Professional Documents
Culture Documents
METHOD STATEMENT - PIle Build Up
METHOD STATEMENT - PIle Build Up
Approved
Rev Date Description
Yes No
Contents
1. General
2. Materials
3. Methodology
Method Statement for bored pile buildup works
Proposed 15 MW Wind Power Plant at Nanattan, Mannar
1.0 GENERAL
This Method statement purposeful to rectify the damaged or under cast piles.
2.0 MATERIALS
Water
Rebar
Steel Casing (shuttering for built-up pile)
3.0 METHODOLOGY
Concrete will be hacked up to a hard concrete level. (Joint inspection will be done for
confirmation)
Surface of the pile will be cleaned with water and pressurized air.
Casing will be installed (checking the center of the pile and verticality of the casing)