You are on page 1of 1

Main Contract

SSA Weekly Plan


18 July 2023 - 24 July 2023

No. Description Person In Charge / SPV


A Parking Area & Others
1 Excavation RCP Line 18-19. Mr. Alvin
2 Concrete Pouring SM A1 dan SM 01. Mr. Alvin
3 Backfill Manhole. Mr. Alvin
Grinding Polish Wall Manhole 22, 23, 25, 26, 29, 30 for
4 Mr. Alvin
Epoxy Application Preparation.
5 Excavation Septic Tank ST 07. Mr. Alvin
Install RCP 18-19 (Need More Info From Leemax
6 Mr. Alvin
Pabrikasi Area).
7 Pabrikasi Upper Slab Manhole 22, 23, 25, 26, 29, 30. Mr. Alvin

B Sewage Area, Canteen Area & Masjid Area


1 Wall concrete casting ST-05 Mr. Suprapto
2 Install RCP MH 06-10 Mr. Suprapto
3 Excavation MH 13, 14, 12 & 20 Mr. Suprapto
4 Install Slab Formwork & Rebar Sewage Tank Mr. Suprapto
5 Slab Concrete Casting Mr. Suprapto
6 Bacfill & Compaction Septic Tank ST-02 Mr. Suprapto
7 Excavation & LC SM B3 & SM B14 Mr. Suprapto
8 Install Rebar SM B3 & SM B14 Mr. Suprapto
9 Install Wall Rebar Phase 2 for Sewage Tank Mr. Suprapto

C Section 2 Area (FS, MS & MW)


Wall Formwork installation & Wall Concrete Casting for
1 Mr. Erwin
SMH 14 & 15.
Excavation, install PE pipe & back fille between SMH 14
2 Mr. Erwin
& 15.
Wall Formwork installation & Wall Concrete Casting for
3 Mr. Erwin
SMH 11 & 12.
Excavation, install PE pipe & back fille between SMH 11
4 Mr. Erwin
& 12.
Excavation, LC , Setting Forwork & Slab Casting for
5 Mr. Erwin
Septic Tank Material Warehouse, SMH 10 & 03.