You are on page 1of 6

WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: WAGON TRIPLER

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

01 no of JCB & 01 no of
1 GSB Gr I 250 02.01.2021 04.01.2021 80 5 compactor/roller
80 m*4 m*0.5 m

01 no of JCB & 01 no of
2 WMM 250 04.01.2021 07.01.2021 80 5 compactor/roller

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: WAGON TRIPLER 144 SQM RCC ROAD

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

1 Excavtion 850 04.01.2021 06.01.2021 122.4 3 01 no f JCB

01 no of JCB & 01 no of
2 GSB Gr I 250 07.01.2021 09.01.2021 36 5
compactor/roller

144 SQM of area as


per decidsed by EIC 01 no of JCB & 01 no of
3 of VL WMM 250 10.01.2021 12.01.2021 36 5 compactor/roller

4 PCC 100 14.01.2021 15.01.2021 14.4 7 01 no of Ajax

5 RCC 250 16.01.2021 18.01.2021 36 10 01 no of Ajax

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: ROAD WIDENING AT IPP GATE ENTRANCE

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

Excavation & 01 no of JCB & 01 no of


1 Compaction 300 29.12.2020 05.01.2021 approx. 50 m3 4 compactor/roller
Sujected to as per
final exacvation
completion, triangle
shape
01 no of JCB & 01 no of
2 WMM 300 08.01.2021 12.01.2021 approx. 50 m3 4 compactor/roller

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: DRAIN EXCAVTAION FOR AHP AT IPP

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

1 Excavation 10.01.2021 15.01.2021 - 4 01 no of JCB

2 Bottom PCC 16.01.2021 16.01.2021 - 4 01 no of Ajax


As per Drg.
53 RM Provided by EIC
Both Side wall of VL
3 Reinforcment 17.01.2021 20.01.2021 - 8 -
fixing

4 Casting of Wall 20.01.2021 21.01.2021 - 8 01 no of Ajax

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: CULVERT ENCASING FOR AHP AT IPP

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

Excavation/Dismen
1 taling the existing 15.01.2021 18.01.2021 - 4 01 no of JCB
strutures

2 Bottom PCC 18.01.2021 21.01.2021 - 4 01 no of Ajax


As per Drg.
75 RM Provided by EIC
Hume Pipe laying of VL
01 nof JCB/01 no of 3rd
3 of NP3 grade of 22.01.2021 26.01.2021 - 10
Gen. Hydra
600 mm dia

Encasing the pipe


4 area with layer of 27.01.2021 02.02.2021 - 8 01 no of Ajax
reinforcement

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO
WORK SCHEDULE FOR IPP PROJECTS

CLIENT: VL
AGENCY: JP AUTOCLAVERS & CO.
AREA: NEW COAL YARD ROAD FOR CHP

Thickness in Date of Manpower


SL NO Dimensions Activiity mm starting Date of Completion Qty in (M3) reqd. Resources reqd. Remarks

1 Excavtion 850 21.01.2021 24.01.2021 133.88 3 01 no f JCB

01 no of JCB & 01 no of
2 GSB Gr I 250 25.01.2021 28.01.2021 39.38 5
compactor/roller

(45 m* 3.5 m) 01 no of JCB & 01 no of


3 WMM 250 29.01.2021 02.02.2021 39.38 5 compactor/roller

4 PCC 100 03.02.2021 05.02.2021 15.75 7 01 no of Ajax

5 RCC 250 07.02.2021 12.02.2021 39.38 10 01 no of Ajax

NOTE: The above programme subjected to area clearence & recevied work permit at proper time
As per Work schedule the time for all area will be completed for next 45 days,instead of 06 months as per mentioned in PO