Project Objective
The objective of this project is to build a residential building with an area of 150 sq. m. in a
period of 8 months. The said project will serve as a single family house which will cost an amount of 8
Million Pesos.
Deliverables
1. A 150 sq. m. 3 storeys finished home, with 3 bedrooms and 2 bathrooms and 1 comfort
room.
2. Exterior finish in accordance with environmentally preferable and high standard products.
3. Security independence systems, including fire alarm and surveillance cameras attached to
the gate, front and rear part of the house.
4. A 1-car garage, with a built-in connection for electrical vehicle recharging.
5. Highly rated-electric stainless and heat insulation kitchen appliances and materials, which
includes ovens, microwaves and dishwasher.
6. Interior design using wallpapers.
7. Equipped with split type and single type air conditioning unit for rooms and exhaust fan for
bathrooms.
8. The house shall also be installed with intelligent lighting system and ventilation.
9. A high speed internet provided by Globe.
Milestones
1. Bidding ……………………………………………………………………………………………….. February 8, 2019
2. Contract signed ………………………………………………………………………………….. February 14, 2019
3. Site Inspection …………………………………………………………………………………… February 20, 2019
4. Completion of Project Design ……………………………………………………………. March 14, 2019
5. 30% design review …………………………………………………………………………….. March 31, 2019
6. 60% design review ……………………………………………………………………………… April 15, 2019
7. 90% design review ……………………………………………………………………………… April 18, 2019
8. Design Complete ………………………………………………………………………………… April 26, 2019
9. Permits Completion ……………………………………………………………………………. April 28, 2019
10. Buying of Materials……………………………………………………………………………… April 29, 2019
11. Clearing Operation ………………………………………………………………………………. May 14, 2019
12. Completion of Excavation …………………………………………………………….……… May 31, 2019
13. Completion of Foundation……………………………………………………………………. July 24, 2019
14. Completion of Framing …………………………………………………….…………………. August 1, 2019
15. Completion of Roofing ……………………………………………….……………………….. August 16, 2019
16. Completion of Plumbing, electrical, and mechanical installation …….…. August 21, 2019
17. Passing of Plumbing, electrical and mechanical inspection ……………….…. September 5, 2019
18. Exterior Finished …………………………………………………………………………………. September 20, 2019
19. Interior Finished ………………………………………………………………………………….. September 20, 2019
20. Installation of appliances and systems ….……………………………………………. September 30, 2019
21. Final inspections and approval of the owner……………………………………….. October 5, 2019
Technical Requirements
1. The house must abide the National Building Code of the Philippines.
2. The structure must pass seismic stability codes.
3. The structure will be built with a minimum 2 x 6 inch sustainably source framing to allow for
increased insulation and structural stability.
4. The house will be supplied by electrical power by La Union Electric Cooperative Inc.
5. The design of the house must facilitate the use of natural lighting as much as possible, using
windows and doors.
6. Each room shall have 2 HP air conditioning unit, and bathroom with exhaust fan.
7. Surveillance cameras shall be installed in the gate, front and rear part of the house.
8. Garage shall accommodate one large vehicle.
9. Internet connection shall be provided by Globe Telco.
COMPLETION OF
SIGNING INTERIOR FINISHING
EXCAVATION
INSTALLATION OF
COMPLETION OF
SITE INSPECTION APPLIANCES AND
FOUNDATION
SYSTEMS
COMPLETION OF
ROOFING COMPLETION
PERMITS
COMPLETION OF
PLUMBING, ELECTRICAL,
BUYING OF MATERIALS
AND MECHANICAL
INSTALLATION
PASSING OF PLUMBING,
ELECTRICAL, AND
MECHANICAL
INSPECTION