DAILY CONSTRUCTION REPORT

Project : FL3B-BM RELATED


Date : Monday, 28 November 2022
Area : PB#5 (Night Shift)

Progress
Total
No Time Area / Activity UoM Excavation Cutting Pile Lean Concrete Install PHT Rebar Fabrication Installation Rebar Formwork Pouring Concrete
Volume
Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance Yesterday Today Cum Balance
1 19.00 - 06.00 Slurry Dewatering
· Excavation Pile Cap 261,67 m3 36,45 36 225
· Cutting Pile 146 Nos 42 42 104
· Lean Concrete 19,71 m3 2,43 3,24 5,67 14,04
· Install PHT 146 Nos 42 42 104
· Rebar Works (Fabrication / Install)
PHT 4012,08 Kg 1154,16 1154 2857,92 989,28 989,28 3022,8
Pilecap 73323,5 Kg 22312,57 22313 51010,9 22312,57 22312,57 51010,9
Tie Beam 7590 Kg 2760,36 2760 4829,64 2760,36 1380,19 4140,553 3449,45
Collumn 104562 Kg 15066,37 4999,86 20066 84496,1 13399,37 13399,37 91162,9
· Formwork (Fabrication/ Install)
Pilecap 310,98 m2 52,65 52,65 258,33
Tie Beam 54,12 m2 9,84 9,84 44,28
Collumn 912 m2
· Pouring Concrete
Pilecap 261,67 m3 48,6 48,6 213,07
Tie Beam 15,84 m3 2,112 2,112 13,728
Collumn 216,6 m3 216,6

Support Note:
Excavator : 0 Unit 1. Fabrication rebar PC7 (FWS) and rebar column C1 Slurry Building = 3 person
Dump Truck : 0 Unit 2. Install top rebar PC12 FWS = 7 person until 07.00 PM - 00.00 AM (Completed)
Man Power 3. Install Tie Beam Grid C2-C3 and A2-A3 Slurry Building 01.00 AM - 07.00 AM. (Completed 2 Nos)
· Fabrication : 3 MP 4. Fabrication bottom rebar PC7 FWS = 1120,56 Kg
· Installation : 6 MP 5. Fabrication column C1 slurry = 4999,864 Kg (3 Nos)
· Foreman : 1 MP 6. Night shift working until 06.00 AM

Weather Report : Time 19 20 21 22 23 24 1 2 3 4 5 6


Weather Good Good Good Good Good Good Good Good Good Good Good Good