Professional Documents
Culture Documents
Method of Statements Electrical System
Method of Statements Electrical System
FOR
WIRES AND CABLES INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of Wires
and Cables for the project.
This document details Wires and Cables Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Excavation:
No wiring be carried out until the appropriate tests required or in the
electrical testing section have been done and the consultant has
given his clearance for wiring to commence.
A loop in form of wiring shall be used as far as practicable or unless
otherwise indicated. Joints in conductors shall be made using
insulated terminal blocks complying with requirements of this
specification.
At expansion joints adequate slack shall be left in the cable.
Where Conduits are installed for wiring by others, a draw wire shall
be provided between each draw in position.
Where three-phase circuits comprising single-core cables are
installed in trunking, all cables of a shall be tied together at intervals
not exceeding 200mm.
Cables forming part of alarm, control, communication or monitoring
circuits shall have identification sleeves at their terminations.
Identification shall be consistent with the relevant wiring diagrams.
Pulling:
Make sure that all conduits and boxes in both ends are free from
damages and blockages etc and installation is approved.
Blockage shall be checked by inserting the draw wire and checking
that it reaches to the other end without any disturbance.
Once the conduit is not blocked the wires shall be pulled using the
draw wires while ensuring no damage occurs while pulling.
Pulling compound or lubricant shall be used for pulling the wires
where required.
Use soap based pulling compound for short runs i.e. less than 20
meters for semi conductive insulated wires.
Use wax based pulling compound for the runs greater than 20
meters for semi conductive insulated wires.
While pulling the wires care should be taken to not insert the pull
tension greater than the manufacturer allowed limits.
Termination::
Erect scaffolding where required as per the site requirements.
Cable rollers shall be placed under the cable during pulling over
longer distances and standoff rollers for acute bends, to ensure that
the cable is pulled with minimum effort and the cable outer jacket is
free of scouring lines.
The cable shall be pulled by using pulling means such as fish tape,
rope and basket weave wire/cable grips so as not to damage cable
or its containment system. Care will be taken to ensure that the
maximum pulling tension of all the cables is not exceeded at any
time.
Cable should be free of any static load i.e. to be places side by side
parallel on the cable tray or ladders. Any kind of dead weight on the
cable shall be avoided.
The cables shall be secured to the containment system using
approved cable ties for horizontal runs and cable cleats for vertical
runs.
Termination shall be done by using the approved termination
materials that include glands, lugs and other accessories part of
termination kit, by using proper crimping tools. Matching colour
gland sheaths shall be provided.
Commissioning:
Set the Meggar meter to 1000 volts DC for cables and 500 volts DC
for wires.
Take reading between phase, phase and neutral, phase and earth
neutral and earth.
Note that resistance reading must not exceed 2 megaohms(MΩ).
Check and record the resistance readings as per specification on
the approved insulation resistance test forms.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Wires and Cables Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Wires and Cables Installation will
be as follows:
Measuring tape
Cutting plier
Bending spring
Pipe Wrench
Drilling Machine
Crimping tool
Screw driver
Pulling spring
Hammer
Common tools
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
UNINTERRUPTIBLE POWER SUPPLY INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Uninterruptible Power Supply for the project.
This document details Uninterruptible Power Supply Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Commissioning:
Check the power quality of UPS output.
Check whether the harmonics are within the limit
Check the transfer time.
Check the sine wave composition.
Check battery voltage and internal resistance of each cell, including
inter-cell and inter-tier connectors.
Check the temperature of battery.
Check the currents and discharge events.
Check the individual cell voltage.
Check to verify that the UPS systems are performing to manufacturer
specifications.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
2. To ensure that the progressing of works is carried out according
to the planned program and as per the approved method of
statement.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
1. Hand Tools
4. Diagonal-Cutting Pliers
6. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
5. Technician From Supplier
6. Store Keeper
METHOD STATEMENT
FOR
TRANSFORMER INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Transformer for the project.
This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Pre-Installation:
All materials and documentation relevant to this particular section of
works shall be checked by the Construction Department prior to the
commencement of works ensuring that these are correct and approved
type.
Before any permanent works will continue, pre-inspection on all
materials, tools and access for installation to be carried out.
Installation:
Before the transformer will be delivered to site, ensure that the
transformer railing is fixed as per approved drawings and comply on
municipality requirement.
Move the transformers from the designated off-loading area or storage
area using fork lift and set them in position near to the transformer
room.
Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
Push in the transformers inside the transformer room. Set the
transformer on their final positions and make sure that they are
properly secured and protected.
Raise Request for Inspection for Transformer Installation.
Conduct on site test for the transformer.
