMG_4058
CIVIL1 SCL PG
Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 98 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4061 IMG_4062
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 99 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4056 IMG_4064
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 100 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4057 IMG_4063
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 101 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4055
CIVIL1 SCL PG
Nov 30, 2022 6:59 PM

b3902765-4c3d-4878-bf7a-d68df97e6073
CIVIL1 SCL PG
Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 102 Created with PlanGrid


CRG(1SBR01) Substructure

65ad6241-fb2a-4e8c-99a7-bad4f61c2b9e 42259595-128e-474e-a5b0-77788d7689ab
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:39 PM Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 103 Created with PlanGrid


CRG(1SBR01) Substructure

4514befd-39d2-4456-9c89-f3ef2c3ed45a 2fafc0d8-48db-4b16-b506-7d519d6d42d0
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:39 PM Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 104 Created with PlanGrid


CRG(1SBR01) Substructure

cadeb88d-5817-4676-835e-cc92ab65f008 9b7670e3-10ab-4f0d-810f-dac926afab70
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:39 PM Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 105 Created with PlanGrid


CRG(1SBR01) Substructure

81b406af-19d9-49fb-b294-e217ed7d13e0
CIVIL1 SCL PG
Nov 30, 2022 6:39 PM

44a683db-7c62-42a2-8216-d2e2e9167e28
CIVIL1 SCL PG
Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 106 Created with PlanGrid


CRG(1SBR01) Substructure

2fcedd9e-6041-41e4-ac34-2db932024ad0
CIVIL1 SCL PG
Nov 30, 2022 6:39 PM

ef5ff4e2-53fe-45f3-9809-e9d52f475595
CIVIL1 SCL PG
Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 107 Created with PlanGrid


CRG(1SBR01) Substructure

a5a8b1b9-0d99-4d6c-ba37-6d5180d3ef14 89156bc6-d9d9-434b-8f97-4690e9705b92
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:39 PM Nov 30, 2022 6:39 PM

Prepared by QC CIVIL SCL PG 108 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4053 IMG_4052
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:36 PM Nov 30, 2022 6:36 PM

Prepared by QC CIVIL SCL PG 109 Created with PlanGrid


CRG(1SBR01) Substructure

20221130_173418_photo 20221130_172606_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 30, 2022 5:34 PM Nov 30, 2022 5:26 PM

Prepared by QC CIVIL SCL PG 110 Created with PlanGrid


CRG(1SBR01) Substructure

20221130_172552_photo 20221130_171838_photo
QC CIVIL SCL PG QC CIVIL SCL PG
Nov 30, 2022 5:26 PM Nov 30, 2022 5:18 PM

Prepared by QC CIVIL SCL PG 111 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4045
CIVIL1 SCL PG
Nov 30, 2022 5:11 PM

20221130_171504_photo
QC CIVIL SCL PG
Nov 30, 2022 5:15 PM

Prepared by QC CIVIL SCL PG 112 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2223
CIVIL1 SCL PG IMG_3941
Nov 30, 2022 4:55 PM CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

e78e5969-eefc-4422-85a5-e0ace18037c2 224cdfaa-5822-4639-b891-e8bca367574f
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 113 Created with PlanGrid


CRG(1SBR01) Substructure

63a4718b-f9f3-4ee8-abd5-39b189c008d0
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

2c0fcd06-2dec-40fb-a46a-d756829d27c5
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 114 Created with PlanGrid


CRG(1SBR01) Substructure

#296 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 6:33 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Nov 23, 2022

Shijo- No Electrical Services on pile cap.


MEP SCL PG Nov 30, 2022

Shameer- No mechanical services on pile cap.


MEP SCL PG Nov 30, 2022

Abdul Nafih- Noted. Stamp closed.


QC MEP SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 115 Created with PlanGrid


CRG(1SBR01) Substructure

11_29_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Nov 30, 2022 5:37 PM

Prepared by QC CIVIL SCL PG 116 Created with PlanGrid


CRG(1SBR01) Substructure

#297 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 9:06 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works is in progress


CIVIL1 SCL PG Nov 23, 2022

Prabhu - pile cap rebar works are done .


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC1,2,3,4 & 5 inspected and all comments mentioned in C3 Stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified


CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 117 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2235 IMG_4063
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 9:06 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 118 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4060 IMG_4056
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 119 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4057
CIVIL1 SCL PG
Nov 30, 2022 8:58 PM

IMG_4058
CIVIL1 SCL PG
Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 120 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4059 IMG_4064
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 121 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4062 IMG_4061
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:58 PM Nov 30, 2022 8:58 PM

Prepared by QC CIVIL SCL PG 122 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4054
IMG_4051
CIVIL1 SCL PG
CIVIL1 SCL PG
Nov 30, 2022 6:33 PM
Nov 30, 2022 6:33 PM

Prepared by QC CIVIL SCL PG 123 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4044
CIVIL1 SCL PG
Nov 30, 2022 5:15 PM

20221130_171446_photo
QC CIVIL SCL PG
Nov 30, 2022 5:14 PM

Prepared by QC CIVIL SCL PG 124 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4316 IMG_4328
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:40 AM Nov 30, 2022 7:40 AM

Prepared by QC CIVIL SCL PG 125 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4330 IMG_4329
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:40 AM Nov 30, 2022 7:40 AM

IMG_2109 IMG_2106
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 126 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2112 IMG_2107
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

IMG_2113
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

IMG_2111
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 127 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2105 IMG_2110
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

IMG_1918 IMG_1919
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:49 PM Nov 23, 2022 10:49 PM

Prepared by QC CIVIL SCL PG 128 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1923 IMG_1921
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:49 PM Nov 23, 2022 10:49 PM

IMG_1920
CIVIL1 SCL PG
Nov 23, 2022 10:49 PM

IMG_1922
CIVIL1 SCL PG
Nov 23, 2022 10:49 PM

Prepared by QC CIVIL SCL PG 129 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1916
CIVIL1 SCL PG
Nov 23, 2022 10:49 PM

Prepared by QC CIVIL SCL PG 130 Created with PlanGrid


CRG(1SBR01) Substructure

#298 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 2:40 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

