MONTHLY PROGRESS REPORT

NO. 23
FEBRUARY ‘23

APPENDIX IV
Works Contract Claims

March 2023
List of documents:

1. Summary Table- Claims recorded to date (February ’23)


2. This month's claim events (nothing to record)
1. Claim’s status till the end of February 2023

Relevant
Letter Ref.
No Date Subject Contract Status
No
Clauses
Agreement
ALB_08 Request for Extension of Time due Cl: 2.4-8.4-
1 18/08/2021 signed by
0077-21 to Delay of Advance Payment. 16.1-20.1
parties
Claim for EoT and additional
Rejected
ALB_08 payment due to “conditionally” Cl: 2.2 - 8.3 -
2 18/02/2022 by the
0249-22 obtained “Construction Work 8.4 - 20.1
Engineer
Permit" by the Employer
Claim for EoT and additional Under
ALB_08 Cl: 2.1 - 8.3 -
3 18/02/2022 payment due to late "Access to the Engineer’s
0251-22 8.4 - 20.1
Site" given by the Employer Review
Claim for EoT and additional Under
ALB_08 Cl: 2.2 - 8.3 -
4 08/04/2022 payment due to disruption "Access Engineer’s
0295-22 8.4 - 20.1
to the Site" in section 4 Review
Engineer
Claim for EoT and additional
suggestion
ALB_08 payment due to “Change in Ci: 3,3-5.1-
5 18/04/2022 to be
0312-22 Legislation"- new seismic coefficient 13.7-8.4-20.1
evaluated
for structures
as VO
Claim for EoT and additional
Cl: 1.13-2.2 - Rejected
ALB_08 payment due to Employer Failure to
6 22/04/2022 8.3 - 8.4 - by the
0326-22 finalize the 3 parties’ agreement for
20.1 Engineer
archaeological in Section 4
Claim for EoT and additional Under
ALB_08 Cl: 14.7-14.8-
06/05/2022 payment due to Contractor's Engineer’s
0335-22 16.1 -20.1
entitlement to suspend work Review
7
Under
ALB_08 Cl: 14.7-14.8-
28/07/2022 Submission of Final Claim Engineer’s
0370-22 16.1 -20.1
Review