Test shall include winding insulation resistance test and shall conform
to manufacturer’s recommendation and specification.
All tests must be recorded and conducted in the presence of
Consultant by manufacturer testing engineer.
Dress and terminate the incoming and outgoing cables on the
transformers.
Ensure that the cables were supported properly.
Cable glands, lugs and termination kits shall be approved type.
After termination works has been completed, clean the transformer
cable box and ensure that it is free from foreign materials and excess
openings must be sealed off and ensure that all the connections are
properly tight and torque.
Raise Request for Inspection for the cable terminations and dressing.
Commissioning:
Cover the cable boxes.
Bolts and nuts must be tightened properly.
Make sure that the transformer room is clean and free from foreign
materials.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
TELEPHONE / DATA INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations
Telephone / Data System for the project.
This document details the Telephone / Data System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Installation of Wires:
Grounding:
Identification:
Programming:
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Telephone / Data System Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Telephone / Data System
Installation will be as follows:
Wire cutters
Hacksaw
Measuring tape
Drill machine
Wooden hammer
Flat file
Screw drivers
Base Cutter
12. SUPPORTING
tement should be read in conjunction with the below referenced
documentations:
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
STREET LIGHTING INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, Installations of Street
Lighting .
This document details Installation of Street Lighting :
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings, approved specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians.
8. MATERIALS REQUIREMENTS
Street Lighting Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Installation of Lighting Fixtures will
be as follows:
1. Screw drivers
2. Hacksaw
3. Needle nose pliers
4. Electrical drill and drill bits (only for surface installation works)
5. Diagonal-Cutting Pliers
6. Wire Stripper/Cutter with Spring
7. Side-Cutting Pliers
8. Level
9. Shank Screwdriver
10. Electrical tape
11. Voltage tester
12. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves
& safety vest )
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
POWER FACTOR CORRECTION CAPACITORS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of Power
Factor Correction Capacitors for the project.
This document details Power Factor Correction Capacitors Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Check the cable trenches and supports are painted and ready for
permanent installation of the said equipment.
Move the PFCC from the storage area to their designated Locations.
Fully crated panels shipped on a timber sub-base shall be lifted under
the sub-base.
When moving the fully crated PFCC from the storage area to their
Locations of installation using fork lifts, the mast must be as close as
possible to the face of the crate and forks must be fully projected under
the crate. Lift the fully crated PFCC squarely.
Uncrate, unpack and remove the PFCC from its timber base. Care
must be taken to protect the Feeder Pillars from unnecessary
scratches or bents on the panels.
Move in the PFCC using steel pipe rollers to its final location. Care
must be taken to ensure that the PFCC does not over balanced while
being moved to its final locations.
Align the PFCC horizontally and vertically.
Secure the PFCC assembly and ensure that it is fixed properly on its
base.
Remove all unused bolts, nuts, washers and clean the PFCC. Feeder
Pillars side covers and doors shall be put back.
Ensuring that it is properly tightened.
Conduct insulation resistance test on the PFCC to ensure that all joints
are properly insulated.
Raise Request for Inspection for switchgear installation.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
NURSE CALL SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of NCS
system for the project.
This document details the NCS system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Installation of Patient Bed Head, Patient Hand Set and Over door Lamp
units :
Exact location of the Patient Bed Head, Patient Hand Set and Over
door Lamps shall be as per approved NCS installation layout plan as
well and to be coordinated with Medical Equipment and Medical Gas
at site.
Select location in Bed Head Unit where the Socket and Patient Hand
set has to be mounted and install cables (data cable) according to
manufacturer instructions.
Select location in corridors ( in over door of Patient rooms) to prepare
mounting kit and install over door corridor lamp according to
manufacturer instructions.
Installation of Wires:
Grounding
Identification
Programming
After making sure all the system installed in correct way from
Subcontractor and supplier, programming of the system must
take place before final testing and commissioning accourding
to Consultant requirement and senario of the system.
Testing and commissioning of the system submitted separetly
for this system mentioned all the procedure of Testing of the
system and commissioning it.
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians.
8. MATERIALS REQUIREMENTS
NCS Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Nurse Call System Installation will
be as follows:
1. Hand Tools
3. Diagonal-Cutting Pliers
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
MV CABLE PULLING AND INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, Installations and
Pulling of MV Cable .
This document details Installation and Pulling of MV Cable :
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
The sizes and routes routing will be as per the approved Shop
Drawings.
Excavation:
1. Permit to Work (PTW) shall be raised for the excavation clearly
mentioning the location of work, size of excavation and levels.
2. Excavations area shall be surveyed and marked to the lines and levels
as shown on the drawings.
3. The area of excavation will be cordoned off using safety devices.
4. Ensure the working area at any confined space is free from any
Hazardous Gas by proper Gas testing using the Gas testing
instrument.
Materials:
1. Not necessary for the construction shall be removed carefully and
stored neatly for reinstating after the construction works.
2. The material received from the client shall be stored in designated area
of store.
3. Arrangements shall be made to protect against effects of weather and
environment.
Pulling:
1. Insulation resistance of the cables shall be checked before laying
cables.
2. After the test, the end of the cable shall be sealed to prevent the
ingress of moisture.
3. Location of the panels / equipment shall be identified.
4. Cables shall be lubricated if bends in conduits are encountered in a run
to facilitate drawing in.
5. Cables must not be bent to a radius of less than 12 times the overall
diameter of the cable.
6. Rollers must be used where cables are installed in an open trench
using a pulling rope and eye; cable rollers are to be used at frequent
intervals to support the cables and must never be more than 3 meters
apart.
7. The rollers are to be placed securely to prevent movement.
8. The pulling rope must be equipped with a swivel and be attached to the
cable by a stocking grip with pulling eye.
9. The cable drum intended for cable pulling shall be identified as per that
indicated in the drum schedule.
10. The cable drums shall be un-packed and placed on a cable roller, as
required.
11. Cable laying will generally start from one end of the route length or at
any suitable point, as necessary.
12. Depending on the weight and size of the drum, suitable size of the
cable rolling shaft (Spindle) shall be placed inside the central axis of
the drum.
13. Suitable jacks shall be placed firmly on the ground and jackedup to
allow clearance from the ground depending on the size of the cable
drum.
14. The drum shall be lifted by required equipment and placed on the
jacks.
15. The cable drum will be correctly positioned and the direction of cable
pulling as indicated by arrow on the drum shall be complied.
16. The cable shall be drawn into the trench smoothly with a minimum of
stops and at an average speed of between 9-12 meters per minute, to
avoid irregular movement.
Termination:
1. Termination point inside the panels / equipment shall be considered for
suitable spare length to be left available during pulling of cable
termination.
2. After cutting the cable to the required length the termination work will
be conducted as per ADDC Standard.
3. Jointing and Termination will be carried out as per ADDC standards. All
jointing and termination work will be carried out by trained technicians,
experienced in such work for the operating voltage concerned.
4. Proper crimping tools shall be used compression type lugs. All cables
are to be terminated used glands of proper type and size as per area
classification.
5. The gland shall be assembled strictly in accordance with
manufacturer’s instruction, particular attention being paid to ensure
good mechanical and electrical contact between part without excessive
strain or distortion of cable.
6. The entire body of the cable must enter the gland. The cable shall be
on a straight axis from a point at least six diameter before entering the
gland. Seals shall be checked for correct size at the point of
application.
7. Unused cable entries shall be closed with plug suitable for the degree
of protection classification.
8. After completion of indoor and outdoor termination the cable is ready
for Testing.
Commissioning:
1. The following calibrated testing instruments will be used:
1 KV / 5 KV IR Test Kit - 1 no.
Multi Meter - 1 no.
Continuity Tester - 1 no.
Continuity Tester - 1 no.
Torque wrench - 1 no.
VLF - Test Kit.
2. Before starting the test, the corresponding Circuit Breakers at
both ends of the cables are racked out and earthed properly.
3. Test will be conducted at the MV panel end. The opposite end of the
cable termination will be secured & protected. Testing engineer will be
at the end where high voltage is applied and another Engineer to
monitor at the opposite end of the cable.
4. Insulation Resistance will be done first: (a) between termination lugs;
(b) Phase, Neutral and Earth termination lug; (c) conductor to
termination lug. This will be done one minute each at 5kV, and the
results are noted as per approved test report format.
5. The continuity test and phase sequence tests would be carried out and
results would be recorded for records and future reference.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings, approved specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
MV Cable Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Installation and Pulling of MV
Cable will be as follows:
1. Cable Rollers
2. Cable Pulling Grip
3. Hand Cable cutter
4. Manual Cable Crimpers
5. Hacksaw blade
6. Power Tools
7. Tool Box
8. Measuring Tape
9. Ladders / Scaffoldings/Platform
10. Hand tools Hilti Drill Machine
11. Hilti Concrete Bit (6mm to 16 mm)
12. Anchor Bolt/Screw
13. Screw Driver
14. Adjustable Spanner
15. Hammer
16. Electrician’s Knife
17. Multi Meter
18. 1 KV / 5 KV IR Test Kit
19. Continuity Tester
20. Torque wrench
21. VLF – Test Kit
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
LV SWITCHGEAR AND MOTOR CONTROL CENTER INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations LV
Switchgear and Motor Control Center for the project.
