You are on page 1of 5

Fatality – NAOC 26/06/2023

Contractor hit by Slick Line sheave during Rigless Operations


Contractor hit by Slick Line Sheave during Rigless Operations
Pressure release, Lubricator Emergency Management and
Rigless Operations at Clough Operative issue
Scope of Work ejection and LTI MEDEVAC
Creek Well 2 during the job
(furtherly resulted in fatality)

During the activity, the team This brought to fail the pressure
observed the Slick Line and the equalization across the downhole Personnel at location were able
The activity on Clough Creek Scope of Work was to carry out upper sheave were not moving. plug and consequently led to the to immediately secure the Well.
Well 2 started on June 17th with maintenance activities on In order to fix the issue, ejection of the same inside the However they took the wrong
Xmas Tree and ambient valve Contractor Supervisor bled off the
the equipment mobilization in lubricator which parted and decision to transfer the IP by
recalibration. pressure in the hydraulic hose of jumped on air. boat to bring him to Clough
location. On June 18 th job Operation was performed with the SL stuffing box through the The lubricator ejection determined Creek Flow Station without
officially commenced on site. support of Slick Line service dedicated hydraulic line, and the Slick Line cable tension and stretcher. In addition the Night
and downhole plug. proceeded to slack the cable at strong knockback. Consequently MEDEVAC was activated with
the bottom sheave to resume jar the lower sheave, connected to some challenges related to
action such cable, strongly impacted the some improvement points on
IP’s chest and chin. the execution to be
IP medical conditions immediately implemented after Aviation
appeared critical. The event led also Advisor recommendations.
to a slight gas release

Accident resulted in a Fatality and in the


activation of a 1st Level Emergency (Not
Noticeable Outside)
(*) Additional considerations on the event’s dynamic will be done after
2
cases’ study by experts and lubricator’s failure analysis
What Went Wrong
Rigless Program developed
PtW, Risk Assessment, Method of Human Factor, Risk Misperception and Change Management
In presence of an issue (blocked Slick Line sheave), Contractor Emergency Response
Statement, Isolation Certificate, TBT
Supervisor decided to bleed off pressure in the hydraulic hose of Lack of knowledge on First Aid
forms: all available in location
the Slick Line stuffing box by pushing the small ball in the check Operations and Emergency
Improvement needs have been
valve seat allowing the hydraulic oil to bleed. This brought to the Communications.
observed in the procedures
failure of the pressure equalization and following lubricator’s Night MEDEVAC Operations to be
coordination and implementation
ejection. Operator didnt’ stop the activity to re assess the Risks. improved.

1 2 3 4 5

Lack of Supervision Competence & Training


NAOC Company Man present but not in Contractor’s personnel competences were not previously
the event’s scene and not fully aware on assessed before starting the activity due to lack of
activity’s risks. NAOC HSE spv not in Procedures. During the contractor’s personnel interviews
location. Contractor’s HSE SPV not carried out in the Investigation process competence’s gaps
appointed. appeared evident for some crews members.

Most impacted SAFETY GOLDEN RULES:


Planning of the Execution of the Competence & training • Energized Systems
activities activities • Management of Change (MoC)
• Permit to Work (PtW)

Most impacted PROCESS SAFETY FUNDAMENTALS:


• Provide Safe Isolation prior to Start Maintenance Activities;
3
• Operate Bypass of Safeguards only with Authorization;
Lesson Learnt

• Event’s Investigation through a multidisciplinary Team; • While dealing with HIGH PRESSURE FLUIDS ensure proper BARRIERS always in

• Immediate Suspension of Rigless Activities to re-assess their place;

safety conditions; • In case the assessed workflow (as per Method of Statement) CHANGES, proper
Risk Assessment must be done and mitigations identified. It must be treated as
• Safety Stand Down with all Eni Nigeria employees;
MANAGEMENT OF CHANGE;
• Meeting with the involved Companies in order to understand
• Whenever you are planning a job, always take in consideration the
more clearly the event’s dynamic;
OPERATIONAL CONTEXT and the PROCESS CONDITIONS;
• Meeting with WOP Contractors to spread the Event’s
• All OPERATIONS (Routinely and Critical ones) require COMPETENT PERSON to
dynamic, Lessons Learnt and agree about the way forward to be performed; their knowledge must be FORMALLY ASSESSED prior to start any
improve; job;
• In all locations MEDEVAC DRILLS must be performed and personnel to be
adequately informed and trained about the existent Procedures to be
implemented;
• Proper COMMUNICATION devices in remote areas are fundamental to manage
any EMERGENCY SITUATION;
• ENSURE SAFE RESCUE by MEDEVAC of the workers DURING DAY & NIGHT;
• STOP WORK AUTHORITY to be always applied whenever required (Anyone is
entitled).

4
Thank you

You might also like