MONTHLY PROGRESS REPORT

NO. 23
FEBRUARY ‘23

APPENDIX III
Works Contract Amendments &
Variations

March 2023
List of documents:

1. Summary table of signed Amendments

2. Amendments during this month (nothing to report)


1 Summary table signed Amendments.

Impact
No. Subject Date
Time Cost
Add SoW for the PD of Station Building
CA No.1 30/09/2021 No No
and stops
Additional
Add SoW for the design and build
EoT: 176 1.459.092,43 Euros,
CA No.2 completely 5 New bridges, instead of 15/06/2022
Days taken by the
partial reconstruction
Contingency
Completion of the “Table of adjustment
CA No.3 13/07/2022 No Not defined
Data” included in the Appendix to Tender
Vo. No.2 for “Re-design and Construction Additional 213.541,82
CA No. 4 of three (3) bridges, with new seismic 23/01/2023 No Euros, taken by the
coefficients” Contingency