This document details the LV Switchgear and Motor Control Center
Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
LV Switchgear and Motor Control Center Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for LV Switchgear and Motor Control
Center Installation will be as follows:
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
8. Crimping tool
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
LIGHTNING PROTECTION SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations for
Lightning Protection System for the project.
This document details the Lightning Protection System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Site survey of the proposed Lightning Protection System based on
approved CSD by foreman/sub-contractor together with Engineer.
Installation must be carried out based on approved shop drawings
& samples by foreman/ sub-contractor.
Method and material used for the installation of Lightning protection
system shall comply BS6651. (Protection of structure against
lightning).
The earth electrode pits location shall be marked out on site before
commencement of hammering in electrodes. The earth pits shall be
near the location of the down conductors.
Those earth pits located in the basement shall be provided with
seals to prevent penetration of the ground slab.
Electrodes are hammered into the ground and reading is taken to
ensure that the resistance is less than 10 ohms per electrode.
Lightning Protection System accessories.
Earth termination network: The means of dissipating the current to
the general mass of earth. Choose an earth electrode to suit the
ground conditions in the locality of the structure. Electrodes are
available in the form of rods and plates (lattice or solid)
Earth rod clamps: Select a high copper content alloy earth rod
clamp for the connection of the earthing conductor to the earth rod.
In this below ground application, the clamp must ensure a good
electrical contact and resist corrosion throughout the lifetime of the
installation.
Earth inspection chambers: Select an earth inspection chamber to
protect the earth electrode connections.
Bonding: Bonding is the most commonly employed method of
avoiding the damaging effects of side flashing. All continuous
metalwork should be considered for bonding. All metallic services,
eg cable armouring, gas, water or steam piping, entering the
building should also be bonded as directly as possible to the earth
termination network.
Select the correct type of metalwork bond for the application, ie a
flat column face, a circular rainwater pipe or a ribbed reinforcing
bar.
Depending on the specification, the down conductor tapes can be
thermal weld to the rebar and casted in the column or run in a
continuous strip on the surface of the external wall.
For casting of column, floor, continuous supervision is necessary to
ensure that the tape is extended before the main builder close up
form work before casting. Approved clamps to be used for
extension tape.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Lightning Protection System Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Lightning Protection works will be
as follows:
1. Center punch
2. Brace
3. Hammer
5. Diagonal-Cutting Pliers
8. Level
9. Shank Screwdriver
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
LIGHTING FIXTURES INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, Installations of
Lighting Fixtures.
This document details Installation and Pulling of Lighting Fixtures :
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
The sizes and routes routing will be as per the approved Shop
Drawings.
Preparation:
1. Engineer in-charge shall check to ensure that the Light Fixtures
manufacturing, complies with specification and drawings.
2. Engineer shall check to ensure that when installing Light Fixture in
Hotel Guest Room, Corridor, Foyer, Front of House (FOH) and Back of
House (BOH), architectural finishing work is completed.
3. Ensure there is any physical obstruction during the delivery light
fixtures.
4. Ensure that the Light fixture design/equipment provided all are fully
comply with the specification.
5. Supplier shall deliver light fixtures unit to site and store it designated
place.
6. Handle the light fixture unit with care to avoid damage to components,
frame and finish.
7. When the light fixtures unit is received, unpack it sufficiently to inspect
it for concealed damage to determine that the shipment is complete
and correct.
8. If the light fixtures are to be stored prior to installation, replace the
packing for protection during that period. When conditions permit, leave
the packing intact until light fixtures unit are at their final installation
location.
9. Protect the fixtures against the dust and debris during construction
period.
10. A trolley or pallet may offer a more convenient method of handling the
light fixtures to shift from one location to other.
Installation:
1. Site survey of the proposed light fixture is based on approved shop
drawing by foreman / sub-contractor together with Engineer.
2. Installation must be carried out based on approved shop drawings &
samples by foreman / sub-contractor.
3. Most wall and ceiling fixtures–other than recessed fixtures–fit into
standard electrical outlet boxes and are usually easy to mount.
4. Most fixtures are mounted by a fixture stud or a fixture strap.
Occasionally you need an extension nipple or a plain nipple for
mounting certain fixtures.
5. Any additional mounting devices required for special types of fixtures
are usually included in the materials furnished by the manufacturer.
6. Read and follow the manufacturer's instructions carefully for a neat
installation.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings, approved specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians.
