22.3 Km to IMIP
Total 18 Months of Road Construction, the completion schedule may change in accordance with the alterations of following constraints:
Project Constraints
Area B & D Planned Finished
- Permitting, including Timber cruising/ITSP 01-Jan-24
- Land clearing permit 01-Jan-24
Area A & C
- Permitting, including Timber cruising/ITSP 01-Sep-24
- Land clearing permit 01-Sep-24
Culvert procurement area B 30-Jan-24
Culvert procurement area A 28-Feb-24
Critical Path:
1. Permitting at area A & ITSP Completion with planned to completed on 01 Sep 2024
2. Area A & C Earthworks completion
3. Culvert installation at area A & C
4. Finishing Works area A & C
4
23KM MAIN HAUL ROAD EXTENSION APPENDIX A
REV. A Pricing Schedule WBS/CBS & Pricing Schedule - 23KM MHR Extension
CLIENT
DOCUMENT No.
HR Extension 22.3 KM – Pricing Schedule
PT SULAWESI CAHAYA MINERAL
PROJECT ID 5131900
DATE 28-Nov-23 1 of 2
Area AA
Area
5.9+4.4 km
Area C
2.3 km
Area B
Area D 9.2 km
0.5 km
7
PROJECT PERMITTING
Area A
Stakeholder : IMIP
IMIP action: Forestry release; certification;
final release to MBM to commence
Timeline Est. : ±12 Months
MBM action: Release IPPKH – now complete
Area B
Stakeholder : KLHK Area A
KLHK action:
• Issue PAK IPPKH Conveyor 2
Timeline Est. : ±2-3 Months
MBM action:
• Timber Cruising (ITSP)
Area C
Stakeholder : KLHK
KLKH action:
Area C
• AMDAL permitting – underway
• PPKH Conveyor 3 approval
Timeline Est. : ±12-15 Months Area D
MBM action:
• PPKH Application
• Boundary Marking
• Timber Cruising (ITSP) Area B
Area D
Stakeholder : BDM
MBM + BDM action:
• Agreement to work together inside
BMD IPPKH
Timeline Est. : ±2-3 Months
MBM Action:
November
• Discussion with23
BDM 4 8
PROJECT SCOPE
10
CULVERT INSTALLATION PLAN
Area A Area B Area C Area A
Culvert No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Diameter m 1 1.5 1.5 1 1.5 1.5 1.5 1.5 1.5 1.5 1 1 1.5 1 1.5 1.5 1.5 1.5 1.5 1.5
Length m 45 130 70 85 250 160 125 100 45 45 75 75 175 145 175 135 250 175 130 150
Thickness mm 3.5 3.5 3.5 3.5 7 3.5 3.5 3.5 3.5 3.5 3.5 3.5 7 3.5 7 3.5 7 7 3.5 3.5
Qty Nos 2 1 2 1 2 5 2 1 4 5 1 2 2 2 2 2 6 4 3 4
Height Embankment m 1.5 15 1.5 5 57 34 22 12 1.5 1.5 1.5 8 40 41 60 31 51 71 23 29
Total Length m 90 130 140 85 500 800 250 100 180 225 75 150 350 290 350 270 1500 700 390 600
STA 19+660 STA 21+830 STA 24+920 STA 26+850 STA 28+200 STA 28+900 STA 30+200 STA 30+750 STA 31+270 STA 31+540 STA 32+000 STA 32+240 STA 32+580 STA 32+900 STA 33+300 STA 33+800 STA 35+500 STA 36+920 STA 38+300 STA 40+320
11
CONSTRUCTION ACCESS & FACILITIES
3
2
4
13
Satellite Camp and other facilities
14
BENCHMARK (BM) SURVEY
1. Establish new 22 Benchmarks (BM) along road corridor – priority
area B
2. GPS SURVEY Observation for Main control
3. Loop Close Traverse from existing BM MHR to IMIP by Total Station
4. Update Drone mapping – STA 19+500 to STA 20+400
5. Update Topo Survey
STA 20+000
15
GEOTECHNICAL INVESTIGATION – BORE HOLE
16
GEOTECHNICAL INVESTIGATION
BH – Bore Hole
17