Prabhu- pile cap casting started (01-12-2022) at 12.05am


CIVIL1 SCL PG Dec 1, 2022

Prabhu- pile cap casting on progress


CIVIL1 SCL PG Dec 1, 2022

Prabhu- pile cap casting done 7.15am (01-12-2022)


CIVIL1 SCL PG Dec 1, 2022

PRADEEP ILANGO:- curing ensured for 7days


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found Satisfactory. stamp closed


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 131 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_211804_photo 20221201_211746_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 9:18 PM Dec 1, 2022 9:17 PM

Prepared by QC CIVIL SCL PG 132 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_211726_photo 20221201_211549_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 9:17 PM Dec 1, 2022 9:15 PM

Prepared by QC CIVIL SCL PG 133 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_211541_photo
CIVIL1 SCL PG
Dec 1, 2022 9:15 PM

IMG_4361
CIVIL1 SCL PG
Dec 1, 2022 9:51 AM

Prepared by QC CIVIL SCL PG 134 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4360
CIVIL1 SCL PG
Dec 1, 2022 9:51 AM

IMG_4359
CIVIL1 SCL PG
Dec 1, 2022 9:51 AM

Prepared by QC CIVIL SCL PG 135 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4358
CIVIL1 SCL PG
Dec 1, 2022 9:51 AM

20221201_052539_photo
CIVIL1 SCL PG
Dec 1, 2022 5:25 AM

Prepared by QC CIVIL SCL PG 136 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_052450_photo 20221201_052423_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 5:24 AM Dec 1, 2022 5:24 AM

Prepared by QC CIVIL SCL PG 137 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_052413_photo
CIVIL1 SCL PG
Dec 1, 2022 5:24 AM

Prepared by QC CIVIL SCL PG 138 Created with PlanGrid


CRG(1SBR01) Substructure

#299 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 2:40 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- pilecap concreting completed


CIVIL1 SCL PG Dec 4, 2022

PRADEEP ILANGO:- curing ensured for 7 days


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found Satisfactory. stamp closed


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 139 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2273 IMG_2272
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 4, 2022 9:49 PM Dec 4, 2022 9:49 PM

IMG_2274
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

PHOTO-2022-12-02-05-40-40 2
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 140 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-02-05-40-41
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

PHOTO-2022-12-03-07-27-47
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 141 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-01-21-13-13
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

PHOTO-2022-12-03-07-28-06
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 142 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-02-05-40-39
CIVIL1 SCL PG
Dec 4, 2022 9:49 PM

Prepared by QC CIVIL SCL PG 143 Created with PlanGrid


CRG(1SBR01) Substructure

#300 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 8:50 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works is in progress


CIVIL1 SCL PG Nov 21, 2022

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC14,15,16,21 & 22 inspected and all comments mentioned in C3 Stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:-all comments rectified and photos attached


CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 144 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4054
IMG_4051
CIVIL1 SCL PG
CIVIL1 SCL PG
Nov 30, 2022 6:36 PM
Nov 30, 2022 6:36 PM

Prepared by QC CIVIL SCL PG 145 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2108
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

IMG_4047
CIVIL1 SCL PG
Nov 30, 2022 5:30 PM

IMG_2109 IMG_2112
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 146 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2113 IMG_2107
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

IMG_1517 IMG_1518
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 10:10 AM Nov 21, 2022 10:10 AM

Prepared by QC CIVIL SCL PG 147 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1515 IMG_1519
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 21, 2022 10:10 AM Nov 21, 2022 10:10 AM

IMG_1520
CIVIL1 SCL PG
Nov 21, 2022 10:10 AM

Prepared by QC CIVIL SCL PG 148 Created with PlanGrid


CRG(1SBR01) Substructure

#301 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 6:42 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Nov 21, 2022

Shijo- No Electrical Services on pile cap.


MEP SCL PG Nov 30, 2022

Shameer- No mechanical Services on pile cap.


MEP SCL PG Nov 30, 2022

Abdul Nafih- Noted. Stamp closed.


QC MEP SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 149 Created with PlanGrid


CRG(1SBR01) Substructure

11_29_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Nov 30, 2022 5:38 PM

Prepared by QC CIVIL SCL PG 150 Created with PlanGrid


CRG(1SBR01) Substructure

#302 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 8:52 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- dead shutter -block work completed;backfilling is in progress


CIVIL1 SCL PG Nov 23, 2022

PRADEEP ILANGO:- Formwork and backfilling completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC 14,15,16,21 & 22 Pile cap reinforcement checked and found comments 1. Top mesh
spacing to be aligned and rectified. 2. cleaning of pile rebars, 3. protection of verticals before casting.4.
complete backfilling around the pile cap. 5. All supporting documents : turkish checklist , WIR approval ,
DM approval and concrete clearance to be attached. 6.curing photos to be updated in C4 stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and documents attached
CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.Gandhi rajan: Found satisfactory. stamp closed.
QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 151 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4055
CIVIL1 SCL PG IMG_2154
Nov 30, 2022 7:00 PM CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

IMG_2155
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

56f3c41f-87a6-4692-8b9d-95ab4814472a
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 152 Created with PlanGrid


CRG(1SBR01) Substructure

9ba2793d-e588-433e-9117-7962ea26f21a
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

1cb48072-8ee5-4354-8401-1b1ff92ab10f
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 153 Created with PlanGrid


CRG(1SBR01) Substructure

71603062-9d05-43d8-97ec-db45e5819727
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

89137ff4-be61-473b-a11e-b81fbe44ac76
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 154 Created with PlanGrid


CRG(1SBR01) Substructure

df59c0c2-bd70-47eb-888d-dd788e8a8bf7
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

03618dce-9834-4b6f-a226-906cc1397ba1
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 155 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4053
CIVIL1 SCL PG
Nov 30, 2022 6:37 PM

1de6479a-eff1-4315-a977-b915d95700f2
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 156 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4045
CIVIL1 SCL PG
Nov 30, 2022 5:12 PM

IMG_4052
CIVIL1 SCL PG
Nov 30, 2022 6:37 PM

IMG_2223
CIVIL1 SCL PG IMG_3941
Nov 30, 2022 4:55 PM CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

Prepared by QC CIVIL SCL PG 157 Created with PlanGrid


CRG(1SBR01) Substructure

e78e5969-eefc-4422-85a5-e0ace18037c2 224cdfaa-5822-4639-b891-e8bca367574f
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:13 PM Nov 29, 2022 6:13 PM

63a4718b-f9f3-4ee8-abd5-39b189c008d0
CIVIL1 SCL PG
Nov 29, 2022 6:13 PM

Prepared by QC CIVIL SCL PG 158 Created with PlanGrid


CRG(1SBR01) Substructure

#303 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 15, 2022 4:37 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 15, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

Prabhu - pile cap casting started 12.05am(01-12-2022).