8. MATERIALS REQUIREMENTS
Lighting Fixtures Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Installation of Lighting Fixtures will
be as follows:
1. Screw drivers
2. Hacksaw
3. Needle nose pliers
4. Electrical drill and drill bits (only for surface installation works)
5. Diagonal-Cutting Pliers
6. Wire Stripper/Cutter with Spring
7. Side-Cutting Pliers
8. Level
9. Shank Screwdriver
10. Electrical tape
11. Voltage tester
12. P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves
& safety vest )
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
LIGHTING CONTROL PANELS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Lighting Control Panels for the project.
This document details Lighting Control Panels Installation :
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Lighting Control Panels Installation
will be as follows:
1. Hand Tools.
3. Diagonal-Cutting Pliers.
5. Side-Cutting Pliers.
8. Measuring Tape.
9. Multi Meter.
10. Necessary conduit for System Cabling.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
HANGERS AND ANCHORS AND SUPPORTS OF SERVICES
INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations Hangers
and Anchors and Supports of Services for the project.
This document details Hangers and Anchors and Supports of Services
Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
After examine conditions at the job site where work shall be performed
to insure proper arrangement and fit of the work, we will coordinate the
drawings and specifications in order to insure the completeness of the
work required. Verify measurements and dimensions at the job site and
cooperate in the coordination and scheduling of the work.
Proceed with installation of hangers, supports and anchors only after
required building structural work has been completed in areas where
the work is to be installed. Correct inadequacies including (but not
limited to) proper placement of inserts, anchors and other building
structural attachments.
We will install hangers, supports, clamps and attachments to support
piping properly from building structure, directly mounted with the
Hollow core slab by using the M10 Unfix and the threaded rod M10 will
be installed directly inside the unfix and we will arrange for grouping of
parallel runs of horizontal piping to support together. Where supporting
piping of various sizes together by trapeze hangers, space hangers for
smallest pipe size or install intermediate supports for smaller diameter
pipe.
Install hangers and supports complete with necessary inserts, bolts,
rods, nuts, washers and other accessories. Except as otherwise
indicated for exposed continuous pipe runs, install hangers and
supports of same type and style as installed for adjacent similar piping.
We will adjust hangers so as to distribute loads equally on attachments
and we will provide grout under supports so as to bring piping and
equipment to proper level and elevations.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Hangers and Anchors and Supports of Services Components and
Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Hangers and Anchors and
Supports of Services Installation will be as follows:
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
FIRE ALARM SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of Fire
Alarm system for the project.
This document details the Fire Alarm system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer recommendations
Approved shop drawings and project specifications.
Installation:
Verify that hardware and devices are NRTL listed for use with fire-
alarm system before making connections.
Make addressable connections with a supervised interface device to
the following devices and systems.
Install the interface device less than 3 feet (1 m) from the device
controller.
Make an addressable confirmation connection when such feedback is
available at the device or system being controlled as follows :
1. Alarm-initiating connection to smoke-control system (smoke
management) at fire-fighter smoke-control system panel.
2. Alarm-initiating connection to stairwell and elevator-shaft pressurization
systems.
3. Smoke dampers in air ducts of designated air-conditioning duct
systems.
4. Alarm-initiating connection to elevator recall system and components.
5. Alarm-initiating connection to activate emergency lighting control.
6. Alarm-initiating connection to activate emergency shutoffs for gas and
fuel supplies.
7. Supervisory connections at valve supervisory switches.
8. Supervisory connections at low-air-pressure switch of each dry-pipe
sprinkler system.
9. Supervisory connections at elevator shunt trip breaker.
10. Supervisory connections at fire-pump power failure including a dead-
phase or phase reversal condition.
11. Supervisory connections at fire-pump engine control panel.
Installation of Components:
Smoke-Detector OR Heat-Detector
Comply with NFPA 72, “Smoke-Sensing Fire Detectors” & “Heat-
Sensing Fire Detectors”.
Smooth ceiling spacing shall not exceed 30 feet (9 m).
Fire-Alarm Control Unit: Surface mounted, with tops of cabinets not
more than 72 inches (1830 mm) above the finished floor.
Annunciator: Install with top of panel not more than 72 inches (1830
mm) above the finished floor.
Installation of Wires:
Grounding:
Identification:
Programming
After making sure all the system installed in correct way from
Subcontractor and supplier, programming of the system must
take place before final testing and commissioning accourding
to Consultant requirement and senario of the system.
Testing and commissioning of the system submitted separetly
for this system mentioned all the procedure of Testing of the
system and commissioning it.
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
FAS Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Fire Alarm System Installation will
be as follows:
1. Power source
2. Drilling machine
3. Tool Box
4. Measuring Tape
5. Calibrated Ohm Meter / Multi meter
6. Ladders / Scaffoldings
7. Hammer
8. Safety requirements tools such as safety shoes, safety helmet, safety
glasses, fluorescent vest, and safety gloves to ensure maximum ability
of safe work and dust mask when required.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
ELECTRICAL PVC CONDUITS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Electrical PVC Conduits for the project.
