WALKWAY
WALKWAY
WALKWAY
Purpose
This draft proposal is for construct 100mm thk RC walkway with broom finish
and is subjected to revise, amend or other alternatives and future discussion with
parties involved.
Scope Of Work
• Site clearance
• Pegging
• Excavation for site preparation
• Sub-base and crusher run base preparation
• Laying of walkway materials
Material
Method Of Construction
1) Site clearing
Prior to start any works or part of it, the area must be cleared-out of debris, dust
any other materials.
2) Pegging
To peg the necessary lay out as per drawing provided and should be approved
by the LA’ s or S.O.
3) Excavation
This shall consist of all the required excavation within the limits of the works. It
shall include the removal and proper utilization and hauling or disposal of all
excavated materials and constructing, shaping and finishing of all earthworks
over the entire extent of the works in conformity with the required lines, grades
and typical cross section. If at the time of excavation, it is not possible to place
any materials in its proper section of the permanent construction it shall be
stockpiled in approved areas for later use.
4) Sub-Base Preparation
A sub-base and crusher run base 100mm thk with proper compaction shall be
done.
5) Laying Of Walkway
All materials used in the installation is according to the relevant by-laws and
Authority and where not otherwise specified to be in accordance with the
relevant British Standards. All work will be executed using only experienced
tradesmen.
1) Programme
2) Store and storage yard
3) To comply with local authority safety regulations and requirements.
Personal protection equipment such as PPE (Helmet, Safety Shoe) and
other safety relative equipments.