CIVIL1 SCL PG Dec 1, 2022

Prabhu- pile cap casting on progress


CIVIL1 SCL PG Dec 1, 2022

Prabhu - pile cap casting done 7.15(01-12-2022).


CIVIL1 SCL PG Dec 1, 2022

PRADEEP ILANGO:- Curing ensured for 7 days


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 15, 2022

Photos

Prepared by QC CIVIL SCL PG 159 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_212027_photo 20221201_212009_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 9:20 PM Dec 1, 2022 9:20 PM

Prepared by QC CIVIL SCL PG 160 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_212003_photo 20221201_211945_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 9:20 PM Dec 1, 2022 9:19 PM

Prepared by QC CIVIL SCL PG 161 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4360
CIVIL1 SCL PG
Dec 1, 2022 9:49 AM

20221201_211939_photo
CIVIL1 SCL PG
Dec 1, 2022 9:19 PM

Prepared by QC CIVIL SCL PG 162 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4359 IMG_4361
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 9:49 AM Dec 1, 2022 9:49 AM

Prepared by QC CIVIL SCL PG 163 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4358
CIVIL1 SCL PG
Dec 1, 2022 9:49 AM

20221201_070824_photo
CIVIL1 SCL PG
Dec 1, 2022 7:08 AM

Prepared by QC CIVIL SCL PG 164 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_070815_photo 20221201_070030_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 7:08 AM Dec 1, 2022 7:00 AM

Prepared by QC CIVIL SCL PG 165 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_070016_photo 20221201_062151_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 7:00 AM Dec 1, 2022 6:21 AM

Prepared by QC CIVIL SCL PG 166 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_054259_photo 20221201_054249_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 5:43 AM Dec 1, 2022 5:42 AM

Prepared by QC CIVIL SCL PG 167 Created with PlanGrid


CRG(1SBR01) Substructure

20221201_051808_photo 20221201_051755_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 1, 2022 5:18 AM Dec 1, 2022 5:17 AM

Prepared by QC CIVIL SCL PG 168 Created with PlanGrid


CRG(1SBR01) Substructure

#304 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 8:52 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works is in progress


CIVIL1 SCL PG Nov 23, 2022

Prabhu- pile cap reinforcement are done


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC1,2,3,4 & 5 inspected and all comments mentioned in C3 Stamp.
QC CIVIL SCL PG Nov 30, 2022

Gandhi Rajan: PC1 8,9,10,11 & 13 inspected and all comments mentioned in C3 Stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified


CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Prepared by QC CIVIL SCL PG 169 Created with PlanGrid


CRG(1SBR01) Substructure

Photos

IMG_4054
IMG_4051
CIVIL1 SCL PG
CIVIL1 SCL PG
Nov 30, 2022 6:37 PM
Nov 30, 2022 6:37 PM

Prepared by QC CIVIL SCL PG 170 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4044
CIVIL1 SCL PG
Nov 30, 2022 5:16 PM

IMG_4320
CIVIL1 SCL PG
Nov 30, 2022 7:41 AM

Prepared by QC CIVIL SCL PG 171 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4316 IMG_4324
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:41 AM Nov 30, 2022 7:41 AM

Prepared by QC CIVIL SCL PG 172 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4323
CIVIL1 SCL PG
Nov 30, 2022 7:41 AM

IMG_4325
CIVIL1 SCL PG
Nov 30, 2022 7:41 AM

Prepared by QC CIVIL SCL PG 173 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4326 IMG_4328
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:41 AM Nov 30, 2022 7:41 AM

Prepared by QC CIVIL SCL PG 174 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4329 IMG_4327
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 7:41 AM Nov 30, 2022 7:41 AM

Prepared by QC CIVIL SCL PG 175 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2108
CIVIL1 SCL PG
Nov 29, 2022 6:14 PM

IMG_4330
CIVIL1 SCL PG
Nov 30, 2022 7:41 AM

IMG_2104 IMG_2106
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:14 PM Nov 29, 2022 6:14 PM

Prepared by QC CIVIL SCL PG 176 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2112 IMG_2113
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:14 PM Nov 29, 2022 6:14 PM

IMG_2107 IMG_2110
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:14 PM Nov 29, 2022 6:14 PM

Prepared by QC CIVIL SCL PG 177 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1895
CIVIL1 SCL PG
Nov 23, 2022 10:44 PM

IMG_1875
CIVIL1 SCL PG
Nov 23, 2022 10:45 PM

IMG_1893 IMG_1877
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:44 PM Nov 23, 2022 10:44 PM

Prepared by QC CIVIL SCL PG 178 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1884 IMG_1885
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:44 PM Nov 23, 2022 10:44 PM

IMG_1892 IMG_1894
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:44 PM Nov 23, 2022 10:44 PM

Prepared by QC CIVIL SCL PG 179 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1876 IMG_1878
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:44 PM Nov 23, 2022 10:44 PM

IMG_1882 IMG_1883
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 23, 2022 10:44 PM Nov 23, 2022 10:44 PM

Prepared by QC CIVIL SCL PG 180 Created with PlanGrid


CRG(1SBR01) Substructure

#305 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 7:42 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

Shijo- No Electrical Services on pile cap.


MEP SCL PG Nov 30, 2022

Shameer- No Plumbing Services on pile cap.


