Gantt Chart for Trunking Rectification

January February
No. Job Description Remarks
W1 W2 W3 W4 W5 W6 W7 W8 W9 Area A = C1 to C9 Area A = C10 to C18
1) Subject to PR approval and supplier
Issue PR for trunking Paint and material
1 availability due to CNY.
delivery.
2) Target delivery by 27/1/2023
Target start : 28/1/2023
2 Rectification at Area A C1 to C9
Target complete : 4/2/2023
Target start : 5/2/2023
3 Rectification at Area B C10 to C18
Target complete : 12/2/2023
Target Completion
Actual Timeline
Exceeded Timeline

Gantt Chart for LED Light Relocation at BA Compounding Area.


January February
No. Job Description Remarks
W1 W2 W3 W4 W5 W6 W7 W8 W9
1) Subject to PR approval and supplier
Issue PR for new LED for C4/C12/C10 and
1 availability due to CNY.
material delivery
2) Target delivery by 27/1/2023
Target start : 17/1/2023
2 Rectification at Area A C1/C2/C3
Target complete : 19/1/2023
Target start : 20/1/2023
3 Rectification at Area A C5/C6/C7
Target complete : 22/1/2023
Target start : 23/1/2023
4 Rectification at Area A C8/C9
Target complete : 24/1/2023
Target start : 25/1/2023
5 Rectification at Area A C11/C13/C14
Target complete : 27/1/2023
Target start : 29/1/2023
6 Rectification at Area A C15/C16/C17/C18
Target complete : 31/1/2023
Target start : 1/2/2023
7 Rectification at Area A C4/C12/C10
Target complete : 3/2/2023
Target Completion
Actual Timeline
Exceeded Timeline