CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: WAGON TRIPLER
01 no of JCB & 01 no of
1 GSB Gr I 250 02.01.2021 04.01.2021 80 5 compactor/roller
80 m*4 m*0.5 m
01 no of JCB & 01 no of
2 WMM 250 04.01.2021 07.01.2021 80 5 compactor/roller
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS
CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: WAGON TRIPLER 144 SQM RCC ROAD
01 no of JCB & 01 no of
2 GSB Gr I 250 07.01.2021 09.01.2021 36 5
compactor/roller
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS
CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: ROAD WIDENING AT IPP GATE ENTRANCE
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS
CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: DRAIN EXCAVTAION FOR AHP AT IPP
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS
CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: CULVERT ENCASING FOR AHP AT IPP
Excavation/Dismen
1 taling the existing 15.01.2021 18.01.2021 - 4 01 no of JCB
strutures
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS
CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: NEW COAL YARD ROAD FOR CHP
01 no of JCB & 01 no of
2 GSB Gr I 250 25.01.2021 28.01.2021 39.38 5
compactor/roller
NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO