Status of Drawing review from SBDE

Mail Fwd. Status of


Sl. No. Description of Drawings Pkg. No. Review Date Age in Days Remark
date Review
SSI Rerport of Proposed ROB at Km.
1 RI-3 28-09-2023 Not Done 16-12-2023 79 Data for Dwg. Sl. No. 4
18+740
Bore log data & DPR Drawings for
Gave reply for RI-5 MNB 17+588 (48
2 the Review of Minor Bridge 2+600, RI-6 16-11-2023 Not Done 16-12-2023 30
m span) to this mail
5+858 & 8+104
Working Drawing of Major Bridge
3 RI-6 28-11-2023 Not Done 16-12-2023 18 Resent after proof checking
(CH.06+894)
4 GAD for ROB at Km. 18+740 RI-3 04-12-2023 Not Done 16-12-2023 12 Under Review
Test Pile Drawing for minor bridge
5 RI-3 06-12-2023 Not Done 16-12-2023 10 Under Review
14+390
Working Drawings for the Box
6 RI-4 15-12-2023 Not Done 16-12-2023 1 Under Review
culvert at km 4+511/ km 4+480
Bearing & Exp. Joints
7 manufacturer's design and RI-4 15-12-2023 Not Done 16-12-2023 1 Under Review
drawings.