Germaine Revised: 27/02/2023

Estimate
Lead
Job No Project Name Comments Deadline working
Engineer
days
2023-15 Ville Es gros (phase 3) MG send out trial pits to clients
2022-100 High Trees MG Drainage design checked. Ammend drawings as per comments by IH.
2022-91 42 clos saut falluet MG calcs and drawings c1 ready for checking.
2022-94 77 St Marks Road MG Calcs completed. JM to finish RC details and bar bending.
Drawings (done as much as I can) - awaiting for trial holes. opening up
2022-60 167 Les Quennevais Park MG
works sent out. Waiting for site visit
Drainage report on hand. Awaiting benchmark details for timber frame.
2022-99 Clos de la Hauteur MG Drainage design . awaiting for trial holes. opening up works sent out.
Waiting for site visit

Issued SER package - need to desgn privacy screen supports (RC beam)
2022-45 Icho House MG
Schedule 2
2021-134 Sunbury MG Revised drawings sent. Compile calcs for SER
2020-64 ville es gros 2 MG/BH Schedule 2 item
2019-69 ville es gros 1 MG/BH Schedule 2 item
additional work, internal check- updare drawings/calcs as per internal
2022-48 Eden house MG
check
2020-142 7 peter street BH juliette balcony fixing and member design (screws) checked by TM

Totals 0