This document details Electrical PVC Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
During the course of the installation of the conduit system,
procedures for working and dressing the installation as
recommended shall be employed.
All bends and sets shall be in accordance with IEE regulation 522-
08 formed with the aid of a helical spring fitted internally, with if
necessary, the conduit warmed sufficiently for it to move without
avoidable wall thinning of the out side of the bend.
Commissioning:
When conduits are run on shuttering, prior to the laying of concrete
insitu, additional security must be provided near to every box and at
intervals of not more than 1.2 meters by binding short lengths of
steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed
to prevent excessive movement and damage during the pouring
and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is
poured. Unless otherwise indicated to cast in conduits shall not be
less than 30mm.cores to plastered over conduits shall not be less
than 5mm.
Where conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building
material.
Ensure conduits are not concealed until works has been inspected
and approved. Ensure that conduit and fittings buried in concrete or
behind plaster are protected against corrosion or electrolytic action
prior to rendering.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Electrical PVC Conduits Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Electrical PVC Conduits
Installation will be as follows:
1. Hack saw
2. Measuring tape
3. Cutting plier
4. Knipex (End cutter)
5. Bending spring
6. Drilling Machine
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
ELECTRICAL PANELBOARDS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Electrical PanelBoards for the project.
This document details the Electrical PanelBoards Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
8. Crimping tool
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
ELECTRICAL IDENTIFICATIONS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Electrical Identifications for the project.
This document details Electrical Identifications Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Install identification devices according to manufacturer's written
instructions.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/ charge hand are aware of
the job requirements and they have enough information to carry
out their duties properly.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Electrical Identifications Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Electrical Identifications
Installation will be as follows:
Wire cutters
Hacksaw
Measuring tape
Drill machine
Wooden hammer
Flat file
Screw drivers
Base Cutter
10. WASTE MANAGEMENT
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
ELECTRICAL GALVANIZED CONDUITS INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Electrical Galvanized Conduits for the project.
This document details Electrical Galvanized Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
No conduit smaller than 20mm in diameter or larger than 32mm
diameter shall be used.
Straight run - 10 m.
Conduits shall not be run closer than 0.15m to any steam or hot
water pipes and shall be run underneath such pipes rather than
over them. It should not also be run closer than 0.05m to any
telephone, bell or other signaling circuit.
Commissioning:
When conduits are run on shuttering, prior to the laying of concrete
insitu, additional security must be provided near to every box and at
intervals of not more than 1.2 meters by binding short lengths of
steel wire, of not less than 2mm diameter twisted around the
conduit and reinforcing steel. The conduits shall be adequately fixed
to prevent excessive movement and damage during the pouring
and setting of concrete and shall be protected from mechanical
damage. Check there is no damage before screed / concrete is
poured. Unless otherwise indicated to cast in conduits shall not be
less than 30mm.cores to plastered over conduits shall not be less
than 5mm.
Where conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building
material.
Ensure conduits are not concealed until works has been inspected
and approved. Ensure that conduit and fittings buried in concrete or
behind plaster are protected against corrosion or electrolytic action
prior to rendering.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Electrical Galvanized Conduits Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Electrical Galvanized Conduits
Installation will be as follows:
Painting Brush
Measuring tape
Cutting plier
Threading Machine
Box spanner set
Bending Machine
Pipe Wrench
Drilling Machine
Round files
Bench vise
Tripod stand wise
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
EARTHING SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Earthing System for the project.
This document details the Earthing System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Coordinate installation of earthing system system with installation of
other building systems and components, including electrical wiring,
supporting structures, metal bodies requiring bonding to earthing
system, and building finishes.
Install conductors with direct paths from ground pits to ground
connections.
When different metal to be connected, a bimetallic clamp shall be used.
Bond roof vents, flashing and any other metal masses projecting
through the roof to the grid.
Thermo weld all connections between cables and ground rods.
Compression type connectors may be used where approved by the
Consultant.
Measure the resistance of the complete installation and submit for
review to the Consultant.
Test clamps shall be provided in each inspection pit to allow for testing
and commissioning.
Concrete inspection pits with cover shall be installed flush with finished
floor level and be fully accessible.
The complete installation shall be tested and inspected to ensure that it
complies with the requirements of the Specification and the Local
Authorities. The tests shall be carried out in accordance with the
Regulations and to the satisfaction of the Consultant.
