You are on page 1of 1

QC CARD

LODHA UPPER THANE


R C C PRE POUR
INSPECTION Request No-
Building Name : Structure:
Level: Date of Casting :
Location : Grade :
Source : Qty:

Sr. Contractor Execution QA Department


Perticulars Tolerances Remarks
No Observation Observation Observation

A SHUTTERING CHECKS - CONVENTIONAL


1 Props in plum & located at exactly end of the spans ± 10 %

2 Shuttering, supports and bracings as per formwork design/ approved ±5%

3 Horizontal wallers in full contect with vertical runners (Column) ±5%


4 Battens in full contect with spans / channels/ I beam (Slab) ±5%
5 Packing to stirrup head / channel / I beam given if used ±5%
6 Opening of stirrup head not more than 60 % Zero
7 Pin of Props used Min-12mm Dia Zero
±5 / 5 / 5
8 Centre, alignment and orientation of member checked
mm
9 Gaps sealing and cleaning of member done Zero

10 Approved shuttering Oil/ releasing agent has been applied Nil

11 Kandas / Cover block provided as required Zero


B SHUTTERING CHECKS - MIVAN
a. Pre Erection Checks.
1 Slab cleaned and marking of layout done Nil

2 Check for reinforcementsas per drawing Nil

3 check for electrical boxes & service lines if any Nil

4 all formwork coated with approved releasing agent Nil


a. Post Erection Checks.
1 Formwork erected as per sequence / Numbering Nil

2 Wall ties installed correctly with PVC sleeve Nil

3 All pins and wedges fixed and tightened Nil

4 All shutters checked for plumb, right angle & alignment ±2 mm

Wexternal working platforms fastened securely to the concrete


5 Nil
structure
6 Spaces between the rocker and floor levelhave been sealed ±2 %
Plumb and alignment of openings, internal walls, external walls & level
7 ± 5 mm
of beam and slab soffits checked
C REINFORCEMENT CHECKS
1 As per drawing with correct spacing and Diameter Nil
2 No crowing bars Zero
3 Lap length & hook bent @ 135 O as per drawing 15mm
4 Chairs provided as specified / required Zero
5 Cover block - Size / Strength / spacing checked Zero
6 Joggling done in (1 in 6) with extra stirrups Zero
7 Master ring provided in column to ensure spacing of main bar Nil
D ELECTRICAL CONDUCTING
1 Done as per the Drawing Nil
2 Drop position not in cover zone checked Zero
3 Space between Conduits maintained checked ±5%
4 Consultant's Approvel form filled Nil

QC BY (Contractor) QC BY (Project Execution) QE BY (Quality Dept.)


Name : Name : Name :
Signature: Signature: Signature:
Date & time: Date & time: Date & time:
Format No-LUT/QA/QF-002 R0 Dt-10-2-18

You might also like