PEMBANGUNAN PLTA KERINCI MERANGIN H

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Senin, 23 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 9:10 2:10 Drilling Face (60 Hole, 3m Depth)
2 9:10 9:40 0:30 Charging and Blasting
3 9:40 9:50 0:10 Ventillating
4 9:50 12:00 2:10 Mucking Out (4 DT Howo)
5 12:00 12:30 0:30 Scalling & Cleaning
6 13:00 16:00 3:00 Standby Dewatering
7 16:00 21:00 5:00 Safety Shotcrete 14 m³
8 21:30 22:00 0:30 Survey & Marking
9 0:00 1:30 1:30 Install Steel Ribs 1 set STA 7309.152
10 1:30 3:30 2:00 Install Forepoling 20 pcs STA 7309.152
11 3:30 5:00 1:30 Install Wiremesh 1 roll STA 7309.152
12 5:00 7:00 2:00 Safety Shotcrete 5 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
UNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

AILY REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
aan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7307.275 7309.152 1.877 1.877

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Selasa, 24 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:00 0:00 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
- Perbaikan Pompa
-
-
-
Issue
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Rabu, 25 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 9:30 2:30 Breaker
2 9:30 10:00 0:30 Survey & Marking
3 11:00 14:00 3:00 Install Steel Ribs 1 set STA 7288.776
4 14:00 16:00 2:00 Install Wiremesh 1 roll STA 7288.776
5 18:00 0:00 6:00 Safety Shotcrete 8 m³
6 1:20 3:40 2:20 Drilling Face (45 Hole, 3m Depth)
7 3:40 4:10 0:30 Charging and Blasting
8 4:10 4:25 0:15 Ventillating
9 4:25 7:00 2:35 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7287.95 7290.567 2.617 2.617

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream Jam : 07:00 - 07:00 WIB


Hari/Tanggal : Kamis, 26 Agustus 2021 Shift : Day & Night

Jam Kerja Waktu STA


No Uraian Pekerjaan Ket.
Mulai Selesai (Menit) AWAL AKHIR +EXCAVASI (m) TOTAL (m)
1 7:00 8:00 1:00 Continues Mucking Out (4 DT Howo)
2 8:00 8:30 0:30 Scalling & Cleaning
3 9:30 10:00 0:30 Survey & Marking
4 10:30 11:30 1:00 Install Steel Ribs 1 set STA 7290.567
5 11:30 13:00 1:30 Install Wiremesh 1 roll STA 7290.567
6 14:00 19:00 5:00 Safety Shotcrete 8 m³
7 19:30 1:00 5:30 Standby Dewatering
8 1:30 4:10 2:40 Drilling Face (60 Hole, 3m Depth)
9 4:10 4:40 0:30 Charging and Blasting 7290.567 7292.908 2.341 4.958
10 4:40 4:55 0:15 Ventillating
11 4:55 7:00 2:05 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material Type Jumlah Satuan
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1 Sigunit L-72 AF pcs
2 Asst Formen 1 2 Genset 250 Kva 1 2 Semen pcs
3 Operator 1 3 Compressor 750 CFM 2 3 Pasir Liter
4 Miner 9 4 Blower 110 1 4 Crushing Brush Sak
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5 Oxygen M3
6 SPV 1 6 Wheel Loader 1 6 Apart Pcs
7 Pelaksana /Surveyor 1 7 Sanchin 2 7 Mata Gerinda Tbg
8 8 Jack Hammer 4 8 Ring Baut 32 Bh
9 9 Breaker SH210 (07) 1 9 Sekop Pcs
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by Approved by

Satria Ronaldo
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Jum'at, 27 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 7:30 0:30 Continues Mucking Out (4 DT Howo)
2 7:30 8:10 0:40 Scalling & Cleaning
3 8:45 9:20 0:35 Survey & Marking
4 10:00 12:00 2:00 Install Steel Ribs 1 set STA 7292.908
5 12:00 14:00 2:00 Break Pray Jum'at
6 14:00 15:30 1:30 Install Wiremesh 1 roll STA 7292.908
7 16:00 20:30 4:30 Safety Shotcrete 7 m³
8 23:30 2:00 2:30 Drilling Face (60 Hole, 3m Depth)
9 2:00 2:25 0:25 Charging and Blasting
10 2:25 2:40 0:15 Ventillating
11 2:40 5:10 2:30 Mucking Out (4 DT Howo)
12 5:10 5:50 0:40 Scalling & Cleaning
13 6:20 7:00 0:40 Survey & Marking
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7292.908 7294.9 1.992 6.95

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Sabtu, 28 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 9:00 2:00 Standby Dewatering
2 9:00 14:00 5:00 Prepare Safety Shotcrete
3 17:30 20:00 2:30 Safety Shotcrete 5 m³
4 20:30 22:00 1:30 Install Steel Ribs 1 set STA 7294.900
5 22:00 23:30 1:30 Install Wiremesh 1 roll STA 7294.900
6 23:30 1:00 1:30 Install Forepoling 20 pcs STA 7294.900
7 1:30 7:00 5:30 Safety Shotcrete 10 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Minggu, 29 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 15:00 8:00 Safety Shotcrete 8 m³
2 17:30 20:00 2:30 Drilling Face (45 Hole, 3m Depth)
3 20:00 20:25 0:25 Charging and Blasting
4 20:25 20:40 0:15 Ventillating
5 20:40 23:10 2:30 Mucking Out (4 DT Howo)
6 23:10 23:40 0:30 Scalling & Cleaning
7 0:00 0:30 0:30 Survey & Marking
8 2:00 4:00 2:00 Install Steel Ribs 1 set STA 7295.919
9 4:00 6:00 2:00 Install Wiremesh 1 roll STA 7295.919
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7294.9 7295.919 1.019 7.969

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs