You are on page 1of 2

[Format 7-1]Table IBI PM T&C Prepare by

PIPE LEAK TEST RECORD


DATE 27/9/2022
T.T.E. ENGINEERING(M) SDN.BHD
REPORT by SHAKIRIN

1.LINE NAME CDA Area PRODUCTION B1


2.SYSTEM NAME 6 Axis Drill Machine #31 (Machine #91) (Refer to the attached Drawings)
3.PIPE SIZE 32 A

4.MATERIAL GI
5.TESTING CONDITION
DI water/City Water/ Nitrogen / Others (         )
1) Test with
Compressed Air (Oil Free / Untreated )
2) Working Pressure 0.93 MPa
3) Testing Pressure 1 MPa
4) Pressure holding Time 30 minutes
5) Testing points All connection / Partial (see the attached drawings)
6.TESTING RESULT
1) Testing Date & time Start 27/9/2022 6.00PM
End 27/9/2022 6.30PM
2) Conducted by TTE Person name CF SIEW
3) Witness IBIDEN/TTE Person name SYAHIR
4) Before Testing 1.10 MPa
5) After Testing 1.10 MPa
6) Result Accept ・Reject Person name/sign
7.TESTING INSTRUMENT
Instrument Name Measurement Range Model Brand Remark
1) Pressure Gauge 0 ~ 2 MPa Unijin
2) ~
3) ~
8.REMARKS
[Format 7-1]Table
9.Reference documents.
  1)Piping schematic shop drawing show testing line
  2)Testing record photo.
  3)Others

Initial Air Leak Testing Pressure = 1.1MPa Initial Air Leak Testing Pressure(S) = 1.1MPa

After Air leak Testing Reading(S) = 1.1MPa After Air leak Testing Reading(S) = 1.1MPa

You might also like