MEP SCL PG Nov 30, 2022

Abdul Nafih- Noted. Stamp closed


QC MEP SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 181 Created with PlanGrid


CRG(1SBR01) Substructure

11_29_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Nov 30, 2022 5:37 PM

Prepared by QC CIVIL SCL PG 182 Created with PlanGrid


CRG(1SBR01) Substructure

#306 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 8:52 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- deadshuter (block work)completed backfilling is in progress


CIVIL1 SCL PG Nov 23, 2022

PRADEEP ILANGO:- Formwork and backfilling completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC 8,9,10,12 & 13 Pile cap reinforcement checked and found comments 1. Top mesh
spacing to be aligned and rectified. 2. cleaning of pile rebars, 3. protection of verticals before casting.4.
complete backfilling around the pile cap. 5. All supporting documents : turkish checklist , WIR approval ,
DM approval and concrete clearance to be attached. 6.curing photos to be updated in C4 stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and documents attached
CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 183 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4055
CIVIL1 SCL PG
Nov 30, 2022 7:00 PM

31248bf6-b8c5-45f9-95a2-050f1eb2e1a0
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 184 Created with PlanGrid


CRG(1SBR01) Substructure

a1cc149e-3301-4dca-93f8-51800f060388
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

afb4efd3-e8bb-49de-9c03-cd031b32af1c
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 185 Created with PlanGrid


CRG(1SBR01) Substructure

b6c2d57b-a61c-4780-ab7a-cd5b10ae41df
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

29703bb7-788b-4162-a6bf-6e63b0618002
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

9ba2793d-e588-433e-9117-7962ea26f21a 71603062-9d05-43d8-97ec-db45e5819727
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 186 Created with PlanGrid


CRG(1SBR01) Substructure

59e4510e-220d-4c84-a420-b037fd76061e dbcabc6a-78c7-45fa-9d3c-acbfcbc3c153
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 187 Created with PlanGrid


CRG(1SBR01) Substructure

9b7670e3-10ab-4f0d-810f-dac926afab70 44a683db-7c62-42a2-8216-d2e2e9167e28
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 188 Created with PlanGrid


CRG(1SBR01) Substructure

59db1df1-be6d-4e67-a366-91fabb54d182 7b2e95fb-b855-4fe8-b1ac-33d7a71b9355
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 189 Created with PlanGrid


CRG(1SBR01) Substructure

2b8ca956-4df0-44a2-9f90-b7a0c8033158 6363a776-08cb-491b-af82-50e71f5a5385
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 190 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4052 IMG_4053
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:38 PM Nov 30, 2022 6:38 PM

IMG_2223
IMG_4046 CIVIL1 SCL PG
CIVIL1 SCL PG Nov 30, 2022 4:56 PM
Nov 30, 2022 5:13 PM

Prepared by QC CIVIL SCL PG 191 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_3941
CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

2c0fcd06-2dec-40fb-a46a-d756829d27c5
CIVIL1 SCL PG
Nov 29, 2022 6:14 PM

e78e5969-eefc-4422-85a5-e0ace18037c2 224cdfaa-5822-4639-b891-e8bca367574f
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 29, 2022 6:14 PM Nov 29, 2022 6:14 PM

Prepared by QC CIVIL SCL PG 192 Created with PlanGrid


CRG(1SBR01) Substructure

#307 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 2:41 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- pilecap concreting completed


CIVIL1 SCL PG Dec 4, 2022

PRADEEP ILANGO:- curing ensured for 7 days


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found Satisfactory. stamp closed


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 193 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2273 IMG_2272
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 4, 2022 9:50 PM Dec 4, 2022 9:50 PM

IMG_2274
CIVIL1 SCL PG
Dec 4, 2022 9:50 PM

PHOTO-2022-12-01-21-13-12
CIVIL1 SCL PG
Dec 4, 2022 9:50 PM

Prepared by QC CIVIL SCL PG 194 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-02-05-40-40
CIVIL1 SCL PG
Dec 4, 2022 9:50 PM

PHOTO-2022-12-03-07-28-06
CIVIL1 SCL PG
Dec 4, 2022 9:50 PM

Prepared by QC CIVIL SCL PG 195 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-02-05-40-41 PHOTO-2022-12-01-21-13-13
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 4, 2022 9:50 PM Dec 4, 2022 9:50 PM

Prepared by QC CIVIL SCL PG 196 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-02-05-40-40 2 PHOTO-2022-12-02-05-40-42
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 4, 2022 9:50 PM Dec 4, 2022 9:50 PM

Prepared by QC CIVIL SCL PG 197 Created with PlanGrid


CRG(1SBR01) Substructure

PHOTO-2022-12-03-07-27-47
CIVIL1 SCL PG
Dec 4, 2022 9:50 PM

Prepared by QC CIVIL SCL PG 198 Created with PlanGrid


CRG(1SBR01) Substructure

#308 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 9:07 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Nov 29, 2022

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC 23,24,25 & 26 inspected and all comments mentioned in C3 Stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified


CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 199 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2235
CIVIL1 SCL PG
Nov 30, 2022 9:07 PM

IMG_4058
CIVIL1 SCL PG
Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 200 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4061 IMG_4059
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 201 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4062 IMG_4064
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 202 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4056 IMG_4057
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 203 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4054

IMG_4063 CIVIL1 SCL PG

CIVIL1 SCL PG Nov 30, 2022 6:38 PM

Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 204 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4051
CIVIL1 SCL PG 20221130_174607_photo
Nov 30, 2022 6:38 PM QC CIVIL SCL PG
Nov 30, 2022 5:46 PM

Prepared by QC CIVIL SCL PG 205 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4047
CIVIL1 SCL PG
Nov 30, 2022 5:30 PM

20221130_174341_photo
QC CIVIL SCL PG
Nov 30, 2022 5:43 PM

IMG_2102 IMG_2108
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:16 AM Nov 30, 2022 8:16 AM

Prepared by QC CIVIL SCL PG 206 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1880 IMG_2109
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:16 AM Nov 30, 2022 8:16 AM

IMG_1876 IMG_2103
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:16 AM Nov 30, 2022 8:16 AM

Prepared by QC CIVIL SCL PG 207 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_1878
CIVIL1 SCL PG
Nov 30, 2022 8:16 AM

IMG_1875
CIVIL1 SCL PG
Nov 30, 2022 8:16 AM

IMG_1881
CIVIL1 SCL PG
Nov 30, 2022 8:16 AM

Prepared by QC CIVIL SCL PG 208 Created with PlanGrid


CRG(1SBR01) Substructure

#309 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 7:42 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works is in progress


CIVIL1 SCL PG Nov 29, 2022

Shijo- No Electrical Services on pile cap.


