JOB SAFETY ANALYSIS

Job Title/Task: QMS Document No: Rev:00 Date: Page:


Pumping of main stimulation treatment NISNL/OPS/RA/05 23/03/2019 1 of 1

Department: Location: Analysed By: Reviewed By: Approved By: RPC: (Risk Priority Code):
Operations Port Harcourt Temitope Adewumi Dumbari Nwikwor Austin Edema 3

REVIEW (completed offshore – use Review of JSA’s Work Method)


H.SC: (HAZARD SEVERITY CODE)
R.P.C: (RISK PRIORITY CODE)
Reviewed By: Supervisor: Date: Plant/Location:

Sequence of Basic Hazard Hazard Effect HSC RPC Risk Reduction Measures HSC RPC
Job Steps
1. Tool box meeting. Bad information. 1.1 Personnel injury. 2 2 1.1.1 Ensure all personnel have all relevant 2 3
information.
2. Check pop off Pop off valves set 2.1 Equipment damage. 2 3 2.1.1 Check pop off valves before starting 2 3
valves. wrongly. treatment.
3. Ensure well is open Bleed off line open 3.1 Personnel injury. 3 3 3.1 Ensure bleed off valves are closed before 3 3
and bleed off line is when well master opening the well.
closed. valve is open. 3.2 Equipment damage 3 3 3.2 Ensure bleed off valves is closed before start 3 3
pumping.
Chemical spills. 3.3 Environment 2 3
damage.
4. Inform all Personnel not 4.1 Personnel injury. 3 3 4.1 Inform all personnel on board before starting 3 3
personnel before informed before job job.
starting job start.

Moving equipment.
5. Start job. Well screens out. 5.1 Personnel injury. 2 3 5.1.1 Inform personnel to keep clear of all 2 3
treating lines.
Unexpected pressure 5.2 Equipment damage. 2 3 5.1.2 Check mechanical over pressure settings. 2 3
NISNL/OPS/RA/05 Once printed this document becomes uncontrolled Page 1 of 2
release.
5.3 Environment 2 3 5.1.3 Install warning tapes and signs. 2 3
Well valve closes. damage.
5.1.4 Designate personnel for oil based fluid 2 3
Treating lines breaks. release containment and clean up.

Well out of control. 5.1.5 Provide eyewash station in case of spill 2 3


on personnel.

5.1.6 Use soda ash for neutralization of spill 2 3


acid.
6. Bleed of lines. Pressure trapped on 6.1 Personnel injury. 3 2 6.1.1 Before bleeding off ensure that well is 3 3
treating lines. closed.
6.2 Equipment damage. 1 3 3 3
Treating line not 6.1.2 Before rigging down check that lines are
properly closed. 6.3 Chemical spill. 3 3 flushed clean and that pressure is zero.

Well not closed. 6.1.3 Then commence rig down.

NISNL/OPS/RA/05 Once printed this document becomes uncontrolled Page 2 of 2