This document contains PERT data for a project with activities A through M and their durations, standard deviations, and variances. The critical path for the project has a total expected duration of 28 days with a standard deviation of 3.0372 days.
This document contains PERT data for a project with activities A through M and their durations, standard deviations, and variances. The critical path for the project has a total expected duration of 28 days with a standard deviation of 3.0372 days.
This document contains PERT data for a project with activities A through M and their durations, standard deviations, and variances. The critical path for the project has a total expected duration of 28 days with a standard deviation of 3.0372 days.
A 0 0 0 B 4 0.67 0.45 D 6 0.33 0.11 G 2 0.33 0.11 I 9 2 4 K 3 1.33 1.77 L 4 1.67 2.79 M 0 0 0 TOTAL: 28 9.2245 Critical Path Info: Duration= 28 days (Mean) σT e = 3.0372