MEP SCL PG Nov 30, 2022

Shameer- No mechanical Services on pile cap.


MEP SCL PG Nov 30, 2022

Abdul Nafih- Noted. Stamp close


QC MEP SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 209 Created with PlanGrid


CRG(1SBR01) Substructure

11_29_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Nov 30, 2022 5:38 PM

Prepared by QC CIVIL SCL PG 210 Created with PlanGrid


CRG(1SBR01) Substructure

#310 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Nov 7, 2022 3:42 PM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Nov 30, 2022 9:07 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Nov 30, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- backfilling is in progress


CIVIL1 SCL PG Nov 29, 2022

PRADEEP ILANGO:- Formwork and backfilling completed


CIVIL1 SCL PG Nov 30, 2022

Gandhi Rajan: PC 23,24,25 & 26 Pile cap reinforcement checked and found comments 1. Top mesh
spacing to be aligned and rectified. 2. cleaning of pile rebars, 3. protection of verticals before casting.4.
complete backfilling around the pile cap. 5. All supporting documents : turkish checklist , WIR approval ,
DM approval and concrete clearance to be attached. 6.curing photos to be updated in C4 stamp.
QC CIVIL SCL PG Nov 30, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and documents attached
CIVIL1 SCL PG Nov 30, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Nov 30, 2022

Photos

Prepared by QC CIVIL SCL PG 211 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_2235
CIVIL1 SCL PG
Nov 30, 2022 9:07 PM

IMG_4058
CIVIL1 SCL PG
Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 212 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4062 IMG_4060
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 213 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4059 IMG_4061
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 214 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4056 IMG_4057
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 215 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4063 IMG_4064
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 8:59 PM Nov 30, 2022 8:59 PM

Prepared by QC CIVIL SCL PG 216 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4055
CIVIL1 SCL PG
Nov 30, 2022 7:00 PM

ef5ff4e2-53fe-45f3-9809-e9d52f475595
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 217 Created with PlanGrid


CRG(1SBR01) Substructure

2fcedd9e-6041-41e4-ac34-2db932024ad0
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

7b2e95fb-b855-4fe8-b1ac-33d7a71b9355
CIVIL1 SCL PG
Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 218 Created with PlanGrid


CRG(1SBR01) Substructure

f0c17336-417b-4be3-9f3f-48d707f71724 6363a776-08cb-491b-af82-50e71f5a5385
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 219 Created with PlanGrid


CRG(1SBR01) Substructure

17ff05b2-03a8-49bd-96a2-738d576a49de b16bf1e0-8ecc-46ca-a5ee-91af7c6661cd
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 220 Created with PlanGrid


CRG(1SBR01) Substructure

c700bbd5-744b-418b-9c30-5564bf22e09e daa5e528-39e6-4012-9d6a-d2c8897db1bd
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:40 PM Nov 30, 2022 6:40 PM

Prepared by QC CIVIL SCL PG 221 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4052 IMG_4053
CIVIL1 SCL PG CIVIL1 SCL PG
Nov 30, 2022 6:39 PM Nov 30, 2022 6:39 PM

IMG_2223
IMG_4046 CIVIL1 SCL PG
CIVIL1 SCL PG Nov 30, 2022 4:56 PM
Nov 30, 2022 5:15 PM

Prepared by QC CIVIL SCL PG 222 Created with PlanGrid


CRG(1SBR01) Substructure

e78e5969-eefc-4422-85a5-e0ace18037c2
CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

IMG_3941
CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

Prepared by QC CIVIL SCL PG 223 Created with PlanGrid


CRG(1SBR01) Substructure

2c0fcd06-2dec-40fb-a46a-d756829d27c5
CIVIL1 SCL PG
Nov 30, 2022 7:01 AM

Prepared by QC CIVIL SCL PG 224 Created with PlanGrid


CRG(1SBR01) Substructure

#583 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 22, 2022 9:30 AM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 22, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- concreting completed


CIVIL1 SCL PG Dec 15, 2022

PRADEEP ILANGO :- curing ensured


CIVIL1 SCL PG Dec 21, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 22, 2022

Photos

Prepared by QC CIVIL SCL PG 225 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4666
CIVIL1 SCL PG
Dec 21, 2022 3:24 PM

IMG_4673
CIVIL1 SCL PG
Dec 21, 2022 3:24 PM

Prepared by QC CIVIL SCL PG 226 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4672 IMG_4671
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 21, 2022 3:24 PM Dec 21, 2022 3:24 PM

Prepared by QC CIVIL SCL PG 227 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_101034_photo
CIVIL1 SCL PG
Dec 15, 2022 10:10 AM

IMG_4669
CIVIL1 SCL PG
Dec 21, 2022 3:24 PM

Prepared by QC CIVIL SCL PG 228 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_101024_photo 20221215_100957_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 15, 2022 10:10 AM Dec 15, 2022 10:09 AM

Prepared by QC CIVIL SCL PG 229 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_100942_photo
CIVIL1 SCL PG
Dec 15, 2022 10:09 AM

Prepared by QC CIVIL SCL PG 230 Created with PlanGrid


CRG(1SBR01) Substructure

#584 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 7:55 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- Tie-beam rebar works started


CIVIL1 SCL PG Dec 14, 2022

Suresh-- No Electrical service


MEP SCL PG Dec 14, 2022

Shameer- No mechanical services.


MEP SCL PG Dec 14, 2022

Abdul Nafih- No MEP Service.Stamp closed.


