Check List for Drainage, Electrical Duct, Firefighting system Design for
civil Work of CPA
Deadline for submission
1. All draft drawing, calculation, BOQ and specification within 31 th March 2023. 2. All final drawing, calculation, BOQ and specification within 6 th April 2023.
List of submittals (For Draft and final)
Sl No Item
1 Drainage and Sewerage A. Plan
B. Detail Drawing C. Specification D. BOQ E. Calculation and Report 2 Civil work of Electrical system A. Plan and Cable Box B. Detail Drawing C. Specification D. BOQ E. Calculation and Report 3 Fire Fighting System A. Plan B. Detail Drawing C. Specification D. BOQ E. Calculation and Report Responsible Person and Progress of work
Sl No Item Scope of work Responsible Person Draft Final
31/03/2023 06/04/2023 1 Drainage A. Plan SM Engineering and B. Detail Drawing SM Engineering Sewerage C. Specification SM Engineering D. BOQ SM Engineering E. Calculation and Report SM Engineering 2 Civil work A. Plan SM Engineering of B. Detail Drawing SM Engineering Electrical C. Specification SM Engineering system and D. BOQ SM Engineering Cable Box E. Calculation and Report SM Engineering 3 Fire A. Plan SM Engineering Fighting B. Detail Drawing SM Engineering System C. Specification SM Engineering D. BOQ SM Engineering E. Calculation and Report SM Engineering