METHOD STATEMENT
FOR
INSTALLATION OF LV AC SWITCH GEAR, PANELS &
DISTRBUTION BOARD
SYSTEM
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
info-utilities@elsewedy.com
www.elsewedy.com
INDEX
1.0 Purpose
2.0 Scope
3.0 Reference
7.0 Procedure
1.0 PURPOSE
The purpose of this procedure is to describe the method of installation & Testing of L V AC Switch Gears, Panels
& Distribution Boards.
2.0 SCOPE
This procedure shall be applicable to installation and testing of L V switchgears viz., Power Control Centers,
Distribution Boards and Feeder Pillars of voltage 433 V and below. The Procedures also covers installation and
testing of LV Switchgears, Panel's & DB under the project
3.0 REFERENCES
Approved GA drawings.
4.2 DEFINITIONS
Company : This shall mean Gulf for building & Construction or it’s nominated representative
He shall be responsible for overall execution, administration, monitoring and control of the project as per the
contractual requirements including but not limited to:
Assess manpower, equipment and other resources required to achieve targets set and co-ordinate with
RAY Management for obtaining necessary resources for the project and deploy as required
Coordinating for all the procurement and subcontracting activities related to the project.
Identify Training needs and Coordinate for fulfilling the Training Requirements.
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
Sequence of activities to be carried out for the work as per this work procedure
Contract specific requirements for installation and testing of earthing system, if any specified shall be
identified and the requirements of such specification shall prevail in addition to the non-conflicting
Toolbox talks with the concerned work force prior to start of the work is a mandatory requirement.
Ensure that relevant permits applied and obtained prior to the commencement of work.
Ensure all PPEs are available with all the workers involved in the work.
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
info-utilities@elsewedy.com
www.elsewedy.com
Ensuring the sufficient First Aiders and Fire Wardens are available with the crew.
Permit to work system shall be followed with due care wherever applicable.
Ensure all PPEs are available with all the workers involved in the earthing related works
All required equipment and tools should be checked before start of work for suitability and integrity.
Ensure that the work is done under the supervision of Supervisor I Engineer.
All necessary tools are to be taken along once and for all till the completion of the work.
Incidents I Accidents if any shall be reported to concerned authorities in the prescribed written format.
Equipment’s:
Crane (Suitable)
Hiab
Caution Tape
Hand Tools
Skid rollers
Pallet truck
Pipe rollers
Marking Accessories
Spirit Level
Lifting equipments (shackle,
belt etc)
Measuring Tape
Ladders
Torque wrench
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
info-utilities@elsewedy.com
www.elsewedy.com
Ductor
Multimeter
7 PROCEDUR
Ensure that all civil works are completed and civil to electrical handover is done before starting the
installation activities
Ensure air conditioning inside the switchgear room preferably before equipment is installed.
Ensure temporary power connection is available for connecting up panel space heaters if required.
All floors are to be leveled to ensure suitable for installation and switch room floors shall be clean and
Cordon off area around installation locations for restricting access to unauthorized personnel and fix
Ensure that necessary lifting gears, belts, spread bar of adequate capacity is available at site and before
shifting.
Always maintain the switchboard in a vertical position during handling and avoid sudden shock I am
Force to move the equipment should be applied only to skid and leverage force should not be applied to
the panels.
Ensure that when pushing or pulling operation, the front and rear of the switchboard sections are
Lift the panel (without crates) using crane to the landing platform of the switchgear room. Lower the
boom and extend it maximum without the sling touching the door
Lower the boom so that the panel is landed on to the Skid roller/Pallet truck/Pipe roller.
Ensure that lifting gears, slings, spread bar are of adequate capacity.
Tie the nylon belt, which is taken across the panel, to a hook chuck, or chain block and hold it tight.
Remove the front side sling from the hook of the crane.
Pull the nylon belt so that the panel will move inside the substation.
After the complete panel is well inside the access platform, the rear side sling can be removed.
Check foundation and base frames etc. are ready and matches with the layout drawing and manufacturer
recommendations.
Check foundation frame with drawing for correctness of bolt fixing holes and correct level all through
Make sure cutout is made on the foundation for cable entry etc. and doesn't foul with the equipment.
Only the correct size and type of tools shall be used in the erection of switchgear.
