MILESTONE MATRIX: -UPPER KOLAB PUMPED STORAGE PROJECT, OHPC

S.N Achieveme
Activity Target Progress / Status
o. nt
State government approval for
1. Date of MOA/ MOU 18.03.2021 18.03.2021 Conceptual layout of the project
received on 18.03.2021.
Completed ToR received vide letter
2. Grant of ToR from MoEF Jan 2020 Feb 2020 dated 28.02.2020 (valid upto
27.02.2024)
3. Topographical Survey May 2020 July 2021 Completed
Expected by
4. Geological Mapping Studies June 2023
June 2023
Under Progress

5. Hydrological Studies March 2022 March 2022 Completed

6. Geophysical Survey Not suggested by appraisal agencies

Expected by
7. Data collection for 3 seasons Oct 2023
Oct 2023
One season studies completed & rest
two seasons studies under Progress.
Expected by
8. EIA/ EMP Studies June 2024 -Do-
June 2024
ToR received vide letter dated
Date of Submission of Proposal
9. Dec. 2019 Dec. 2019 28.02.2020 of MoEF & CC which is
for EIA/EMP
valid upto 27.02.2024.
Layout submitted to HCD(NWS) on
date after compliance of their views
10. Layout Finalization Sep 2023 Sep 2023
dated 13.04.2023 and is under review
in HCD, CWC.
1.Site Specific Seismic
Studies
N.A
11. Studies
Expected by Transient analysis carried out & will be
2. Transient Studies May 2023
May 2023 submitted .
Necessary documentation has been
Drilling/ Expected by carried out for seeking Forest
Dec. 2023
13. Borehol DR-1 to 15 Dec. 2023 Clearance from DFO for Drilling ( 15
es nos. Drill Holes) and is under Process.

DF-1
After carrying out Geological Mapping
15. Drifting Studies, proposal will be submitted to
GSI for their views/comments.
May 2023 Expected by Hydrology submitted to CWC on
Hydrology
1
(CWC) *
May 2023 18.3.2023 and is under review in
CWC.
August Expected by On getting approval of Hydrology
Power Potential
Clearan 2
Studies (CEA)
2023 August 2023 aspect from CWC, PPS studies will be
ces (As carried out.
16. applicab Dec. 2023 Expected by
le) Dec. 2023
Geological
3
(GSI)
Aspect Under Process
Foundation Oct. 2023 Expected by
Engg. And Oct. 2023 Based on site geotechnical
4 Seismic investigations, revised proposal will be
(FE&SA - submitted FE&SA Directorate., CWC.
CWC)
Layout submitted to HCD(NWS) on
HCD- July 2023 Expected by date after compliance of their views
CWC July 2023 dated 13.04.2023 and is under review
Gener in HCD, CWC.
al CMD
layout D/
5
&
July 2023 Expected by
Emb/ Under Process
Planni BCD- July 2023
ng CWC
HET Oct 2023 Expected by
D- Under Process
CEA Oct 2023
Construction Dec. 2023 Om finalization of Layout aspect by
material and Expected by
6
Geotechnical
CWC, proposal will be submitted to
Dec. 2023
(CSMRS) CSMRS .
Inter-State August Expected by Under preparation & Will be summited
7
(ISM – CWC) * 2023 August 2023 by 26.5.23
Transmission Dec 2023 Expected by
8 System Under Process
(PSP&A-CEA) Dec. 2023
March.
2024 Expected by
26. DPR Submission Date
March. 2024

Expected by
27. TEC / Concurrence Date July 2024 July. 2024
Dec 2024 Expected by
28. EC & FC
Dec. 2024
June. 2025
29. Start of Construction

Dec. 2029
30. Commissioning Date

I. Intervention Required: Requesting to all aspect directorates for giving their views/approvals at the earliest.