Project objective: Develop the new website for the company, make it better than the old one and add on
sales online, recipes with the spices, and also they want to expand the sales overseas for countries like:
Hong Kong, Japan and Singapore.
Milestones
This section should reflect key dates for activities as specified in the Project Management Plan
Actually, in this case, our Planned Expenditure for this reporting period was 38,000 but we spend 39,000.
It means we spend 1,000 more than the planned expenditure.
The impact of it will be that for rest of the project we will get less amount. Now for the Remaining budget
for life of project, will be only 6,000.
Risk Management
Security/ Maintanance Moderate Example: Virus on Talk to the IT team and hire a
the website; others new software for safety.
from outside the
company could
reply the credit
card.
Skill Level Minor Need to spend Trainings for higher skill levels
extra money,
because the staff is
not capabl
Over Budget Moderate It could cancel the Cut costs of the project
project or have
extra problems on
the deadline
Recommendations
The team is ready to action, so we are going to send the e-mails for the designers and the
photographers to evaluate. The IT team is going to start the new system as well.