Install the equipment on the foundation frame starting with center section matching with the central
Ensure fixing bolts are used in every position that has been provided for them.
Before placing each section, check for any items such as sleeves I linings, bushings, trap wires, links,
packing etc. that need to be threaded or inserted before placing the adjacent section, ensuring that such
Final placing of sections to either side of center section shall be under taken alternately with leveling
Tighten each bolt, starting from the center section and working out wards at both sides.
Final placing of sections to either side of center section shall be undertaken alternately with leveling and
skimming as required.
Check serial Nos. and type of each unit against drawings to confirm whether it is as per the requirement
As each panel is completed, checks shall be made to confirm that it is perfectly vertical. Between fixing of
sections , bus bars and insulators shall be checked to ensure that no strain is placed on them.
Ensure the anti-condensation heaters are energized at the earliest possible time.
Ensure Bus bar contact surfaces and tee-off connector surfaces are clean on both sides before bolting;
after cleaning, faces shall be wiped with a clean rag to remove all dust.
Only nuts, bolts and washers supplied with switchgear shall be used for bolting switchgear, bus bars etc.
Ensure all connecting parts of busbar system are properly installed, bolts tightened, torque and marked
Thorough check in all compartments, cubicles, units, bus bar cubicle shall be carried out to ensure no
In draw out type Switchgear panels, the modules I breakers are checked for easy insertion I withdrawal
Ensure that the earth buses on the either side of the panel are connected to the main earthing grid.
All the instruments, relays etc. should be tested as per the QCP check list prior to mounting.
Ensure proper mounting of instruments, relays, meters, indication lamps, which are supplied loose.
Incoming and outgoing cables shall be installed and terminated as per the approved drawings in
accordance with the Quality Control Procedure for Installation & Testing of cables.
Ensure floor penetrations are sealed after cables are installed, by suitable polyurethane foam sealant if
required
Ensure all the inter panel wiring is completed as per the drawing.
Ensure that the equipment identification I labels are properly placed as per drawing.
7.2 LV SWITCHGEARS
· Initial checks on the installed switchgear as detailed in the applicable section of L V AC Switchboard
Installation Check sheet Form shall be carried out and the results shall be recorded.
The Ductor test for checking the contact resistance of the Circuit Breaker, Isolator and Bus Bar Joints
shall be carried out and the results shall be recorded in the test format.
When the switchgear is provided with circuit breakers, checks I tests as detailed in Circuit Breaker
Testing Report Form shall be carried out and the results shall be recorded.
If the LV switchgear is provided with independent CT operated protection relays, other than integral
overloaded short circuit protection, then the tripping of the breaker through these relays shall be
checked.
The incoming and outgoing cables to the switchgear shall be connected as per the approved drawings.
The control and earthing between sections, if any, shall be provided as per the applicable termination
drawings.
7.2.5 Earthing
The switchgear shall be connected to the earth grid, at least at two different locations, using earth
It shall be ensured that the earth continuity bar in the switchgear is installed properly and in connected
to grid earthing.
P.O. Box 311- 5th Settlement 11835
Plot 27, 1st District, 5th Settlement,
New Cairo, Cairo, E G Y P T
T +20 2 27599700 [60-lines]
F +20 2 27599731
info-utilities@elsewedy.com
www.elsewedy.com
Current Transformers and Voltage Transformers shall be tested as per procedure and the test data shall
be recorded.
The relays shall be tested in accordance with the manufacturer's instructions and I or in accordance
with specific procedures to be developed for testing of such relays. The test data shall be recorded.
After completion of the testing as listed above viz., Ductor Test, Circuit Breaker Test, CT test, VT test and
Relay test as applicable, the switch gear shall be subjected to the final installation check. Checks I tests as
indicated in the applicable sections of the L V Switchgear Installation Check sheet shall be carried out
7.2.8 Acceptance
The results obtained during the testing of the L V AC switchboard shall be verified with the records of
routine test reports, if any, supplied by the manufacturer of the switchgear for conformance.
On completion of the checks/tests the applicable test records shall be signed-off by the Discipline
8. Records
ITP:
Formats:
LV AC Switchgear Installation.
Equipment Earthing
. . . END OF PROCEDURES. . . .