Before After
Before After
Keterangan : Penambahan Support Tray Horizontal Keterangan : Penambahan Support Tray Horizontal
Before After
Pengaman Kaca Panel Kwh Di lepas Pengaman Kaca Panel Kwh Di lepas
Keterangan : Keterangan :
untuk pencatatan meter oleh PLN untuk pencatatan meter oleh PLN
Before After
Keterangan : Keterangan :
Before After
Keterangan : Keterangan :
Before After
Keterangan : Keterangan :
Before After
Keterangan : Keterangan :
Before After
Keterangan : Keterangan :
Before After
Keterangan : Keterangan :
Site ID :
Site Name :
Site Address :
Installed By :
Material Supplied By :
Tower Upgrade Type :
Inspection Date :
Carrier :
RFI Date as per Colo Tracker :
REVIEWED AND APPROVED BY: ACCEPTANCE TEST BY: ACCEPTANCE TEST BY:
PT. PROTELINDO O&M Contractor Name
Version : 2 QC PROTELINDO
Page: 1 of 2
Revision : 1 Eng-QC-TU-Site Acceptance-Form-001 Form Issued Date: 31-Jul-08