ACCESS ENGINEERING PLC

CONSTRUCTION OF CAST-IN SITU BORED PILE FOR


PROPOSED 150MW WIND POWER PLANT AT NANATTAN
MANNAR

METHOD STATEMENT FOR BORED PILE BUILDUP AND


RECTIFICATION WORKS

Access Document No: PWPP/PBUR/MS/R0

Approved
Rev Date Description
Yes No

00 09/06/2022 Submission for Approval


Method Statement for bored pile buildup works
Proposed 15 MW Wind Power Plant at Nanattan, Mannar

Contents

1. General
2. Materials
3. Methodology
Method Statement for bored pile buildup works
Proposed 15 MW Wind Power Plant at Nanattan, Mannar

1.0 GENERAL

This Method statement purposeful to rectify the damaged or under cast piles.

This under casting has identified during the visual inspections.

Illustration of under cast pile

Cut off level

Under cast Height = X)


Method Statement for bored pile buildup works
Proposed 15 MW Wind Power Plant at Nanattan, Mannar

2.0 MATERIALS

Water
Rebar
Steel Casing (shuttering for built-up pile)

3.0 METHODOLOGY

 Firstly, pile top will be cleaned.

 Excavation up to required level will be done by stepwise if required

 Concrete will be hacked up to a hard concrete level. (Joint inspection will be done for
confirmation)

 Surface of the pile will be cleaned with water and pressurized air.

 Casing will be installed (checking the center of the pile and verticality of the casing)

 Concrete will pour up to cut off level.

 Casing will remove after hardening of concrete.


Method Statement for bored pile buildup works
Proposed 15 MW Wind Power Plant at Nanattan, Mannar

After completion of work

Cut off level

Build up portion (Height =X)