JOB SAFETY ANALYSIS

Job Title/Task: QMS Document No: Rev: 00 Date:23/03/2019 Page:


Function test Equipment NISNL/OPS/RA/03 1 of 1
Department: Location: Analysed By: Reviewed By: Approved By: RPC: (Risk Priority Code):
Operations Port Harcourt Temitope Adewumi Dumbari Nwikpor Austin Edema 3

REVIEW (completed offshore – use Review of JSA’s Work Method)

Reviewed By: Supervisor: Date: Location:

Sequence of Hazard Hazard BEFORE RPC Risk Reduction Measures AFTER RPC
Basic Job Effect Severity/ Severity/
Steps Probability Probability
Function test Unexpected Personnel 1. Fatal or 3 1.1 Hold pre job meeting. 1. No injury/ 3
Equipment. Pressure injury. Permanent 1.2 Wear PPE. illness.
Release, Disabling 1.3 Use caution tape to barricade work area. Probability:
High injury. 1.4 Use qualified personnel for all operation. remote, not likely
velocity Probability: 1.5 Clear area of all non essential personnel. but possible
fluid. remote, not 1.6 Communicate job plan procedure to all personnel.
likely but
possible

NISNL/OPS/RA/03 Once printed this document becomes uncontrolled Page 1 of 1