Commissioning:
The inspection and tests shall be carried out in the same sequence as
set out in the Regulations, Local Authorities and the Consultant
requirements and in such time as to allow any remedial work to be
completed prior to Practical Completion.
All instruments necessary for inspection and testing shall be supplied
and shall be properly calibrated and operated by personnel skilled in
their use.
Allowance shall be made for disconnection or similar operations to
satisfy the requirements for testing, etc., and the reinstatement of the
installation.
Measure earth resistance not less than two full days after the last trace
of precipitation and without the soil being moistened by any means
other than natural drainage or seepage and without any chemical
treatment or other artificial means of reducing natural earth resistance.
Where resistance to earth exceeds specified values, notify the
Consultant the same and include recommendations to reduce earth
resistance and to accomplish recommended work.
Restore surface features at areas disturbed by work of this section.
Restore areas disturbed by trenching, storing or dirt, cable laying, and
other activities to their original condition..
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Earthing System Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Earthing System Installation will
be as follows:
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
DISABLED SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Disabled System for the project.
This document details the Disabled System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Grounding:
Identification:
Programming
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
4. Ensure that the site is maintained clean and tidy.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Disabled System Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Disabled System Installation will
be as follows:
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
DIESEL GENERATOR INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Diesel Generator for the project.
This document details Diesel Generator Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Pre-Installation:
All materials and documentation relevant to this particular section of
works shall be checked prior to the installation.
Make sure that the plinth is completed and painted and ready for final
installation of equipment.
Make sure that the generator room is clear and free of debris and
foreign materials.
Ensure that the access for generator set installation is free from
obstructions.
Make sure that supporting flanks, pipe rollers, chain blocks, hydraulic
jacks and other tools required for installation are in place.
Installation:
Lift the Generator using mobile crane or portable hydraulic crocodile
jack. Place pipe rollers under the generator skid. Make sure that the
pipe rollers are properly set.
Once the generator set will sit on the pipe rollers, push in / pull in the
generator set inside the room. If required, use chain block to pull the
generator set. Make sure that the chain block is properly anchored and
properly set to the direction of generator position.
Where in a generator set crosses a trench or unequal elevation, use
steel channels or I- beams to support the pipe rollers. Make sure that
the steel channels or I-beams are properly supported to carry the
weight of the Generator set.
Set the Generator set in proper location. Lift the Generator set using
portable crocodile hydraulic jack and let it sit on elevated flanks or I-
beams.
Fix the spring vibration isolator. Ensure that it is fixed and aligned
properly.
Lift the Generator set and install the spring vibration isolator. Bolt and
tight properly the Generator base on to the spring vibration isolators.
Associated work related to the Generator set such as generator
exhaust system, fuel system, acoustic lining etc, will commence.
After completing all associated works related to the Generator set,
raise a Request for Inspection for Generator Installation.
Commissioning:
Test the Generator in accordance to specification and manufacturer
recommendation.
All testing will be carried out in the presence of Consultant.
Test shall be carried out by the manufacturer’s testing engineers.
All test sheet shall be certified by the manufacturer representative.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the system
after the installation is completed.
This instruction shall be scheduled at the convenience of the staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shopdrawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
2. To ensure that the progressing of works is carried out according
to the planned program and as per the approved method of
statement.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Diesel Generator Installation will
be as follows:
1. Hand Tools
3. Diagonal-Cutting Pliers
5. Side-Cutting Pliers
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
DEVICES WIRES INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Devices' Wires for the project.
This document details Devices' Wires Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Mark the location of isolator on the walls or ceiling. The mounting
height of isolator/disconnect switch in the walls are as follows :
15A to 125A isolators mounting height shall be 1400mm
A.F.F.L. from the top.
200A and above, mounting height shall be 1800mm A.F.F.L.
from the top.
Fix uni-strut channel support on the wall. Ensure that it is fixed
properly and rigid.
Fix the isolator/disconnect switch on the uni-strut channel support.
Ensure that it has been fixed vertically and horizontally aligned.
Terminate the incoming and outgoing feeder cable using
appropriate wiring accessories.
Raise Request for Inspection for isolator/disconnect switches
installation.
Termination:
Clear all boxes from cement stains and foreign materials.
Fix wiring accessories ensuring that they are fixed properly and
squarely aligned.
Ensure that the type of wiring devices shall be as approved type as
to the areas where they are going to fixed. Ensure that all
connections are correct and the wiring devices and boxes shall be
earthed.
Cover all device plates with plastic sheet to protect the wiring
accessories.
Request for Inspection shall be raised for wiring devices installation.