QC MEP SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 231 Created with PlanGrid


CRG(1SBR01) Substructure

12_14_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Dec 14, 2022 6:41 PM

Prepared by QC CIVIL SCL PG 232 Created with PlanGrid


CRG(1SBR01) Substructure

#585 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 9:59 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam inspected and found comments for rectification in C3 stamp
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 233 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4445
CIVIL1 SCL PG IMG_4444
Dec 14, 2022 4:25 PM CIVIL1 SCL PG
Dec 14, 2022 4:25 PM

Prepared by QC CIVIL SCL PG 234 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_091611_photo 20221214_091559_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:16 AM Dec 14, 2022 9:16 AM

Prepared by QC CIVIL SCL PG 235 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_091545_photo 20221214_091532_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:15 AM Dec 14, 2022 9:15 AM

Prepared by QC CIVIL SCL PG 236 Created with PlanGrid


CRG(1SBR01) Substructure

#586 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 9:59 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- Formwork completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam TBPC1 inspected and found comments for rectification 1. Cleaning 2. Steel to
be provided as per Drawing 3. binding to be done. 4. MEP clearance to be obtained 5. attach turkish
checklist 6. attach PNCA Approval copy. 7. attach concrete survey clearance.
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned comments were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 237 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4464
CIVIL1 SCL PG
Dec 14, 2022 9:52 PM

IMG_4455_edited
CIVIL1 SCL PG
Dec 14, 2022 8:37 PM

Prepared by QC CIVIL SCL PG 238 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4455 d98d9b34-26ae-4482-ba0c-b0b957b717cc
CIVIL1 SCL PG QC CIVIL SCL PG
Dec 14, 2022 8:37 PM Dec 14, 2022 7:32 PM

Prepared by QC CIVIL SCL PG 239 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4449
CIVIL1 SCL PG
Dec 14, 2022 4:38 PM

IMG_4448
CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

IMG_4447
CIVIL1 SCL PG IMG_4446
Dec 14, 2022 4:26 PM CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

Prepared by QC CIVIL SCL PG 240 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4441
CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

IMG_4444
CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

Prepared by QC CIVIL SCL PG 241 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_091832_photo 20221214_091816_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:18 AM Dec 14, 2022 9:18 AM

Prepared by QC CIVIL SCL PG 242 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_091645_photo 20221214_091636_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:16 AM Dec 14, 2022 9:16 AM

Prepared by QC CIVIL SCL PG 243 Created with PlanGrid


CRG(1SBR01) Substructure

#587 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 22, 2022 9:30 AM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 22, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- concreting completed


CIVIL1 SCL PG Dec 15, 2022

PRADEEP ILANGO:- curing ensured


CIVIL1 SCL PG Dec 21, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 22, 2022

Photos

Prepared by QC CIVIL SCL PG 244 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4664
CIVIL1 SCL PG
Dec 21, 2022 3:26 PM

IMG_4660
CIVIL1 SCL PG
Dec 21, 2022 3:26 PM

IMG_4659 IMG_4663
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 21, 2022 3:26 PM Dec 21, 2022 3:26 PM

Prepared by QC CIVIL SCL PG 245 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_102756_photo 20221215_102729_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 15, 2022 10:47 AM Dec 15, 2022 10:27 AM

Prepared by QC CIVIL SCL PG 246 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_102720_photo 20221215_102659_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 15, 2022 10:27 AM Dec 15, 2022 10:27 AM

Prepared by QC CIVIL SCL PG 247 Created with PlanGrid


CRG(1SBR01) Substructure

#588 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 8:20 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Dec 14, 2022

Shameer-No mechanical services.


MEP SCL PG Dec 14, 2022

Suresh-No Electrical services.


MEP SCL PG Dec 14, 2022

Abdul Nafih- No MEP Service.Stamp closed.


QC MEP SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 248 Created with PlanGrid


CRG(1SBR01) Substructure

12_14_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Dec 14, 2022 6:48 PM

Prepared by QC CIVIL SCL PG 249 Created with PlanGrid


CRG(1SBR01) Substructure

#589 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 9:58 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam inspected and found comments for rectification in C3 stamp
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 250 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4445
CIVIL1 SCL PG IMG_4444
Dec 14, 2022 4:26 PM CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

Prepared by QC CIVIL SCL PG 251 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4435
CIVIL1 SCL PG
Dec 14, 2022 10:05 AM

IMG_4437
CIVIL1 SCL PG
Dec 14, 2022 10:05 AM

Prepared by QC CIVIL SCL PG 252 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4438
CIVIL1 SCL PG
Dec 14, 2022 10:05 AM

IMG_4436
CIVIL1 SCL PG
Dec 14, 2022 10:05 AM

Prepared by QC CIVIL SCL PG 253 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4434
CIVIL1 SCL PG
Dec 14, 2022 10:05 AM

Prepared by QC CIVIL SCL PG 254 Created with PlanGrid


CRG(1SBR01) Substructure

#590 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Dec 7, 2022 11:02 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 9:58 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- Formwork completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam inspected and found comments for rectification 1. Cleaning 2. Steel to be
provided as per Drawing 3. binding to be done. 4. MEP clearance to be obtained 5. attach turkish
checklist 6. attach PNCA Approval copy. 7. attach concrete survey clearance.
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 255 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4464
CIVIL1 SCL PG
Dec 14, 2022 9:53 PM

IMG_4462_edited
CIVIL1 SCL PG
Dec 14, 2022 8:51 PM

Prepared by QC CIVIL SCL PG 256 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4451_edited 45b4d154-a2b9-49cd-a506-22f6e4b59a9b
CIVIL1 SCL PG QC CIVIL SCL PG
Dec 14, 2022 8:38 PM Dec 14, 2022 7:31 PM

Prepared by QC CIVIL SCL PG 257 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4449
CIVIL1 SCL PG
Dec 14, 2022 4:38 PM

dcf13e06-5654-4888-8bb8-aace64d31907
QC CIVIL SCL PG
Dec 14, 2022 7:31 PM

Prepared by QC CIVIL SCL PG 258 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4441
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM
IMG_4448
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

