I. OPERATING MECHANISM
S.No. Description Activity
Preventive Maintenance Schedule & Formats for Substation Equipments DOC: D-3-02-XX-01-09
2
Note: Contact Resistance is to be measured for total ie, Main/ Transfer Contacts, in case of HCB
Isolators and both the Main Contacts in case of HDB Isolators. Individual measurement
shall be carried out when the measured values are higher to identify the defect for
rectification.
Max.
Contact Resistance
Test results Permissibl
e Limit
R Phase Y Phase B Phase
Pre-commissioning Values
300 micro-ohm
Previous Values
Present Values