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings and specs and manufacturer recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
4. Ensure that the site is maintained clean and tidy.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
Devices' Wires Components and Accessories
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Devices' Wires Installation will be
as follows:
Measuring tape
Cutting plier
Bending spring
Pipe Wrench
Drilling Machine
Crimping tool
Screw driver
Pulling spring
Hammer
Common tools
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
CLOCK SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations Clock
system for the project.
This document details the Clock system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Installation of Wires:
Grounding:
Identification:
Programming:
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
CS Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Clock System Installation will be
as follows:
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
CCTV SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
CCTV system for the project.
This document details the CCTV system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Installation of Wires:
Grounding
Identification
Programming
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
CCTV System Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for CCTV System Installation will be
as follows:
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
CABLE TRAY AND TRUNKING SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1.SCOPE
This procedure to clear the method of the supply, installations Cable
Tray and Trunking System for the project.
This document details the Cable Tray and Trunking System
Installation :
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Installation:
Cable Tray / Trunking shall be stored on site under cover in dry, well
ventilated storage facilities.
Where sizes of Cable Trays / Trunking are not detailed on drawing then
tray shall be adequately sized to support the cables without bunching
and a 25% reserve margin shall be allowed in size and weight be
loaded.
All routes are chosen to allow ease of access to all cables when
installed. All horizontal cables are to be set around all vertical rising
services as necessary. Ensure sufficient clearance from soffit for every
installation.
Earth continuity conductors shall be provided across gaps in all Cable
Tray / Trunking runs and bolted connections.
The cable tray shall be installed with a 40mm minimum space between
the structure and the tray.
All cable shall be securely fixed to the tray, work and the complete
installation must be carried out in a neat and workmanlike manner
without crossovers.
Technical Assistance:
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Cable Tray / Trunking System
Installation will be as follows:
1. Wire cutters
2. Hacksaw
3. Measuring tape
4. Drill machine
5. Wooden hammer
6. Flat file
7. Screw drivers
9. Base Cutter
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information / action / comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
AUDIO VISUAL SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations A/V
system for the project.
This document details the A/V system Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Installation of Wiring:
Grounding:
Identification
Technical Assistance:
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
3. Inspect all the site activities and train the person to prevent
accidents and it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians
8. MATERIALS REQUIREMENTS
AVS Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Audio Visual System Installation
will be as follows:
1. Tools for fixing the ceiling projector lift/ brackst on a vertical surface.
2. Tools for fitting equipment in the AV rack
3. A small flat-bladed (terminal) screwdriver for electronic devises
4. Tools for cabling terminations and soldering,
5. A pair of wire cutters/strippers appropriate for the type of cable used,
6. Ferules and ferruling tool for dressing the ends of cables (if stranded
conductors are used),
7. Pulling Spring
8. Hammer
9. Measuring tape
10. Drilling tools.
11. Ladders.
12. Scaffolding (to be provided by the contractor for the High level Area).
13. Safety requirements tools such as safety shoes, safety helmet,
safety glasses, fluorescent vest, and safety gloves to insure
maximum ability of safe work and dust mask when required.
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper
METHOD STATEMENT
FOR
ACCESS CONTROL SYSTEM INSTALLATION
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS REQUIREMENTS
9. EQUIPMENTS REQUIREMENTS
13. DISTRIBUTION
1. SCOPE
This procedure to clear the method of the supply, installations of
Access Control System for the project.
This document details the Access Control System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
Specific safety measures have to follow as applicable, and all the safety
measures are covered separately in the project safety plan.
4. OPERATION
Material:
Make sure that civil clearance done prior to start the installation.
Installation will be carried out as per manufacturer
recommendations, Approved shop drawings and project
specifications.
Installation:
Grounding:
Identification
Programming
Technical Assistance:
The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site
Manager on the programming and correct operation of the
system after the installation is completed.
This instruction shall be scheduled at the convenience of the
staff.
All such instruction shall be properly recorded.
WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved
shop drawings, approved specs and manufacturer
recommendations.
6. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are
carried out according to the Contract Specification and with the
approved drawings.
SITE ENGINEER
1. To ensure that the works are carried out according to the
Contract Specification, approved method statement and the
shop drawings.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure
proper distribution of the work force on the required and planned
locations.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in
accordance with the HSE plan and everybody aware of it for it’s
proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to
store the material delivery to the site and keep it in suitable
area that will keep the material in safe from rusty and
damage.
2. One who will acknowledge the receiving of materials at site in
coordination with QA/QC and concerned Engineer.
7. MANPOWER REQUIRED
Charge hand and Experienced Technicians.
8. MATERIALS REQUIREMENTS
ACS Components and Accessories.
9. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for ACS Installation will be as follows:
13. DISTRIBUTION
Copy of this method statement shall be issued to the following for
information/ action/ comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper