DOCUMENT CODE
GN PRC 0001 1 Of 25
CONTRACTOR EMPLOYER
REV. DATE DESCRIPTION PREPARED BY CHECKED BY
APPROVED
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 2 Of 25
CONTENTS
2. PURCHASING
2.1 Purchasing Procedure
2.2 Approved Vendors
2.3 Inquiry
2.4 Bids
2.5 Technical & Commercial Clarification with Bidder
2.6 Evaluation of Bids
2.7 Bids Opening
2.8 Negotiation with Vendor
2.9 Purchase Order
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 3 Of 25
10. ATTACHMENTS
Attachment 1 Procurement Team Organization
Attachment 2 Procurement Work Flow Diagram
Attachment 3 Bidder List to be invited (Format)
Attachment 4 Purchase Recommendation Sheet (Format)
Attachment 5 Vendor Documents Handling Flow Chart
Attachment 6 Procurement Status Report
Attachment 7 Expediting Follow-up Plan and Time Table (Sample)
Attachment 8 Spare Parts List and Interchangeability Record
Attachment 9 Inspection Activities Flow Diagram
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 4 Of 25
1.1.1 The activities for procurement service and supply of equipment and materials will be
carried out by Project Procurement Team in accordance with the project policies,
procedures and schedules and all other guidelines defined in the contract documents.
1.1.2 In order to comply with project requirements and schedule, procurement service activities
will be managed and coordinated in such a way that;
- Selecting technically qualified Vendors from recommended Vendor list.
- Expediting delivery time of selected Vendors to be consistent with the overall
schedule of the project.
- To meet requirements of contract and specifications
- Early purchasing of Long Lead Items and Critical Items
- Planning inspection activities to meet quality standard
- Effective packing and forwarding plan for safe delivery to JOBSITE
- Give priority to U/G procurement activities
- Give priority to long construction activitie
1.2 Definition
3) Bidder: : The person, firm or corporation who are invited to quote for the
Goods required for the PLANT.
5) OWNER :
7) PLANT :
8) JOBSITE : Those parts of the lands and other places where the Facility is
constructed.
9) Goods : The equipment, materials and machinery to be supplied by
Vendor as per the Purchase Order
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 A3 5 Of 25
10) Purchaser Order : The documents and attachments which govern the Purchase
Order contemplated hereby including, but not limited to
the Material Requisition, the documents listed therein and
specifications, drawings, shipping and packing instructions,
and other descriptions or conditions contained herein and in
such documents.
1.4 Organization
The following personnel will be assigned under the Project Manager for the procurement
function and each member of the organization has the responsibilities as described below
and as Attachment 1 (Procurement Team Organization);
- Procurement PSL
- Buyer
- Expediter
- Field Expediter
- Inspection Coordinator
- Inspector
- Logistics Coordinator
3607/32-PRC-9503
DOCUMENT CODE
- Ensuring the correct quality control related to the supply of equipment and materials.
1.4.2 Buyer
Purchasing service of equipment and materials shall be executed by the qualified buyer
under the direction of Procurement PSL. Buyer shares the responsibilities for the
following categories of equipment and materials;
1) Upon placing the Purchase Order, Expediter will be responsible for the expediting of
Vendor’s manufacturing, delivery of equipment and spare parts including Vendor
documents by the various expediting methods.
They will also implement the role of coordinator between field Expediter and Project
team under the control of Procurement PSL.
2) Field Expediter will carry out the expediting works in the area of his own responsibility
after placing the Purchase Order. He will also report the progress status for the
respective items to Procurement PSL.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 7 Of 25
1) Inspection Coordinator will assign the Inspector, who has sufficient experience and
capability.
2) Every inspection will be concentrated on confirmation and/or accomplishment of the
following;
- Vendor has a clear understanding of all required specifications, codes and
standards, and is familiar with specific inspection requirements.
- Vendor has prepared and received an Approval of fabrication drawing,
procedure/plans, required by Purchaser’s requisition prior to commencement of
fabrication.
- Vendor is fully aware of fabrication and/or assembly which will be subject to
inspection of CONTRACTOR’s and/or OWNER’s Inspector.
- Identification of “hold point” that requires the verification by Inspector.
- Vendor is responsible for conducting tests, honoring hold points, and providing
support to CONTRACTOR’s and/or OWNER’s Inspector.
1.4.5 Inspector
Inspector’s main responsibilities are to ensure compliance with the Quality Assurance
System and shall include:
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 8 Of 25
2. PURCHASING
The procurement will be implemented in accordance with the procedures and guidelines
defined in contract documents.
During the project execution, additional Vendors will be required for existing or new
commodities due to technical, schedule or commercial reasons. For these additional
Vendors, CONTRACTOR shall obtain the written approval of OWNER before the
placement of a Purchase Order.
2.3 Inquiry
1) Buyer will select Bidders from Approved Vendor List and new additional Bidders and
prepare Bidder list to be invited for OWNER’s review and approval.
2) Detailed procedure is as below:
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 9 Of 25
- CONTRACTOR shall prepare Bidder list to be invited for each Material Requisition
as per attached form.
- CONTRACTOR shall inform OWNER of Bidder list and issue inquiry package to
selected Bidders.
- CONTRACTOR shall submit to OWNER additional proposed Bidders’ pre-
qualification material, reference list and annual report for OWNER’s parallel
approval.
1) Buyer will issue the inquiry only to Approved Bidders for each item upon receipt of
OWNER’s approval on Bidder list.
2) Buyer will also instruct the Bidder:
2.4 Bids
2.4.1 Submission of Bids
Buyer will expedite submission of bids and let Bidder follow The Bids Submission Channels.
Buyer will clarify commercial matters of quotations and if there are some matters to be
clarified with Bidder, the commercial clarification record shall be issued to Bidder through
letter prepared by buyer.
After receipt of Bidder’s un-priced commercial quotation including full technical quotation by
buyer, it will be forwarded to the lead engineer of respective engineering discipline and
other engineering support discipline with a request for the technical analysis and
commercial analysis.
Bidder will submit the sealed priced commercial quotation including full technical quotation
as per the Bids Submission Channels as stated above.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 10 Of 25
Lead engineer of respective engineering discipline will prepare the technical bid analysis
sheet based on the result of clarification with each Bidder and it shall be issued to OWNErR
for approval.
Based on technical bid evaluation submitted by CONTRACTOR and after full finalization of
all technical issues and approval by OWNER, CONTRACTOR will open commercial bids.
Based on technical and commercial bid analysis CONTRACTOR will negotiate with Vendor.
2.9 Purchase Order
Upon Vendor approval by OWNER, Buyer will prepare the individual Purchase Order for
the selected Vendor and issue to Vendor.
2.9.2 Purchase Order will contain the following, but not limited to:
- Letter of Intent (LOI) details, if issued for earlier commitment of the order or
advance proceeding of any works agreed.
- Agreed delivery date for each item
- Date of order
- List of all commercial and technical documents with revision number
- Item, quantity, unit price, total price, and delivery terms
- Currency of payment
- Payment terms
- Liquidated damages and/or bonus clause (if applicable)
- Location where goods are to be delivered
- Guarantee
- Test and Inspection
- Documentation and Drawing
- Performance bond / Guarantee bond / Advance payment bond / Progress payment
bond (If applicable)
- Packing & marking specifications
- Shipping instructions
- Required commissioning and operation spare parts lists (if applicable)
- Storage recommendations (if applicable)
- Required operation and maintenance instructions (if applicable)
3607/32-PRC-9503
CONT. NO. : REF. NO.
DOCUMENT CODE
GN PRC 0001 11 Of 25
C- Gas Compressor
C-
E-
E-
H-
V-
V-
V-
E-
E-
E-
P-
CONTRACTOR provides expediting activities for each Purchase Order in order to meet the
contractual delivery date.
Three types of method will be used for expediting equipment and materials: desk
expediting, shop visit and meeting. Expediter can use all of these expediting methods from
the beginning of fabrication to completion of delivery.
Desk Expediting
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 12 Of 25
The purpose of shop visit is to survey the actual progress of the production at Vendor’s
shop or office and to check the actual production consistent with Vendor’s overall
production schedule. Shop visit will be the most effective method of expediting because
Expediter can check the physical production progress.
In addition, if any delay in production is found, Expediter can immediately request Vendor
to take corrective action(s) to remedy or minimize delivery impacts / delays.
Number and type of interventions may be subject to variations considering the status and
criticality of equipment and materials.
4.2.4 Meeting
In case any problem arises in course of works, Expediter will hold a meeting with
concerned personnel of CONTRACTOR and Vendor at convenient place to solve the
problem.
During the meeting, Expediter will report the results of the meeting in writing and distribute
copies to Procurement Manager, Vendor and OWNER.
Expediting reports shall be produced after each shop visit. Such reports shall be forwarded
to OWNER after receipt of report from Expediter.
4.3.1 General
1) Expediter will make every effort to detect and address any potential problem at the early
stage in order to prevent any delays in delivery as soon as the Purchase Order was
committed or placed to Vendor.
2) Expediter will:
DOCUMENT CODE
GN PRC 0001 13 Of 25
2) Expediter will confirm the following major items with Vendor prior to determining the
most feasible corrective actions:
3) To implement smooth test and inspection, Inspection Coordinator and Expediter shall
correspond with Inspectors, Vendor and OWNER.
Vendor will submit the written application for inspection to Expediter.
Expediter’s scope of work may deeply depend on the delivery terms of the Purchase Order.
For an effective shipping arrangement, expediting activities must be done in close
coordination with Logistics Coordinator.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 14 Of 25
4.4.1 Vendor Print Controller in CONTRACTOR’s project management team maintains Vendor’s
drawing/data and is responsible for listing and distributing all documents for comment and
for approval. Upon receipt of approved or amended Vendor drawing from engineering
division reflecting OWNER’s comments, if any, any modification and comments are
passed to Vendor for proper action.
4.4.2 Vendor Print Controller liaisons with expediting section in matters of Vendor expediting to
ensure receipt of all necessary contract documentation.
Vendor drawings/documents handling with CONTRACTOR & OWNER
Involvement/inputs is shown in the related flow chart.
4.5 Report
4.5.1 Expeditor’s report is made for each visit and sent to home office as soon as possible. They
are checked, logged and taken with the necessary actions, followed by distribution to the
requiring engineer and other nominated recipients.
Should a major problem be indicated, this is reported immediately by telephone, email or
tele-fax with recommendations for corrective action.
4.5.2 Expediting report is screened by home office for possible follow-up such items as
submitting status of Vendor drawings for CONTRACTOR’s review, data of drawings
4.5.3 In accordance with the requirement of the Purchase Order, Vendor submits a Progress
Report to CONTRACTOR periodically and Expeditor will check the progress and expedite,
if necessary.
Inspection, test and examination shall be implemented to assure that equipment and
material conform to the contract, project requirements, specifications and applicable codes
and standards.
Inspector's responsibility is to check and verify that equipment and materials conform to
the approved Vendor Quality Plans, specifications and order. A timely inspection and
quality tracking activity shall be made to prevent any abnormal conditions that may occur
during welding or fabrication process which will adversely affect the required quality and
level of specification. He shall also check good workmanship throughout the
manufacturing period in accordance with all technical requirements.
However, he shall avoid making unreasonable demands to Vendor for efforts beyond
those requirements to meet the Purchase Order, specifications and codes.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 15 Of 25
The acceptance criteria for inspection activities shall be defined by the following
documents in order of preference (e.g. Purchase Order requirements may over-rule the
requirements of a general specification). Any conflict in the documents shall be brought to
the attention of Procurement Manager for resolution with lead engineer.
- Purchase Orders
- Equipment specifications and drawings
- General project specifications
- Approved Vendor drawings & Vendor Quality Plan
4.9.1 In addition to CONTRACTOR’s own inspection, OWNER may independently arrange their
own inspection of any equipment or materials at Vendors or Sub-Vendors works.
4.9.2 In case that third party inspector is nominated on behalf of OWNER, OWNER will notify
the details of such third party inspection assignments to CONTRACTOR.
4.9.3 OWNER’s representative and/or its nominated third party inspector shall have the right at all
times in coordination with CONTRACTOR to inspect or witness the testing of the
equipment and materials at the place of production or fabrication.
4.9.4 CONTRACTOR will provide notice for inspection to OWNER in writing or through letter, fax
or e-mail so as to reach OWNER at least 10 working days in advance in case of overseas
inspection.
4.9.5 If no representative of OWNER appears at the time and place notified, the inspection or test
may be carried out as planned by CONTRACTOR. Work on “Hold Points” marked shall
proceed only in receipt of a written clearance.
4.10.1 Purpose
The purpose of pre-inspection meeting is primarily to ensure that the quality requirements
of the Purchase Order are being handled satisfactorily and that all requirements in the
Purchase Order and the applicable specifications, standards, and drawings are fully
understood by all concerned.
Pre-inspection meeting is normally held at the manufacturer's premises with
CONTRACTOR's Inspection Coordinator and/or Inspector, Vendor and OWNER (when
necessary) as per the requirements finalized in the Project Pre-Inspection Meeting.
Inspection Coordinator will decide the necessity and schedule of the meeting with
OWNER.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 16 Of 25
2) Vendor's quality control and inspection organization shall be checked and reviewed
for its ability to retain the required quality of workmanship.
4) Other matters
Coordination procedures, such as communication channels between the parties
concerned and submissions, records, etc., should be clearly understood by Vendors
at this meeting.
4.11.1 Before starting production, CONTRACTOR’s inspector shall check that all measures will be
taken to meet the inspection and testing requirements and approval of the following
documents relating to inspection has been obtained.
- Fabrication drawings
- Vendor’s Quality Plan
- Welding procedures / Welder’s qualification records
- Non-destructive examination procedures
- Heat treatment procedures
- All forming operations whether hot or cold on materials other that plain carbon steel
- Any fabrication procedure required by the Purchase Order
4.11.2 Inspection
Upon receipt of Vendor’s inspection notice, Inspector shall perform the inspection as per
The approved Vendor’s quality plan under the instruction of Inspection Coordinator.
Equipment or materials satisfying the following acceptance criteria will be released for
further processing or delivery from the Vendor's shop.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 17 Of 25
4.12.1 General
CONTRACTOR, upon receipt of such Invoices, shall audit and verify them taking into
account the conditions stated in the relevant Purchase Order and its amendments.
In case of inconsistency between the Invoices and the Purchase Order’s conditions shall
resolve all queries with Vendor until the Invoices are completely in line with agreed terms
and conditions,
Vendor’s Invoices (Billing Invoices) shall be made on Vendor’s own form and shall
contain the following information.
- Name and complete address of Vendor
- P.O Number and P.O. Description
- Vendor reference number
- Invoice Number
- Bank name, address and account number for payment
- Country of origin
- Item numbers, quantity of each item and description of materials exactly as appearing
on the P.O.
- Unit prices and total price of the Invoice
- Payment terms of the Invoice
All other applicable supporting documents to the billing Invoices which shall include
applicable documents of the following:
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 18 Of 25
Upon receipt of the billing Invoice and supporting documents from Vendor, CONTRACTOR
shall:
- Immediately verify the Invoices to the effect that each invoice is made in accordance
with terms and conditions specified in Purchase Order, agreements, exemption list and
related procedures.
- In case of errors or inconsistency between the invoices and the relevant documents as
noted above, then CONTRACTOR will ask Vendor to provide corrected invoice. In
such case payment due date will be modified with respect to the date of receipt of
corrected invoice.
4.12.4 Payment
- Upon receipt of invoices, CONTRACTOR shall make the payment to Vendors directly
to their designated bank accounts according to the agreed terms and conditions of
payment.
- In case of down payment, the amount of invoice shall be reduced with the amount
corresponding to the amortization of down payment.
For the control of materials and document, CONTRACTOR will utilize its computerized
control system.
6.1 Introduction
This plan describes about the shipping arrangement, transportation, customs clearance and
documentation for all offshore materials and equipment as followings, but not limited to;
3607/32-PRC-9503
CONT. NO. : REF. NO.
DOCUMENT CODE
GN PRC 0001 19 Of 25
- All offshore materials and equipment shall be packed securely. The nature of the
product, conditions at sea ports of exit and entry and transit to and from the inland
points determine the type of packing needed.
- Other factors are the hazards of loading and unloading, stevedoring handling,
warehousing and shipment. Protection from damage due to salt water, condensation,
rain, snow, heat or contamination during transportation shall be considered.
- Proper shipping marks in accordance with project requirements will be clearly marked
on the surface of each package, in order to easily recognize and identify the project
cargoes during transportation.
- Preliminary packing list will be received from Vendor in order to book the space of
vessel at least two weeks before actually cargo readiness for shipment.
- Forwarder, under CONTRACTOR’s control and direction, will book the space of the
vessel and conduct overall shipping arrangement for project cargoes from the place of
cargoes receipt in Vendor’s countries up to ports of entry in IRAN, and give a detail
schedule to CONTRACTOR.
- Documents for shipping and customs clearance shall be provided and/or collected by
Logistics Coordinator. The basic documents are Bills of Lading, Commercial Invoice,
Packing List and Certificate of Origin.
- Logistics Coordinator in head office shall distribute those original documents to the
relevant parties, i.e., Site Management or Local Forwarder in IRAN.
- The shipping notice containing details about the consignment including copies of
shipping documents shall be given to relevant parties, i.e., CONTRACTOR’s Site
Management, Local Forwarder and OWNER, if required, by fax or e-mail upon
each shipment effected, at least one week before ship’s arrival in IRAN, in case of
transportation by sea.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 20 Of 25
- In accordance with customs law, CONTRACTOR will carry out customs clearance
works.
- CONTRACTOR will conduct all necessary work after ship’s arrival, such as safe
handling of Goods at ports of entry, Delivery Order collection from the carrier’s
agent, providing customs declaration form and payment to relevant parties at ports of
entry on behalf of CONTRACTOR in advance.
- CONTRACTOR, after completion of customs clearance, shall carry out transfer of all
Goods from customs area at ports of entry up to project Job Site, giving information to
CONTRACTOR about delivered Goods.
- CONTRACTOR shall plan the complete route from the ports of entry up to project job
Site. These activities should require permission from various authorities and third
parties for removal and replacement of some street/road obstacles and/or other
possible obstacles along the authorized route.
3607/32-PRC-9503
CONT. NO. : 1032/GC-GN/CON-EP09-00 REF. NO. : 3607/34-78-MRP
DOCUMENT CODE
GN PRC 0001 21 Of 25
They should be provided as part of the initial orders for machinery and equipment based
on Vendor’s recommendation subject to OWNER’s approval.
They are required by CONTRACTOR in the performance of the work to achieve plant
completion and commissioning activities.
They are items required to maintain equipment in satisfactory working order, after
commissioning, to assure two(2) years of continuous operation of the plant.
7.2.1 Review equipment inquiries for complete coverage of spare parts, to ensure adequate
7.2.2 Expedite Vendors for early receipt of recommended spare parts lists including break down
prices and delivery times.