IMG_4447
IMG_4446 CIVIL1 SCL PG
CIVIL1 SCL PG Dec 14, 2022 4:27 PM
Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 259 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4444
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM IMG_4437
CIVIL1 SCL PG
Dec 14, 2022 10:06 AM

Prepared by QC CIVIL SCL PG 260 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4435
CIVIL1 SCL PG
Dec 14, 2022 10:06 AM

IMG_4434
CIVIL1 SCL PG
Dec 14, 2022 10:06 AM

Prepared by QC CIVIL SCL PG 261 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4438
CIVIL1 SCL PG
Dec 14, 2022 10:06 AM

IMG_4436
CIVIL1 SCL PG
Dec 14, 2022 10:06 AM

Prepared by QC CIVIL SCL PG 262 Created with PlanGrid


CRG(1SBR01) Substructure

#591 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 22, 2022 9:30 AM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 22, 2022
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- concreting completed


CIVIL1 SCL PG Dec 15, 2022

PRADEEP ILANGO:- curing ensured


CIVIL1 SCL PG Dec 21, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 22, 2022

Photos

Prepared by QC CIVIL SCL PG 263 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4664 IMG_4665
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 21, 2022 3:26 PM Dec 21, 2022 3:26 PM

IMG_4666
CIVIL1 SCL PG
Dec 21, 2022 3:26 PM

IMG_4667
CIVIL1 SCL PG
Dec 21, 2022 3:26 PM

Prepared by QC CIVIL SCL PG 264 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_105038_photo
CIVIL1 SCL PG
Dec 15, 2022 10:50 AM

IMG_4672
CIVIL1 SCL PG
Dec 21, 2022 3:26 PM

Prepared by QC CIVIL SCL PG 265 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_105028_photo 20221215_105013_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 15, 2022 10:50 AM Dec 15, 2022 10:50 AM

Prepared by QC CIVIL SCL PG 266 Created with PlanGrid


CRG(1SBR01) Substructure

#592 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 8:20 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

Shameer-No mechanical services.


MEP SCL PG Dec 14, 2022

Suresh-No Electrical services.


MEP SCL PG Dec 14, 2022

Abdul Nafih- No MEP Service.Stamp closed.


QC MEP SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 267 Created with PlanGrid


CRG(1SBR01) Substructure

12_14_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Dec 14, 2022 6:48 PM

Prepared by QC CIVIL SCL PG 268 Created with PlanGrid


CRG(1SBR01) Substructure

#593 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 9:58 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam inspected and found comments for rectification in C3 stamp
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 269 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4445
CIVIL1 SCL PG IMG_4444
Dec 14, 2022 4:26 PM CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

Prepared by QC CIVIL SCL PG 270 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_093907_photo 20221214_093853_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:39 AM Dec 14, 2022 9:38 AM

Prepared by QC CIVIL SCL PG 271 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_093822_photo 20221214_093805_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:38 AM Dec 14, 2022 9:38 AM

Prepared by QC CIVIL SCL PG 272 Created with PlanGrid


CRG(1SBR01) Substructure

#594 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 15, 2022 10:49 AM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 15, 2022
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- Formwork completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam TBPC2D inspected and found comments for rectification 1. Cleaning 2. Steel to
be provided as per Drawing 3. binding to be done. 4. MEP clearance to be obtained 5. attach turkish
checklist 6. attach PNCA Approval copy. 7. attach concrete survey clearance.
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 273 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4464
CIVIL1 SCL PG
Dec 14, 2022 9:53 PM

IMG_4460_edited
CIVIL1 SCL PG
Dec 14, 2022 8:45 PM

Prepared by QC CIVIL SCL PG 274 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4450_edited c5ddd204-775b-42e7-89c1-a41f75032184
CIVIL1 SCL PG QC CIVIL SCL PG
Dec 14, 2022 8:41 PM Dec 14, 2022 7:30 PM

Prepared by QC CIVIL SCL PG 275 Created with PlanGrid


CRG(1SBR01) Substructure

ebec9c64-063e-4b4f-85c0-0b2d5f682f8d a079e214-2601-48cd-b8b6-6fb6da667061
QC CIVIL SCL PG QC CIVIL SCL PG
Dec 14, 2022 7:29 PM Dec 14, 2022 7:29 PM

Prepared by QC CIVIL SCL PG 276 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4449
CIVIL1 SCL PG
Dec 14, 2022 4:39 PM

IMG_4446
CIVIL1 SCL PG
Dec 14, 2022 4:28 PM

IMG_4441
CIVIL1 SCL PG
Dec 14, 2022 4:28 PM
IMG_4447
CIVIL1 SCL PG
Dec 14, 2022 4:28 PM

Prepared by QC CIVIL SCL PG 277 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4448
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM
IMG_4444
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 278 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_093839_photo 20221214_093658_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:38 AM Dec 14, 2022 9:37 AM

Prepared by QC CIVIL SCL PG 279 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_093643_photo 20221214_093634_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:36 AM Dec 14, 2022 9:36 AM

Prepared by QC CIVIL SCL PG 280 Created with PlanGrid


CRG(1SBR01) Substructure

#595 C4 Pile Cap & Tie Beam Concrete/Curing Approval - Next Sub Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Jan 12, 2023 3:15 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Jan 12, 2023
Description
Pile Cap & Tie Beam
Concrete/Curing Approval -
Next Sub Clearance

Comments

PRADEEP ILANGO:- concreting completed


CIVIL1 SCL PG Dec 15, 2022

PRADEEP ILANGO:- curing ensured


CIVIL1 SCL PG Dec 21, 2022

PRADEEP ILANGO:- status changed to pending, all documents attached


CIVIL1 SCL PG Jan 12, 2023

Gandhi rajan: Found satisfactory. stamp closed.


