11/199/2023-CIVIL SEC-SSA
Instructions of CSI
Ref:
******
Nippon.
3. PRE-MEASUREMENT AND STANDARD DEDUCTIONS:
Pre-measurement should be done as per the standard
practice and co-efcient being adopted in engineering
departments which are given below.
i. No deduction shall be made for openings not exceeding
0.5sqm.
ii. Deductions for openings exceeding 0.5sqm but not exceeding
3sqm, the standard deductions should be followed. When both
faces of wall are provided with same fnish, deduction shall
be made for one face only.
iii. In case of openings of areas above 3sqm each and also in case
of RR/CRS masonry walls, deduction shall be made for
openings, but jambs, softs sills and reveals shall be measured.
iv. The co-efcient applicable for pre-measurements is given
below:
compound walls.
• Cleaning the surface by Bio-wash / Jet-wash and allow the
surface to completely dry overnight for new buildings and old
buildings.
• Primary coat: Apply one primary coat by using spray cum
roller equipment / manual roller.
• Single coat: (Emulsion paint): Ensure clean and free from dust
if primary coat is applied more than 7 days before top coat
application.
• Allow primary coat to completely dry for 4 - 6 hours.
• Apply single coat of Emulsion paint by using spray cum roller
equipment / manual roller.
ii. NEW COMPOUND WALLS:
• Cleaning the surface by Bio-wash / Jet-wash and allow the
surface to completely dry overnight.
• Primary coat: Apply one primary coat by using spray cum
roller equipment / manual roller.
• First coat: (Emulsion paint): Ensure clean and free from dust if
primary coat is applied more than 7 days before top coat
application.
• Allow primary coat to completely dry for 4 - 6 hours.
• Apply frst coat of Emulsion paint by using spray cum roller
equipment / manual roller.
• Second Coat: Ensure clean and free from dust if frst coat is
applied more than 7 days before top coat application.
• Allow frst coat to completely dry for 4 - 6 hours.
• Apply second coat of Emulsion paint by using spray cum roller
equipment / manual roller.
7. WOOD WORK:
i. Sand the wood with 80 grid sand paper along the grains of the
wood to create uniform surface.
ii. To wipe of the surface with a clean dry cloth.
iii. Luppam should be used for smooth fnish and again sand paper
should be used for uniform surface.
iv. Wood - Primer coat:
• Apply a criss cross coat to achieve required thickness.
v. Enamel paint – First Coat:
• Dry overnight for primer coat.
• To wipe of the surface with a clean dry cloth.
• Apply one coat of synthetic enamel paint by using suitable
brushes.
vi. Enamel paint – Second Coat:
File No.11/199/2023-CIVIL SEC-SSA
ii. The H.M and one of the members from parent committee will
be a part of the measurement process and validate that
measurements are taken properly by the Berger/Nippon team.
iii.This will not exonerate Berger/Nippon to show the correct
measurements after work is completed.
c. WOOD WORK:
iv. After completion of the wood work, the detailed
measurements shall be recorded by the feld Engineers in the
presence of H.M, Berger/Nippon Team and one of the members
from Parents Committee.
v. The H.M and one of the members from parent committee will
be a part of the measurement process and validate that
measurements are taken properly by the Berger/Nippon team.
vi. This will not exonerate Berger/Nippon to show the correct
measurements after work is completed.
d. IRON WORK:
i. After completion of the iron work, the detailed measurements
shall be recorded by the feld Engineers in the presence of H.M,
Berger/Nippon Team and one of the members from Parents
Committee.
ii. The H.M and one of the members from parent committee will
be a part of the measurement process and validate that
measurements are taken properly by the Berger/Nippon team.
iii. This will not exonerate Berger/Nippon to show the correct
measurements after work is completed.
1 .WORK COMPLETION CERTIFICATION BY Field Engineer /
Head Master:
Once the work is completed, the Field Engineer / H.M will
acknowledge the completion as ‘Completed / partially
completed / Not Started / Not required’ for each of the 7
elements given below. They will sign on this sheet with seal
and handover to Berger/Nippon team when they leave the
site. One Abstract copy of the Measurement Sheet will be
handed over to the H.M. The H.M will hand over the same to
the Field Engineer.
WORK COMPLETION CERTIFICATE
(please tick the relevant box)
School Name:
Code: Mandal: District
File No.11/199/2023-CIVIL SEC-SSA
Bhaskar Katamneni I A S
To:
All the Collectors and District Magistrate in the State.
All the District Education Ofcers and APCs.
All the P. O’s, ITDAs.
All the Commissioners, Municipal Corporations in the state
All the Executive Engineers through D.E.O
All the Dy.E.E’s, Field Engineers through the Executive Engineer
Copy to:
The State Project Director, APSS, Vijayawada.
The Managing Director, APEWIDC, Vaddeswaram, Guntur District.
The Engineer-in-Chief, PR, PHED, TWED, AP.
The Chief Engineer, APEWIDC, Vaddeswaram, Guntur District.
The Chief Engineer, RWS, Gollapudi, Vijayawada.
The Chief Engineer, APSS, Vijayawada
All the RJDSE in the State.
Copy to M/s. TCS to put a copy in STMS documents.
Copy submitted to the Principal Secretary, Government School
Education.