7.2.3 Promptly provide spare parts recommendations to OWNER for its review.
7.2.4 Maintain a control log of the status of the spare parts procurement work.
7.2.5 Expedite and receive ordered mandatory and other spare parts.
7.2.6 Maintain the same standards of quality control for spare parts as for other materials and
equipment ordered for the project.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 22 Of 25
7.3.1 Spare parts quotations should be obtained as soon as possible to permit early order
placement. Mandatory spares shall be developed with and ordered when the original
equipment purchases are committed. Minimum spare parts requirements and all
supplemental spare parts recommendations shall be developed and submitted for
OWNER review.
7.3.2 Original equipment item and description of that item for which part is recommended;
7.3.4 Reference assembly drawing or complete parts list for each piece of equipment;
7.3.6 Delivery date; CONTRACTOR desires delivery concurrent with the original equipment
order. In any event, the target scheduled delivery date shall be no later than six weeks
before Completion of the affected part of Plant.
CONTRACTOR shall establish total recommendation for identical parts through Vendor
Material controller, when the Goods arrive at project job Site, shall check the quantity,
according to the transport document and verify the good order and conditions of the
packing and/or the equipment which are not protected by package, due to transport
requirements.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 23 Of 25
8.2 Matrial controller, in case of receipt of Goods without any note regarding their conditions
and quantity, shall indicate on the transport document the following remark:
"Packages received in apparent good order and conditions except for the inspection of the
contents".
For the Goods not protected by package the remark will be:
"Goods received in external good order and conditions".
8.3 Material controller, in the event of loss or damage, shall detail on transport document the
relevant remarks, explaining the actual conditions of the Goods received.
8.4 Material controller shall give notice of loss or damage notice immediately to local agent of
Insurance company, carrier and/or Local Forwarder (copy to CONTRACTOR) and obtain
an acknowledgment of receipt.
8.5 According to the common rules, the following documentation, where applicable, shall be
sent by the Site Management to CONTRACTOR, for the adjustment of claims:
9.1.1 Material controller shall make OSI&D report immediately with evidencing documents upon
discovery of any defects after inspection of delivered materials and report to Coordinator
concerned (Buyer, Inspection Coordinator and/or Logistics Coordinator).
9.1.2 Material controller shall find out correct defective contents, quantity and degree of the
defect and, if necessary, arrange to conduct a joint survey in the presence of the
concerned companies (Vendor, Ship Company and/or Underwriter).
9.1.3 The Logistics Coordinator shall send OSI&D statement describing CONTRACTOR’s claim
intention to the party who is responsible for the defect when it is necessary to file claim in
consideration of the extent and quantity of damage and shortage.
9.1.4 The defect notice of the above article shall be made at once after discovery of OSI&D state
and it will be an important evidence for some dispute which may arise hereafter.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 24 Of 25
9.2.1 The Logistics Coordinator may, if necessary, request to the marine surveyor and measurer
corporation authorized under harbour transportation business law and recognized as an
agency having a good and worldwide qualification and ability to survey the imported
materials.
9.2.2 The Logistics Coordinator will arrange if requested by insurance company, the materials to
be inspected by a marine surveyor who is designated by the insurance company.
9.2.3 The Logistics Coordinator will check up the survey report submitted by marine surveyor’s
company to confirm whether it is accorded with the purpose of survey and the facts of
defect.
9.3.1 Survey and inspection for damaged and shorted materials shall be completed at earliest
time possible and the Logistics Coordinator also files claim with evidencing documents to
the party who is responsible for the defect or the insurance company.
9.3.2 The claim shall be made to the responsible party after obtaining proper documents in
accordance with OSI&D report specifying item, quantity and cause of damage and
shortage.
9.3.4 The Logistics Coordinator will make and keep claim index listing all descriptions for claim
and settlement of it.
3607/32-PRC-9503
CONT. NO. : REF. NO. :
DOCUMENT CODE
GN PRC 0001 25 Of 25
10. Attachments
Attachment 1 Procurement Team Organization
Attachment 2 Procurement Work Flow Diagram
Attachment 3 Bidder List to be invited (Format)
Attachment 4 Purchase Recommendation Sheet (Format)
Attachment 5 Procurement Status Report
Attachment 6 Expediting Follow-up Plan and Time Table (Sample)
Attachment 7 Spare Parts List and Interchangeability Record
Attachment 8 Inspection Activities Flow Digram
3607/32-PRC-9503
Attachment 1
Procurement Manager/
PSL
Mr.