QC CIVIL SCL PG Jan 12, 2023

Photos

Prepared by QC CIVIL SCL PG 281 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_5511
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

IMG_5510
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

IMG_4665
CIVIL1 SCL PG
Dec 21, 2022 3:25 PM

IMG_4661
CIVIL1 SCL PG
Dec 21, 2022 3:25 PM

Prepared by QC CIVIL SCL PG 282 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4662 IMG_4672
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 21, 2022 3:25 PM Dec 21, 2022 3:25 PM

Prepared by QC CIVIL SCL PG 283 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4666
CIVIL1 SCL PG
Dec 21, 2022 3:25 PM

IMG_4673
CIVIL1 SCL PG
Dec 21, 2022 3:25 PM

Prepared by QC CIVIL SCL PG 284 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_101219_photo
CIVIL1 SCL PG
Dec 15, 2022 10:12 AM

IMG_4668
CIVIL1 SCL PG
Dec 21, 2022 3:25 PM

Prepared by QC CIVIL SCL PG 285 Created with PlanGrid


CRG(1SBR01) Substructure

20221215_101131_photo 20221215_101123_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 15, 2022 10:11 AM Dec 15, 2022 10:11 AM

Prepared by QC CIVIL SCL PG 286 Created with PlanGrid


CRG(1SBR01) Substructure

#596 C1 MEP Approval – Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical
Starter Rebar/Water Stopper Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Dec 14, 2022 7:56 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Dec 14, 2022
Description
MEP Approval – Pile Rebar
Dev. Length /Pile Cap, Tie
Beam & Vertical Starter
Rebar/Water Stopper
Clearance

Comments

PRADEEP ILANGO:- rebar works started


CIVIL1 SCL PG Dec 14, 2022

Suresh--No Electrical services


MEP SCL PG Dec 14, 2022

Shameer-No mechanical services.


MEP SCL PG Dec 14, 2022

Abdul Nafih- No MEP Service.Stamp closed.


QC MEP SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 287 Created with PlanGrid


CRG(1SBR01) Substructure

12_14_2022_Work Clearance Request (V1.0)_Draft_page-0001


MEP SCL PG
Dec 14, 2022 6:46 PM

Prepared by QC CIVIL SCL PG 288 Created with PlanGrid


CRG(1SBR01) Substructure

#597 C2 IR Pile Rebar Dev. Length /Pile Cap, Tie Beam & Vertical Starter Rebar/
Water Stopper Approval ‐ Formwork Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Jan 12, 2023 3:14 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Jan 12, 2023
Description
IR Pile Rebar Dev. Length /
Pile Cap, Tie Beam &
Vertical Starter Rebar/Water
Stopper Approval ‐
Formwork Clearance

Comments

PRADEEP ILANGO:- rebar works completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam inspected and found comments for rectification in C3 stamp
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 289 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4445
CIVIL1 SCL PG
Dec 14, 2022 4:26 PM

IMG_5504
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

Prepared by QC CIVIL SCL PG 290 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4444
CIVIL1 SCL PG
Dec 14, 2022 4:26 PM 20221214_092755_photo
CIVIL1 SCL PG
Dec 14, 2022 9:27 AM

Prepared by QC CIVIL SCL PG 291 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_092732_photo 20221214_092453_photo
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 9:27 AM Dec 14, 2022 9:24 AM

Prepared by QC CIVIL SCL PG 292 Created with PlanGrid


CRG(1SBR01) Substructure

20221214_092445_photo
CIVIL1 SCL PG
Dec 14, 2022 9:24 AM

Prepared by QC CIVIL SCL PG 293 Created with PlanGrid


CRG(1SBR01) Substructure

#598 C3 Formwork Approval ‐ Pile Cap & Tie Beam Concrete/Curing Clearance

Status Created Sheet


Closed Dec 7, 2022 11:03 AM Zone 01_Main 1 Sub C_(TB)
qccivil.scl.pg@sobhaconst.c
Type om
Planned Work
Last Updated
List Jan 12, 2023 3:14 PM
SBR1‐C Pile Cap/Tie Beam
Rebar, Formwork/Concrete Closed At
Jan 12, 2023
Description
Formwork Approval ‐ Pile
Cap & Tie Beam Concrete/
Curing Clearance

Comments

PRADEEP ILANGO:- Formwork completed


CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Tie beam TBC6A inspected and found comments for rectification 1. Cleaning 2. Steel to
be provided as per Drawing 3. binding to be done. 4. MEP clearance to be obtained 5. attach turkish
checklist 6. attach PNCA Approval copy. 7. attach concrete survey clearance.
QC CIVIL SCL PG Dec 14, 2022

PRADEEP ILANGO:- all mentioned were rectified and documents were uploaded
CIVIL1 SCL PG Dec 14, 2022

Gandhi rajan: Found satisfactory.


QC CIVIL SCL PG Dec 14, 2022

Photos

Prepared by QC CIVIL SCL PG 294 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_5504 IMG_5508
CIVIL1 SCL PG CIVIL1 SCL PG
Jan 12, 2023 12:39 PM Jan 12, 2023 12:38 PM

Prepared by QC CIVIL SCL PG 295 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_5509
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

IMG_5505
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

Prepared by QC CIVIL SCL PG 296 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4464
CIVIL1 SCL PG
Dec 14, 2022 9:53 PM

IMG_5507
CIVIL1 SCL PG
Jan 12, 2023 12:38 PM

Prepared by QC CIVIL SCL PG 297 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4449
CIVIL1 SCL PG
Dec 14, 2022 4:38 PM

1574f405-58e7-44fa-a1a9-9c4395c6373f
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 298 Created with PlanGrid


CRG(1SBR01) Substructure

7278d1d5-e26c-4219-951e-3541097cf43f ff967300-d2ef-444e-9089-d3b5c9171498
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 4:27 PM Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 299 Created with PlanGrid


CRG(1SBR01) Substructure

6c371c90-c5e6-40dd-af65-202d54b403e1 f7f4fa57-53f0-4a12-adb7-5a6680284584
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 4:27 PM Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 300 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4447 IMG_4448
CIVIL1 SCL PG CIVIL1 SCL PG
Dec 14, 2022 4:27 PM Dec 14, 2022 4:27 PM

IMG_4441
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

IMG_4446
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 301 Created with PlanGrid


CRG(1SBR01) Substructure

IMG_4444
CIVIL1 SCL PG
Dec 14, 2022 4:27 PM

Prepared by QC CIVIL SCL PG 302 Created with PlanGrid