Tel:88804770-7
Fax:88804778
YES NO
EMPLOYER HAS RIGHT TO
CHANGE THE VENDORS
CHOSEN BY CONTRACTOR
INQUIRY ISSUE
TECHNICAL CLARIFICATION
MEETING WITH VENDOR
TBA REPORT
( ) WORKING DAYS
NOTIFICATION OF NOTIFICATION OF PRIOR TO COMMERCIAL
COMMERCIAL NEGOTIATION COMMERCIAL NEGOTIATION MEETING
MEETING NEGOTIATION MEETING
WITH VENDOR
COMMERCIAL
CLARIFICATION MEETING
INQUIRY No. :
DESCRIPTION:
CLOSING
DATE: CLOSING TIME:
3.
OWNER DATE
2.
CONTRACTOR PROC. MANAGER DATE
1.
BUYER DATE
AVL ADDITIONAL
1BHF
PG
Attachment 4
PO DETAILS
TECHNICAL RECOMMENDATION COMMERCIAL RECOMMENDATION OWNER SELECTED OPTION
ACTION
SUMMARY SUMMARY
BIDDER NAME
ISSUE DATE PO AMOUNT DELIVERY
/COUNTRY
Attachment 5
JOB TITLE JOB NO. :
CLIENT DOC. NO. : '.
Issue Date:
Total Inquiry Issued Bids Received TBE Issued LOI Issued Pos Issued Inspection ETD ETA
S. No
Code
Category Remarks
Reqs. Nos. % Nos. % Nos. % Nos. % Nos. % Nos. % Nos. % Nos. %
Plan
1 SM Static Equipment
Actual
Rotating Plan
2 MR
Equipment Actual
Plan
3 PK Packages
Actual
Plan
4 SS Steel Structural
Actual
Plan
5 PP Piping
Actual
Plan
6 EL Electrical
Actual
Plan
7 IC Instrumentation
Actual
Plan
8 ZM Others
Actual
Total Plan -
Actual -
NOTES:
Attachment 6
AS OF
2007 2008 2009
VENDOR MANUFACTURER DELIVERY
PO No ITEM PO DELIVERY CRITICALITY REMARK
/ COUNTRY / COUNTRY CONDITION
JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
pair, set)
Required on site date : Approved for purchase by: Date :
Quantity to be supplied
s model
Commissioning spares
Classification of parts
2
Item No.
MANUFACTURERS DATA Remarks (see note 3
Recommended by
Recommended by
MESC. No.
manufacturer
above)
Contractor
Reference/Serial
4 above)
Origin
DESCRIPTION OF PARTS: to include all parts recommended to be kept for Manufacturers Real part No. (see note
Size
No.
5
order No.
PLANT : Date
6 CONSIGNEE : Sign.
Requisition No.
Attachment 8
PROJECT INSPECTION
LEVEL
↓
PREPARATION OF INSPECTION & TEST PLAN
↓
RECEIPT OF
PURCHASE ORDER
↓
INSPECTION ORDER
ASSIGNMENT
↓
REVIEW OF
PURCHASE ORDER
↓
REVIEW OF VENDOR PROJECT
PRINT
APPLICATION FOR
INSPECTION ↓
PROCUREMENT
VENDOR
DEPARTMENT
↓
INSPECTION OF
OWNER / TP
RAW MATERIALS
(WHEN REQUIRED)
(WHEN REQUIRED)
↓ ↑
PRE-INSPECTION MEETING
INSPECITON PROJECT
(WHEN REQUIRED) REPORT
↓
IN-PROCESS INSPECTION
↓
COMPLETION OF
FABRICATION
↓
ATTENDANCE BY
FINAL INSPECTION OWNER / TP
(WHEN REQUIRED)
↓
DELIVERY TO SITE